The Shot The idea Arme had was to utilize a mini-directional drill and a pneumatic pipe bursting tool to install a new HDPE drain line. The BRH-Garver crew would first drill a 2 1/4-inch, 110-ft pilot bore, then run the pipe bursting tool through the pilot bore, pulling the new 8-inch HDPE. Mini-Directional Arme said, "We have been using the Grundopit on lateral sewer line replacement jobs in La Jolla [California]. I thought it would be powerful enough to complete the job, as well as small enough to overcome tight access problems. In addition, the Grundopit is trackable and offers the directional capabilities we needed." Arme was still concerned, though, about the difficult soil conditions in that area of California. Soil Conditions The mini-directional encountered 2 sections of caliche during the 110-ft bore. Arme said, "We started on the floor of the reservoir and bored down to the overflow vault. The project called for 1 1/4% grade but we figured 1% to give ourselves some breathing room.The bore was progressing quickly until we hit the first section of sediment. That slowed us down considerably." According to Arme, the first section of sediment was approximately 6-ft long. The Grundopit was able to grind through that section and another 10-ft section during the last 20 feet of the bore. The crew pumped approximately 750 gallons of a water/polymer mixture with a 500 gallon Grundomudd mixing and delivery system. Despite concerns about tracking, they were able to keep in contact with the Grundopit at depths up to 45 feet. The bore took 6 hours from start to finish. Pipe Bursting Arme said, "Initially we wanted to burst from the vault up. However, the vault was only 4 ft x 8 ft and wouldnt function as a usable launch pit. We needed to maintain grade and didnt have a host pipe to help guide us. We needed to start at a reasonable angle. So we decided to burst down to the vault." Bursting from the floor of the reservoir down to the vault also presented a challenge in the form of a 30-inch ductile iron main located just under the surface. Arme said, "We actually had to move back to the bank of the reservoir to get enough clearance to drop the Herc in at the angle we wanted. Prep work was considerable, but bursting was completed in about an hour and a half." The general contractor was extremely pleased to have the 8-inch drain line in place and is looking at using the same technique to replace other lines. Arme was impressed with the performance of both piece of trenchless equipment and anticipates more work for the mini-directional/pipe bursting trenchless team. UTILITY Contractor, July 2000 |







