|

The
project at McGuire Air Force Base called for bursting
over 8,250 liner feet of 3-inch through 12-inch asbestos
cement pipe and replacing it with High Density Polyethylene
(HDPE) pipe. Spiniello Companies utilized the Grundoburst
800G static pipe bursting system from TT Technologies,
Aurora, Ill.
|
Infrastructure
deterioration is hard to escape. Many cities around the
country are scrambling to repair, replace or rehabilitate
dilapidated water and sewer systems. But the problem
is not exclusive. Infrastructure deterioration is occurring
in buildings, businesses, schools, universities, and
even to the United States Armed Forces.
Spiniello Companies, Fairfield, NJ, was recently awarded a project to help McGuire
Air Force Base New Jersey overcome problems with its potable water system. But
while the Air Force is steeped in tradition, it is also a proponent of new technology.
Traditional open cut construction was not an option on this project. The much
stealthier trenchless pipe bursting method was specified.
Spiniello Chief Engineer Joe Dioslaki said, “We actually bid the project
without a design or plans, site unseen. But the reason it was done that way was
because time was of the essence. They needed these repairs done right away. So
we approached it as a design/build in a sense. They needed a contractor to come
in, layout the bypass system and build the project as it was being planned. And
that’s what we did.”
To burst and replace the over 8,000 linear feet of 3-inch through 12-inch asbestos
cement water main, Dioslaki chose the Grundoburst 800G static pipe bursting system
from trenchless equipment manufacturer TT Technologies, Aurora, Ill.
|

The
trenchless pipe bursting method was specified for
the project at McGuire Air Force Base. Because
the process is trenchless, disruption is kept to
a minimum. Everyone involved with the project was
pleased with the results.
|
Base Background
The
history of McGuire Air Force base goes back to World War
One and the beginnings of Fort Dix. According to a brief
history of the base available through the McGuire Air Force
Base public affairs office, Camp Dix, as it was called
back then, was a key mobilization training base during
WWI and remained viable after the war. It featured a single
airstrip cut into the surrounding pastureland. That changed
during the years leading up to World War II when the base
saw additional concrete airstrips and a re-designation
as Fort Dix Army Airfield.
By the end of the WWII air operations ended at the base, but it was soon reopened
in 1948 at the onset of the Cold War and rededicated as McGuire Air Force. Since
that time, McGuire Air Force Base and Team McGuire, as they are known, have participated
to some degree in almost every major military action since 1948.
But while the base has grown in operations and importance over the years, its
water systems have slowly deteriorated. After a series of main breaks it was
decided the system needed to be replaced. With a majority of the system being
asbestos cement pipe it was hoped that open cutting and removing the pipe could
be avoided. The project was ultimately specified as pipe bursting only and Spiniello
Companies was brought in to tackle the project.
|

The
existing asbestos cement water system at McGuire
Air Force base was deteriorating. Several main
breaks had prompted the replacement on much of
the system.
|
Contractor
Background
Spiniello Companies also has a rich background. The company
was established in 1922 and soon became recognized as a
leader in utility and heavy construction in New Jersey
and several other states. Today, Spiniello Companies has
over 50 years of experience in pipeline rehabilitation
and over 80 years of experience in heavy construction.
Throughout its history the company has welcomed new technology
and benefited tremendously from this attitude.
Spiniello completed its first cement mortar lining in 1946 and since then they
have rehabilitated over 14 million feet of pipe through that method. The company
is also well known for its cured-in-place and sliplining skills. The project
at McGuire gave the highly skilled contractor the opportunity to expand its experience
with pipe bursting.
Dioslaki said, “We have done several pipe bursting projects in the past,
but this was really the first large-scale water bursting project we’ve
had the opportunity to perform. It provided us the chance to really become proficient
with the static pipe bursting method.”
|

In
addition to fracturable pipes, the static Grundoburst
is able to burst ductile iron and steel pipe and
repairs. Until recently this was a major limitation
of pipe bursting equipment. The systems bladed
roller cutting blades are key to this clean pipe
slitting process.
|
Static Pipe Bursting
According
to TT Technologies pipe bursting specialist Ben Cocogliato,
static pipe bursting is gaining popularity with contractors
because of its capabilities. With the recent introduction
of new hydraulically powered static pipe bursting systems,
contractors now have the ability to not only burst and
replace fracturable pipes but also ductile iron, steel
and lined pipes, as well as pipes with ductile iron and
steel repairs.
During the static bursting process, the Grundoburst’s
specially designed bladed rollers are pulled through
an existing line by a hydraulically powered bursting
unit. As the bladed rollers are pulled through, they
split the host pipe. An expander attached to the rollers
forces the fragmented pipe into the surrounding soil
while simultaneously pulling in the new pipe, typically
High Density Polyethylene (HDPE).
Cocogliato said, “The bladed roller configuration is an essential part
of the Grundoburst’s success. The specially designed bladed rollers actually
split the host pipe instead of ripping or tearing it. This is a clean process
and prevents potential damage to the product pipe.
“Patented Quicklock bursting rods are linked together not screwed together
like traditional drill stems or other static systems. This system speeds the
installation process as well as the breakdown procedure. The rods can be quickly
removed one at a time at the exit pit as bursting is in operation. And while
HDPE is commonly used, new techniques and technologies are allowing contractors
a choice when it comes to product pipe. Other pipe materials that can be installed
through static bursting include ductile iron, PVC, specially designed clay
and even steel.”
Bursting Basics
The
project at McGuire Air Force Base required Spiniello
crews to burst and replace over 8,250 linear feet of
3-inch through 12-inch asbestos cement water main.
In order to facilitate the bursting of the water mains,
the Spiniello crew established an intricate bypass
system. The yearlong project began in the winter and
Dioslaki said maintaining the bypass was no small task.
He said, “We
had installed a temporary, above ground bypass with a
restrained joint PVC pressure pipe system. The bypass
served all of the buildings on the network that we were
bursting. It was challenging because we had to keep that
bypass running through an extremely cold winter and make
sure it didn’t freeze. We made sure to keep the
water moving and incorporated several flush points.
Other areas we insulated with hay.”
Typical launch and exit pits were 20 feet long and
6 feet wide. Excavation was kept down to an absolute
minimum. Dioslaki said, “This is an Air Force
base, you can’t have excavated materials and pipe lying around. It’s
not conducive with the activities at an Air Force base. It has to be clean. And
that’s what pipe bursting was able to do. Keep disruption down.”
Most of the bursting done for the project was size-to-size replacement. For one
of the final sections, the Spiniello crew burst and replaced 8-inch asbestos
cement pipe with 12-inch HDPE. According to Dioslaki many runs were challenging.
Crews encountered numerous steel couplings and repair clamps throughout bursting
operations. Runs averaged 200 feet in length with the longest being 400 feet.
Bursting times averaged two hours per run.
|

Static
Pipe Bursting
Step 1
The Quicklock bursting rods were installed through the host pipe, to
the launch pit. A flexible guide rod helps ensure smooth installation
through the host pipe.
Step 2
Once the bursting rods were installed through the host pipe, the Spiniello
crewmembers attached the bladed cutting wheels, bursting head, expander
and new HDPE.
Step 3
The entire configuration was then pulled back by the hydraulically powered
Grundoburst through the host pipe. The bladed rollers split the host
pipe. The bursting head and expander displaced the fragmented host pipe
into the surrounding soil while the new HDPE is pulled in simultaneously.
|
On The Job
On
a typical run, the Spiniello crew began by digging a
launch pit at one end of the line being replaced, and
an exit pit at the other end. The bursting unit was positioned
in the exit pit and connected to a hydraulic power pack.
Then crews began inserting the locking bursting rods
through the existing asbestos cement main and into the
launch pit.
Once at the launch pit, the Spiniello crew attached the bladed cutting wheels,
bursting head, expander and new HDPE. The entire configuration was then pulled
back through the host pipe by the hydraulic bursting unit. The existing asbestos
cement main was effectively burst and the new HDPE was installed without incident.
Once bursting was complete, the Spiniello crews went to work chlorinating and
pressure testing the new lines and preparing them for service.
A Smooth
Transition
According
to Dioslaki the crews adapted quickly to the static bursting
technique. He said, “Right now they think it’s
great, but in the beginning they were a little apprehensive.
It’s a new technology for them. A lot of the work our
crews do is rehabilitation of the existing main and I think
some of the older-time folks thought it was going to compete
with the cement mortar lining; which they love. But when
they started doing the static bursting they realized that
this has its own market. And it was really another tool in
the tool box.”
Dioslaki also pointed out the crews found that the methods
have a lot in common. He said, “You have to do all of the same preparation work, the excavation,
temporary bypass, replacing valves, replacing hydrants and so on. When you go
to do the lining, you’re pulling cleaning tools through the existing pipe.
When your bursting, you’re pulling an expander, cutting blades and the
new pipe. There are a lot of similarities and the crews are very efficient at
this type of work. It’s what they are good at so it was a very smooth transition.”
Dioslaki anticipates more water main bursting work in the future as well as a
second year of work at McGuire Air Force Base.
|