NIBCO
Solutions Takes on Ductile Iron Bursting in Illinois
| 
The
NIBCO crew used a Grundoburst static bursting system
like the one pictured here. The static system has
the ability to bursting ductile iron pipe.
|
NUCA contractor
NIBCO Construction Concepts, LLC, Joliet, Ill., recently
completed a difficult static pipe bursting project in
Peru, Ill. The project was completed for petrochemical
company Huntsman Corporation and included replacing an
aging fire protection system. The project, however, could
not be completed through traditional open cut construction
methods. According to NIBCO Vice President Jay Boban,
NIBCO was chosen to perform a trenchless rehabilitation
and replacement option.
He said, “The ground at the facility was contaminated
from a structure that once existed at the site. We
were only allowed to dig in specific areas, which meant
a trenchless method would need to be used to replace
the existing ductile and cast iron fire protection
system. We decided to utilize static pipe bursting.”
NIBCO crews used the Grundoburst 1000G static pipe bursting system from Associate
NUCA member TT Technologies, Aurora, Ill.
Bursting
Ductile Iron
The
Grundoburst 1000G hydraulically operated static bursting
system is one of six Grundoburst models. The 1000G is designed
for bursting fracturable pipe, as well as ductile iron
and steel pipe up to 20-inches in diameter. According to
TT Technologies Pipe Bursting Specialist Ben Cocogliato,
several of the system’s features make bursting steel,
as well as ductile iron, possible. He said, “During
the static bursting process, a special bladed roller cutting
head is pulled through the existing line by the bursting
unit. As the bladed rollers are pulled through, they split
the host pipe. An expander attached to the rollers forces
the fragmented pipe into the surrounding soil while simultaneously
pulling in the new pipe.”
The specially designed bladed rollers are essential to the bursting process.
The blades actually split the host pipe instead of ripping or tearing it. This
makes the process very clean and prevents potential damage to the product pipe
and allows it to burst steel and ductile iron pipe.
According to Cocogliato, this is a significant advancement
in trenchless pipe replacement. He said, “I see
this technology having a great impact on the gas and
water industries. There are miles of steel and ductile
iron lines throughout North America that are undersized
and/or deteriorating and need to be replaced. Being able
to replace and upsize these lines without digging them
up, is a benefit to everyone. That really proved true
onthe job NIBCO did at Huntsman Corporation.”
The Job
The project
at Huntsman called for the replacement of approximately
3,000 linear feet of 10-inch ductile and cast iron pipe
with 16-inch SDR 9 High Density Polyethylene (HDPE). The
existing system had deteriorated past the point of functional
performance and needed to be replaced to ensure proper
fire protection at the facility.
Before beginning the project, NIBCO crews needed to attend
a special safety course because of the contaminated soil
conditions. Boban said, “Each of the participants
on the project was required to attend and successfully complete a 40-hour hazardous
waste operations course. During the project, workers were required to wear either
no-mex coveralls or tyvec type suits depending on the soil and plant conditions
we were working in. The entire project was continually monitored by an independent
testing agency. All of that made the job challenging.”
In addition to safety issues, the layout and condition
of the existing system added to the project’s complexity.
According to Boban the system contained sections of ductile
iron, as well as cast iron. However locations of specific
pipe materials were not known until they were excavated. Plus, the system contained
many repairs that also posed a challenge.
Boban said, “This project required a lot of preparation
work. We would spend a week preparing to do a 300-foot
run. We had many issues to consider. We had hydrants
and tee-connections on the existing line and other underground
utilities we needed to burst over and under on each run. That took a lot planning
to make sure we did the most efficient and effective way possible."
Results
Typical bursting
runs ranged from 100 to 400 feet in length. For the sections
of cast iron a simple bursting expander configuration was
used. Ductile iron sections required the use of the specially
designed bladed rollers. NIBCO crews dug launch and exit
pits on either side of the run. The Grundoburst was placed
in the exit pit and the QuickLock bursting rods were placed
through the existing line until they reached the launch
pit. At the launch pit the bursting head and expander,
and bladed rollers if needed, were attached to the QuickLock
rods. The new HDPE was then connected and the entire configuration
was pulled through the existing line by the hydraulic Grundoburst
unit.
Once the line was installed, NIBCO crews made all lateral and hydrant connections
then performed restoration work. NIBCO crews performed flawlessly and the project
was successfully completed. |