Assisting Directional Drilling With Pneumatic Pipe Rammingby Jim Schill Some of the most spectacular trenchless projects have been accomplished through the use of directional drilling. Drill operators and manufacturers are finding new and creative ways of tackling tough projects and difficult situations by utilizing pipe ramming technology to assist directional drills. Recently, trenchless equipment manufacturer TT Technologies, Aurora, IL introduced several pipe ramming techniques that are helping drill operators solve drilling problems and tackle tough conditions. The techniques are changing the way drillers approach projects and respond to problems on the job. Four pipe ramming techniques are being used to help prevent failed directional drilling bores and even salvage bores. Properly configured pipe rammers can be used to salvage product pipes, remove stuck drill stems and assist drills during product pullback, overcoming hydrolock. Bore Salvage
Drill Stem Recovery
Pullback Assist The pullback assist technique has been successfully used on steel pipe, as well as HDPE. The technique can be used as a safety measure in anticipation of hydrolock problems or after the pipe has become immobilized (See Figure C). Time is a key factor with any of these methods. The rate of success improves the faster problems are responded to. To improve response time, many drilling contractors are now bringing ramming equipment to directional drilling sites in order to respond quickly to problems if they develop.
Conductor Barrel™ During the Conductor Barrel process, casings are rammed into the ground, at a predetermined angle, until desirable soil conditions are met. The spoil is removed from the casing with an auger or core barrel. Drilling proceeds within the casing in the desirable soil conditions. In addition to assisting drilling operations at the start, the conductor can also serve as a friction-free section during pullback (See Figure D). In addition, the conductor barrel can prevent situations in unstable soils where drilling fluids under pressure force their way into waterways or wetlands, acting in a similar fashion to containment cells. Drilling contractors throughout North America have successfully employed all four directional assist techniques.
Case Study: Pullback Assist on Gulfstream Pipeline Project To solve the problems Laney crews combined the power of their self-manufactured LDD Series directional drill rigs with the percussive action world’s largest pipe rammer, the Grundoram Taurus from TT Technologies, Aurora, IL (part of the international group of Tracto-Technik companies). Gulfstream Project The Bayou LaBatre section called for the completion of two 4,700-ft parallel bores for the final phase of the project. The 36-inch diameter epoxy coated steel product pipe had a 1.25-inch wall thickness. The pipes needed to travel under a shipping channel in the Gulf of Mexico to a location onshore. One line would serve as the main line, the other as the supply line. The Laney crew set up on shore to drill the pilot bore out to the pre-determined spot in the Gulf of Mexico for the installation of the first pipe, the main line. The second bore would install the supply line. Over the course of several weeks the Laney crew set up, performed the necessary survey work, and completed the pilot bore and a series of backreams in preparation for pulling back the pipe. Pullback These were the challenges the Laney crew faced as they began pulling back the 4,700 feet of 36-inch diameter steel pipe. The pipe lay underwater and was hoisted to the surface, connected for pullback and then lowered back down. Pullback started slowly, but continued until approximately a third of the way through. The Laney drill rig began to reach the upper end of its pulling capabilities. The decision was made to stop the pullback and try and recover the pipe. After recovering the pipe with a cross-winch anchored off shore, the Laney crew began pullback a second time. The second pullback halted near the 4,000-ft mark. After a meeting with Gulfstream officials, it was concluded that the supply line was more important to keeping the project on schedule. So, the decision was made to begin work on installing the supply line. While the Laney crew started moving equipment into position for the second bore, TT Technologies (part of the international group of Tracto-Technik companies) was contacted and a 24-inch diameter Grundoram Taurus pneumatic pipe rammer was brought on site to assist with the project.
Pullback Assist The rammer was taken to an awaiting work-barge in the Gulf by another barge equipped with a large crane, pipe adapter and large air compressors. Once at the work-barge, the end of the product pipe was carefully lifted with the crane and rested on the surface work-barge. The end of the pipe was fitted with the specially fabricated adapter that connected to the 24-inch diameter Grundoram Taurus, completing the assembly. With the Grundoram in place, the crew pulled with the directional drill rig. The rammer was started and within a few minutes the pipe began to move. The hammer and drill rig worked in tandem until the section drill stem needed to be removed. The crew shut the rammer off, removed the 31-ft section of drill stem and started pulling again. The rammer assisted for a few more minutes, then the rig was able to complete the pullback on its own. The second bore was complete, but the first bore was still waiting, immobilized for over 21 days.
Push & Pull The crew started the drill rig and pulled back at approximately 50 percent power. Then the hammer was started and the crew let it run for a few minutes. When they believed that the energy from the rammer had moved through the pipe string, more pulling force was applied and the pipe began to move and was ultimately installed successfully. World Pipelines, April 2003 |












