|
Pipe
bursting proves to be a perfect match for Warren, Michigan
watermain replacement and upsizing job.
|
The city of Warren, MI is like many
cities throughout the United States and Canada. For the last several
years, the city has experienced a range of problems with an outdated
and undersized water transmission system installed between 1930
and 1950. The situation is not unique. In fact, some areas are
even battling capacity issues with relatively new systems installed
or upgraded in the late 60s and early 70s.
The city of Warren was left with little
choice, the mains needed to be replaced and upsized. The city
did have a choice however, in the pipe replacement methods it
utilized to accomplish the task. By combining trenchless pipe
bursting with traditional open cut methods, the city saved time,
money and disruption.
The city of Warren is located just
north of Detroit. It is Michigans third largest city, with
a population of 144,000. Sections of the existing cast iron water
transmission system were installed as early as the 1930s and consisted
of 6-, 8-, and 12-inch (150-mm, 200-mm and 300-mm) mains with
1- and 2-inch (25-mm and 50-mm) services.
According to Warren staff engineer
ToddSchaedig, the existing system had been acting up for some
time. Schaedig said, "Over the last several years, the city
has experienced several water main breaks per year. Although PVC
and ductile iron point repairs were made, it became obvious the
system needed to be replaced."
Method of Choice
Schaedig was first exposed to pipe bursting
during a trenchless technology seminar in 1997. At that time,
the method had a firm foot hold in the sanitary and storm sewer
markets and was beginning to emerge as a viable replacement method
for potable water lines. Schaedig saw the potential of pipe bursting
and felt that it should be considered for the upcoming water project.
Troy Freed, of pipe bursting contractor
SOS Service, Brighton, MI, said, "I met with Todd several
times over the next few months to talk about pipe bursting. Our
biggest concern with the Warren project was bursting the numerous
point repairs. Having worked with pipe bursting equipment manufacturer
TT Technologies, Aurora, IL before, I knew that if any pipe bursting
tool could do the job, it was the pneumatic Grundocrack pipe bursting
system from TT." TT Technologies Pipe Bursting Specialist
Larry Gross was called in for additional technical support.
Gross said, "Troy has a good deal
of pipe bursting experience. After looking at the job, we agreed
that the point repairs could be burst with the proper tool configuration."
Schaedig was convinced pipe bursting
could be a successful replacement method for this project. The
city gave the go ahead to designate the job as a pipe bursting
project. It would be the largest and the first of its kind in
the State of Michigan.
By the Numbers
The project called for pipe bursting
over 6,800 lf (2072 m) of 6-inch (150-mm) cast iron watermain
and upsizing to 8-inch (200-mm) potable water HDPE. In addition,
over 1,280 lf (390 m) of 12-inch (300-mm) cast iron needed to
be burst and replaced with 12-inch (300-mm) HDPE. Much of the
bursting took place under heavily traveled areas including the
seven lane State Highway 53, known as Van Dyke Avenue.
The section of Van Dyke over the 6-inch
(150-mm) watermain saw approximately 49,000 cars per day on average.
The section over the 12-inch main saw over 70,000 cars per day.
Existing mains also ran under sidewalks and adjacent to commercial
buildings. In these areas pipe bursting would prove most valuable.
In addition to bursting, several small areas
were open cut, including the removal and replacement of (41) 8-inch
diameter (200-mm) and (2) 12-inch (300-mm) diameter gate valves
and wells. The vast majority of the project, however, was completed
through pipe bursting.
Tool Configuration
The project was awarded to SOS Services last
May and work began in early June. The SOS crew used a TT Technologies
8.5-inch (215- mm) diameter Grundocrack Hercules pneumatic pipe
bursting system, equipped with a 10-inch (250-mm) rear expander,
for the 6- inch (150-mm) mains and a 12-inch (300-mm) diameter
Grundocrack Gigant with a 15-inch (380-mm) rear expander for the
12-inch (300-mm) mains. A 10-ton Grundowinch was used to guide
the bursting tool through the host pipe.
According to Gross, the Grundowinch played
a key role. Gross said, "The Grundowinch provides constant
tension at variable speeds. That was especially important for
this project because of the point repairs. When the bursting tool
reaches a repair it slows down as it works its way through. After
the repair is burst, there is less resistance and the tool speeds
up quickly. The Grundowinch compensates for this change in speed
and prevents slack from developing in the line."
|
Over
6,800 If of 6-inch cast iron watermain was replaced
using the Grundocrack pipe brusting system with minimal
surface disruption.
|
Also essential to the success of the
job was the use of a guide head or "schnozz". The guide
head or "schnozz" is attached to the front of the pipe
bursting tool and adds needed tool length. It allows the tool to
get into the pipe and break it at its weakest point, the inside.
Cast iron pipe tends to break several
feet in front of a standard pipe bursting tool. This causes the
potential for two major problems. First, the shards of cast iron
pipe are sharp and can actually cut winch lines. Second, pipe fragments
can build up making the host pipe impassable. This can cause the
tool to change direction and veer off course.
Besides adding tool length, the guide
head helps protect the winch line. In many configurations, the winch
line is connected to the front of the guide head instead of the
front of the tool. This keeps the line ahead of the actually bursting
and out of the way of shards of pipe.
Gross said, "Cutting blades can
be used in conjunction with a guide head. The blades are welded
directly to the guide head. The blades focus the percussive action
of the tool and greatly enhance overall bursting power, allowing
the tool to successfully burst difficult host pipes, like cast iron
as well as many point repairs like PVC."
Too Close for Comfort
If there was ever a perfect application for
a particular job, pipe bursting was for the city of Warren project.
The watermain that was replaced was surrounded by potential hazards.
A 9-way Ameritech conduit bank containing
fiber optic cable ran parallel to the watermain, just to the west,
under a sidewalk. To the east, a large 24-inch (610-mm) diameter
water transmission line bordered the watermain.
Moving the main further to the west,
under the sidewalk, was ruled out. According to the city engineering
staff, previous excavations showed many basements and footings
extending into the right-of- way under the sidewalk. If a break
should occur in the future, there would be a greater potential
for basement and building flooding.
Moving the main to the east, directly
under Van Dyke, was also ruled out several reasons. First was
expense. The open cut/pavement replacement expense would have
been extraordinary, in addition to possible expense for any future
work that needed to be done. Second, the amount of traffic disruption
precluded this option. The Michigan Department of Transportation
would not allow more than one lane of Van Dyke to be shut down
for any extended period of time.
That left two options: open cut and
replace or pipe bursting. Pipe burstings low profile made
it the method of choice. Bursting would not interfere with the
Ameritech conduits or the 24-inch (610-mm) water transmission
main and work could be confined to a single lane of traffic. The
city would also see a dramatic reduction in amount of, and costs
associated with, pavement replacement versus an open cut application.
According to Schaedig, another benefit
to utilizing pipe bursting was the new product pipe, high density
polyethylene pipe (HDPE). He said, "The citys clay
soils conduct stray electrical currents. The old cast iron mains
act as sacrificial anodes and corrode from the outside in. For
the last six years, the solution has been to use ductile iron
watermains with a polyethylene wrap. However, the city believed
the wrap would cause difficulty in locating watermain breaks.
A new watermain constructed of HDPE solved the installation problems
and provided protection against the stray electrical currents."
The Job
Burst lengths averaged one city block,
approximately 270 feet (82 m). Depending on repairs encountered,
bursting times averaged 20 minutes to one hour. Both the Hercules
and Gigant bursting tools were able to overcome a multitude of
point repairs, due in large part to the "schnozz" technology.
Freed said, "Construction proceeded
steadily. We initially anticipated the project to wrap up in May
of 2000, but everything went so smoothly, in addition to a mild
November, that we were able to finish months ahead of time."
Schaedig said, "Although work
progressed at a rate comparable to open cut, disruption to the
100 or so businesses was minimal. Driveways were kept open, water
users on Van Dyke were only out of water for a few minutes while
being transferred on or off the temporary bypass and many side
streets were open to traffic during construction."
Reaction
The Warren, Michigan pipe bursting
project generated a tremendous amount of interest. It was the
first and, to this date, the largest watermain pipe bursting job
ever in the state. In October of 99, during the final stages
of the job, the city invited representatives from other cities
and engineering firms to a demonstration of the method.
Schaedig said, "The bursting and
fusion demos went extremely well. 60 engineers and public officials
from throughout southern Michigan attended the event. They all
seemed genuinely interested in applying what they had seen in
Warren, on projects of their own. I can safely say that there
will be a lot more bursting going on in the state of Michigan
in the future."
Trenchless Today, March
2000, Page 2
|