Swage Lining with Static Bursting Equipment
in Berlin
Contractor Ludwig Pfeiffer Hoch-und Tiefbau
GmbH & Co.
KG was recently contracted by the Berlin Waterworks, Berlin,
Germany, to rehabilitate a sanitary sewer pressure pipe, in
the city of Berlin, using the swage line-method. The goal of
the project was to renew the ND 1000 (39-in.) steel sanitary
sewer pressure pipe a total length of approximately 600 m (2000
ft.) in order to accommodate higher pressure levels.

The swage line project took
place in Berlin, Germany. Limited working space
required a trenchless application.
|
The host pipe ran under a street
in a residential area. Numerous
restaurants and shops are located in the neighborhood, so an
open trench method would have been extremely disruptive. In
order to avoid the disruption and wide range closures, the
Berlin Waterworks intend to pull in a PE-liner in two sections
into the old pipe without any annular space using the cold
swage line application. This process is in accordance with
the local water regulations.
The Pfeiffer Company often uses
the cold swage line-method for projects like this. During
this process a PE-Inliner is pulled into the old pipe within
the diameter of the existing host pipe without the use of
any heat and in a reduced size. This way the pipes from ND
100 up to ND 1200 (4 to 50 in.) with installation lengths
of up to 1000 m (3300 ft.) can be restored utilizing this
method.
The Pfeiffer Company has a good
deal of experience with static pipe bursting, specifically
with the Grundoburst static pipe bursting system from trenchless
equipment manufacturer TT Technologies, Aurora, Ill, USA
(a subsidiary of Tracto-Technik, Lennestadt, Germany). According to TT Technologies product specialist
Collins Orton, while the Grundoburst unit is designed for static
pipe bursting, it is also very effective for other trenchless
applications. He said, “Static bursting systems
can be used for these types of applications. In essence,
the processes are very similar. In a swage line or even
a slipline situation, however, there is no need to burst the
host pipe. But each method does require the pulling in
of a new product pipe and that’s where the similarities
lie. And that’s why static bursting units can be
used in all three scenarios.”
At the jobsite in Berlin the Pfeiffer Company used the largest
static pipe bursting unit available, the Grundoburst 2500G
from TT Technologies.

The Pfeiffer Company utilized
a Grundoburst 2500G static bursting
unit to complete the
swage line. The Grundoburst unit provided the power
needed for the project and took up less space than a comparable
winch system.
|
Static Bursting & Swage
Lining
During a typical static bursting process, a hydraulically powered
bursting unit pulls specially designed bladed rollers are
pulled through an existing line. As the bladed rollers
are pulled through, they split the host pipe. An expander
attached to the rollers forces the fragmented pipe into the
surround soil while simultaneously pulling in the new pipe. For
the swage line project in Berlin, the hydraulic bursting
unit would be used to pull the swaged pipe into place. A
very large bursting unit would be needed.
Orton said, “In this particular
case the contractor chose to use the bursting unit instead
of a winch because of the space limitations of the project. The Grundoburst 2500G
provides up to 2550 kN (650,000 lbs) of pullback, enough to
meet the requirements of the cold swage line method and still
take up less space than a comparable winch system. Looking
at it logistically, it is easier to move the bursting machine
than a comparable winch.”
On The Job
The construction work in Berlin was divided into two sections. Crews
dug a launch pit near the middle of the run, creating a run
of 322 meters (1050 ft.) in on direction and a run of 216 meters
(700 ft.) in the other. After a high-pressure cleaning
process of the existing pipe, where all loose particles are
removed, a camera inspection was performed. Build up
within the pipe was removed mechanically with a scratching
tool. For swage-lining a metallic smooth surface is not
necessary, but any possible obstacles within the old pipe should
be removed.
During the swage lining process,
the oversized pipe is reduced in diameter to about 10% less
than the inside diameter of the host pipe. The swaged down
pipe is pulled in to the host pipe and allowed to return
to its original diameter. Because
the pipe cannot actually reach its original diameter, it becomes
tight against the wall of the host pipe. In this case
the new pipe was 3% bigger. As soon as the pulling force
is relieved, the pipe tries to return to its original diameter
again. But the inner diameter of the existing pipe limits
it.
According to Orton, as crews fused
together the necessary lengths of HDPE, the inner and the
outer welding beads were removed from the pipe. He said, “The exterior and
interior weld beads are removed to allow the PE pipe to pass
through the reduction die without getting stuck. Removal
of the exterior bead is done with a special skiving knife that
removes the bead in a matter of seconds. The internal bead
is removed with a tool similar to the bead trimmer commonly
found in the US. This tool reaches back into the pipe just
after the fusion weld is cooled and deploys a cutter and spacing
gauge that then are rotated from the end of the pipe. The rotation
carves the bead off. This procedure takes a few minutes per
joint.”

The existing ND 1000 (39-in.)
steel line with ND 1030 (40.5-inch) HDPE 100. During
the swage line process, the HDPE product pipe is pulled
through a reducing dye to enable it to fit inside
of the
host pipe. Once inside, the HDPE attempts to return
to
its original size forming
a tight fit within the
host
pipe.
|
A pulling head was welded to the
front the first section of pipe to be installed. Crews positioned the Grundoburst in the launch pit and rodded the first section of pipe with
the Quicklock bursting rods. Once at the launch pit,
the connection was made between the Quicklock rods and the
product pipe. Once established, crews began the swage
lining process. The static bursting unit pulled the HDPE
through the reduction tool and the swage lining die, in order
to reduce the pipe’s diameter. Crews monitored
the pulling force constantly to make sure it stayed within
the permissible limits for the PE-pipe. To keep the friction
losses as low as possible, environmental friendly anti-seize
fluids are applied. The pipe then continued on into the host
pipe until fully installed.
Once the first section was in place, the bursting unit was
rotated 180 degrees and crews set to work on the next section,
utilizing the same launch pit.
Orton said, “A strong steady pulling force is exerted
to pull the entire length of pipe to be replaced through a
reducing die setup. The die is tapered and will accept the
O.D. of the new PE pipe, it then continues through a funnel
shaped die that continues to reduce the diameter of the PE
pipe to a predetermined diameter, approximately 10 percent
smaller than the I.D. of the host pipe. The process can
be interrupted at any time, for example to butt-weld pre-fabricated
pipe lengths together. The deformation and installation speed
with this dimension is between 50 and 100 m (170 to 330 ft.)
per hour, therefore pipe lengths from 300 to 600 m (1000 to
2000 ft.) lengths can be pulled in, without any problem, in
one day’s work.”
For the project in Berlin, HDPE 100 with dimensions 1030 x
60,6 (40.5 in., SDR 17, PN 10) was chosen. Due to the large
diameter, which in a typical swage line is generally about
3 percent greater than the host pipe, a 100 percent tight and
durable fit of the PE-liner inside the old pipe is created.
After both pipe sections were successfully pulled in, pre-welded
sockets with flanges were welded to each end of each pipe length
to complete the installation. After assembly of the end flange
a pressure check was carried out, as well as a final camera
inspection.
The new PE-liner has the quality
of a new pipe after the installation and can carry all loads
from the ground and traffic, as well as the internal pressure
without effects by the old pipe. Due
to the very good hydraulic characteristics of the HDPE-pipe
further flow reduction is not expected.
Trenchless Technology
International Sept/Oct
2006 |