|
by
Jim
Johnson
|
Project
Profile:
-
Goliath
Grundocrack tool, 18-inch diameter with 37.5-inch
(OD) rear expander, and an air consumption of 1,236
cfm.
-
20-ton
dual-capstan GRUNDOWINCH constant-tension winch.
-
Upsize
3,200 feet of failing 24-inch diameter reinforced
concrete sewer pipe to 32-inch diameter HDPE pipe.
-
10
separate bursts averaging 320 feet each, with the
longest run 450 feet.
|
Anyone
who has ever traveled to Santa Fe, New Mexico, has been impressed
by its beauty. This upscale community is bursting at its seams
with new residents and thousands of tourists annually.
All
sorts of folks make their home in Santa Fe ... artists, shopkeepers,
innkeepers, musicians, mechanics, municipal workers, and more.
It is common knowledge that residents selected Santa Fe because
of the incredible landscape, pleasant climate, and the stunning
southwestern beauty of the city. But, regarding the road leading
to the town's airport, the Santa Fe Wastewater Department knew
that the community's beauty was only skin deep.
A
failing interceptor sanitary sewer line ran for thousands of
feet beneath the community's Airport Road, which also intersected
a busy state highway. The 20-year-old line was showing excessive
exfiltration. Using inspection cameras, it was immediately apparent
that the 24-inch diameter steel reinforced concrete pipe was
still
in good condition, but most of the joints had separated allowing
the exfiltration.
|

TT
Technologies Goliath Grundocrack tool laying next to one
of Triad's trucks.
|
Plus,
the failing line was constantly running near or at capacity
because of sizable population increases. Surges of rainwater
were also too much for the outdated interceptor sewer to handle
after occasional cloudbursts.
Bill
Landin of the city's wastewater staff knew he had a difficult
situation on his hands. To trench and replace the lines that
ran beneath Airport Road and the state highway would require
closing the roads. The resulting detour would take traffic as
much as 20 miles out of the way. Also, the New Mexico State
Highway Department made it clear that trenching through their
highway was unacceptable.
Because
the interceptor line was already flowing at capacity, wastewater
officials also deemed it crucial to increase the diameter of
the line. This eliminated thepossibility of using pipe lining
to seal the leaking concrete sewer pipe.
Because
the city desired a limited amount of disruption, the trenchless
method of pipe bursting was included in the bid. Landin was
already familiar with bursting from previous work experience.
To determine job specifics, he consulted with Jack Sullivan
of Sullivan Design Group. Sullivan routinely provides construction
inspection and observation for the city. Remarked Sullivan,
"The No. 1 issue was bypass pumping."
The
sewer line was the community's primary
interceptor, carrying the majority of sewage from town to the
treatment site. Officials wanted to make certain that all fail-safes
were in place for the bypass.
|

Goliath
Grundocrack tool being pulled into the
entrance pit.
|
As
an experienced trenchless construction company, Triad Builders
of New Mexico, Inc. of Albuquerque submitted a bid, prepared
under the supervision of Vice President Terry Gorsuch, to combine
pipe bursting with open cut. The company also had a creative
bypass plan. Triad was awarded the bid based in part because
of its ability to provide pneumatic pipe bursting. "With bursting,
we could offer less disruption to the public," said Tom Kryfko,
Triad project manager.
Kryfko
also said his firm has been using the pipe ramming method to
install lines throughout the southwestern United States for
several years. The trenchless method of ramming offers the same
positive social benefit as bursting: minimal surface disruption.
Triad owns a Koloss Pipe Rammer, manufactured by TT Technologies
of Aurora, IL.
Kryfko
had become familiar with pipe bursting after networking with
bursting contractors and witnessing product demonstrations at
trade shows in the early 1990s. Gorsuch, a veteran of several
years in the trenchless field, was aware that the company's
rammer could be converted into a pipe bursting tool with the
proper expander. However, Gorsuch determined that their Koloss
rammer, with a diameter of 14 inches, was undersized for the
Santa Fe Airport Road bursting project.
To
arrange for the proper bursting equipment, Gorsuch contacted
Pipe Bursting Specialist Mike Schwager at TT Technologies. After
considering the composition and diameter of the reinforced concrete
pipe, the degree of upsizing, and soil conditions, Triad management
decided to purchase a Goliath Pipe Bursting Tool to perform
the Santa Fe job.
The
Goliath tool has an 18-inch diameter and air consumption of
1,236 cfm. A 20-ton dual-capstan GRUNDOWINCH constant-tension
winch, bentonite pump, air compressor, and 37.5-inch (OD) rear
expander comprised
the rest of the trenchless system.
Wastewater
officials had determined to upsize all failing 24-inch outside
diameter pipe to 32-inch outside diameter, including
the some 3,000 feet of pipe designated
for bursting. By doing so, flow capacity would increase by at
least 80%. However, soil conditions in Santa Fe were not ideally
suited for upsizing for the bursting process.
Unlike
glacial till or loam soils, the cobble and sand mixture would
compact only minimally. A degree of soil compaction is required
when a bursting tool's expander attempts to create a larger
bore for the safe installation of larger replacement pipe.
The
replacement pipe was 32-inch outside diameter SDR 21 and SDR
26 HDPE pipe, depending on pipe depth. PE pipe's flexural qualities
and on-site fusion properties allow it to be pulled in behind
a bursting tool for one-step installations for each length burst.
Triad
determined that 7,500 feet of the failed sewer lines would be
more economically installed via trench and replace. However,
3,200 feet, which ran beneath busy Airport Road and some adjacent
landscaping, was divided into 10 separate bursts averaging 320
feet each, with the longest run established at 450 feet.
Triad
crews, under the direction of Superintendent Ron Ramsey and
Bursting Foreman Mike Carter, arrived in Santa Fe in late June
(1997) to perform the sewer-line replacements. After implementing
an incredibly effective gravity feed sewer bypass (which eliminated
the need for up to eight pumps), crews were ready to burst.
TT Technologies' Mike Schwager, Rick Melvin, and Larry Gross
served as technical advisers for the bursting portion of the
replacements. "We were concerned with the first few bursting
runs because the lines ran only a few feet below the pavement,"
Gross said.
|

TT
Technologies Goliath bursts through reinforced concrete
pipe.
|
The
first three bursts followed lines that were as shallow as 5
feet beneath the pavement. Utilizing an expander to accommodate
the new 32 inch pipe led to some mounding of the asphalt road
surface during these specific bursts.
Although
the mounding was undesirable, it was also inevitable. There
simply was not enough "loft" between the failed line
and pavement to properly accommodate the desired upsizing of
pipe, especially considering the non-compacting nature of the
soil (cobble, boulders, and sand).
Trenching
would have also required the replacement of pavement, as well
as the temporary closing of the highway. Trenching would have
also destroyed a wider path of pavement and taken longer to
accomplish compared to bursting for those first bursts.
Crews
worked from manhole to manhole, moving systematically down the
center lane of the highway. The tool was launched at an excavated
manhole, and exited at the next. Thus, each exit area then served
as the next launch site. It is important to note that throughout
the entire bursting process, two lanes of traffic remained open
for the convenience of motorists.
Unlike
clay sewer pipe, which offers little resistance to bursting,
the issue of reinforced concrete pipe needed to be uniquely
addressed. A custom 4-inch diameter shock valve was required
to supply added pneumatic force to the bursting tool. The shock
valve allows air pressure to build in the line to a desired
level, and then be released at a preset pressure to start the
large bursting tool's piston into motion. Crews experienced
some minor slowdowns when they found their initial air compressor
to be inadequate because of Santa Fe's high altitude and high
ambient summer temperatures. An additional compressor was quickly
accessed, and bursting proceeded. Although the bursts were challenging
for the crew and bursting equipment, at no time did the 20-ton
winch reach capacity.
There
were few laterals for Triad crews to contend with, allowing
the bursting to move along at a more efficient rate. Two gas
lines closely paralleled a pair of bursting runs. Crews carefully
approached these installations but quickly became aware that
the bursting process would not disrupt these sensitive utility
lines.
TT's
on-site advisers agreed that the Santa Fe bursts would be a
challenge. Said Schwager, "Considering the length of runs and
the dramatic pipe diameter upsizing combined with the difficult
soil conditions, the Triad crew did an outstanding job."
Although
there were some concerns and delays, Triad crews were able to
complete the bursting portion of the sewer replacement in just
eight weeks. "On some runs, they were bursting at a rate of
1 foot per minute," TT's Melvin said.
With
their first bursting project completed, the Triad staff had
positive things to say about the job and the equipment. Said
Kryfko, "We're very pleased with bursting."
Triad
has purchased additional equipment from TT Technologies that
can quickly convert their pneumatic pipe rammer into a bursting
tool. They feel they now have the tools to accommodate the trenchless
needs of both municipalities and fellow contractors throughout
the 17 western states. Concluded Kryfko, "There's quite a market
out there for bursting."
Trenchless Technology,
July 1995, Page 47
|