|
Many utilities around the country
are so invested in certain pipe materials that when pipeline
replacement projects come up, it is very difficult for
those entities to consider other piping materials. Others are simply looking
for choice. For many years, this has been a core
issue with pipe bursting technology that has been closely
tied to high density polyethylene pipe (HDPE). While there
is a high level of familiarity with the application of
HDPE pipe in pipe bursting, there is still considerable
interest in other pipe material options, by owners, engineers
and contractors.
Various pipe manufacturers are
working diligently with pipe bursting equipment developers and manufacturers
to find real world ways to adapt their pipe products to
pipe bursting installations. It takes the extensive
experience of these parties to find suitable ways to install
what is best described as sectional, gasketed pipe in the
pipe bursting process. There are many factors to
consider in what is necessary for these pipe materials
to work in pipe bursting applications.

Static bursting allows for
the use of several different product pipes including
the restrained joint PVC pipe that was used for the
South Tahoe Public Utilities District.
|
In addition to the product pipe
issue, for many years bursting and replacing steel pipe
was not possible. When
static bursting equipment was introduced to the North American
market several years ago that changed. Numerous static
bursting projects with steel host pipes have been successfully
completed since then.
The project for the South Tahoe
Public Utility District (STPUD) required bursting and
replacing a steel water main with a C900 restrained joint
PVC. Pacific Liners,
Vacaville, CA, was contracted to complete the project. Sean
McIntyre, Pacific Liners Project Manager said, “Pacific
Liners has many years and thousands of feet of experience
with pipe bursting, but STPUD’s water main project
was a challenge. We have always been interested in
projects that demand creativity
and ingenuity to get the
job done, and our experienced crew
led by foreman Tom Hall
made this particular project run exactly to plan.”
A Grundoburst
1000G static pipe
bursting system from trenchless equipment manufacturer
TT Technologies, Aurora, Ill., was selected for the project. According to TT Technologies
Pipe Bursting Specialist Collins Orton, bursting steel
as well as ductile iron is a significant advancement in
trenchless pipe replacement. He said, “I see
this technology having a great impact on the gas and water
industries. There are miles of steel and ductile
iron lines throughout North America that are undersized
and/or deteriorating and need to be replaced. Some
are even required by legislation to be replaced. Being
able to replace and upsize these lines without digging
them up is a benefit to everyone. And now, with the
ability to utilize various product pipe materials with
the static pipe bursting application, the process is even
more valuable to utilities, contractors and engineers.”
According to the utility’s Web site, STPUD has been
providing water and sewer services to the residents of
South Lake Tahoe since 1950. It is a two-time recipient
of the U.S. Environmental Protection Agency’s Waste
Water Treatment Plant of the Year award.
The district’s water system consists of over 14,000
residential connections and over 660 commercial and government
sites. These customers are served from 13 active
well locations. The collection system consists of
420 miles of sewer lines, 39 lift stations and over 17,000
connections. The district also boasts one of the
first tertiary water reclamation plants, established in
1965.

The Grundoburst static
bursting system utilizes Quicklock bursting rods
that securely link together. This greatly
reduces installation times compared to standard
screw-type bursting rods.
|
During the static bursting process,
specially designed bladed rollers are pulled through
an existing line by a hydraulically powered bursting
unit. As the bladed
rollers are pulled through, they split the host pipe. An
expander attached to the rollers forces the fragmented
pipe into the surrounding soil while simultaneously pulling
in the new pipe.
The bladed roller configuration
is an essential part of static bursting success for steel
and ductile iron pipe materials. The specially designed bladed rollers
actually split the host pipe instead of ripping or tearing
it. This is a clean process and prevents potential
damage to the product pipe.
Orton said, “The old pipe must
be fractured or split, the remaining fragments compacted
in to the surrounding backfill, and the new pipe pulled/pushed
in before the temporary annular space, created by the pipe
bursting tool, begins to collapse and get a firm grip on
the new pipe. Once
the soil has a firm grip on the pipe, it is very difficult
if not all but impossible to continue to move the column
of new pipe forward. In this case, the existing steel
pipe is split at the invert then expanded to make room
for the new pipe and pipe couplings. Ultimately the
split pipe acts like a shroud over the new replacement
pipe.”

After positioning the
Grundoburst
1000G in the exit and placing the
bursting rods in the existing steel water main,
bursting was ready to begin.
|
Restrained Joint C-900 PVC Pipe
C-900 PVC pipe with a restrained joint utilizes a spline
and groove assembly that is very strong. This pipe
is assembled and pulled much the same as restrained joint
ductile iron pipe. The bell and spigot restrained joint
configuration requires that the pipe be pulled backwards
(spigot end first). This allows each consecutive
bell joint to act like an additional pipe bursting expander.
The pipe is assembled one joint at a time in the launching
pit and pulled one joint at a time. The joints are made
up quite quickly, usually in just a couple of minutes.
Only static pipe bursting systems
should be used due to the stiffness of the pipe. The connection of the
PVC pipe to the bursting head consists of an adapter using
the pipe and a steel pulling head of the same configuration
as the pipe joint. The cartridge loading method can
be used.
Orton said, “The advantage of
this cartridge loading approach is there is no need for
a pipe staging area. The
new replacement pipe can be unloaded, as needed, from a
truck and at the end of the day there is no pipe left on
site. This process requires the pipe bursting system
to start and stop repeatedly. Each joint is made-up in
the launch pit, pulled in and then the stopped while the
next section of pipe is lowered into the launch pit and
assembled to the previous joint. However, this type
of pipe appears to be flexible enough to join together
before a pipe burst and inserted through the launch pit
with minimum bending. Of course the launch pit would
need to be of adequate length to accommodate this approach
successfully.”

Pacific Liners was
contracted to replace a 10-inch diameter 350-foot
steel water main with 10-inch PVC through static
pipe bursting. The trenchless application
was chosen because the water main ran underneath
a decorative garden.
|
For the project in South Lake
Tahoe, the Pacific Liners crew needed to replace a 10.00-inch
OD, 10-gauge (0.1406-inch thickness) steel water main
with 10-inch (11.10-inch OD) restrained joint C-900 PVC
pipe. The existing 350-foot
steel water main was being replaced as part of a larger
water main rehabilitation project. Because the line
ran through a decorative garden area, open cutting was
not an option. Pipe bursting was the method of choice
for this particular project.
McIntyre said, “Pacific Liners showed up on site
on a Monday and set up the 1000G bursting unit. The
following day the line was CCTV'd to find out if there
were any bends in the line that would prevent the bursting
rods from making it through the pipe. We found that
there was a 45-degree bend located approximately six feet
from the already prepared launch pit. The launch
pit was extended an additional six feet, the elbow was
removed and the rods were then pushed through the pipe.”
A 4-foot by 25-foot launch pit
was dug at the beginning of the run and another 8-foot
by 20-foot exit pit 350 feet away. The bursting
unit was positioned in the exit pit and connected to
a hydraulic power pack. The
crew then began inserting the QuickLock® bursting rods through
the host pipe and into the launch pit. A flexible
guide rod attached to the front of the first rod was used
to help ensure the smooth installation of Quicklock rods.

During the static bursting
process, specially designed bladed rollers are
pulled through the host pipe. The bladed roller
configuration is essential to the success of the process
and also makes replacing ductile iron and steel pipe
possible as well.
|
McIntyre said, “The rods went
through with such ease that we decided to proceed with
the burst that same day. Three and a half hours later
the ten-gauge steel was replaced with C-900 PVC without
disrupting the decorative garden.”
According to Orton, several
considerations need to be addressed when choosing various
pipe materials with static bursting. He said, “The
specified pipe and specific pipe bursting equipment should
have a proven history similar with the intended application
and service environment, as well as data that reflects
third-party testing, to substantiate suitability of the
pipe by physical property and chemical resistance claims
of the manufacturer. The pipe bursting
equipment system(s) to be used should be proven to be capable
of the required pipe replacement. The structural
condition of the existing pipe also needs to be evaluated
and point repairs identified. CCTV is a very useful
tool in identifying many pipe defects.
Also, when evaluating a bursting
project, it’s important
to recognize that, in this case, the three-and-a-half hours
includes pipe joining time. In the cartridge loading
process you need to stage the pipe sections at the launch
pit. Each individual section of pipe is brought into
the launch pit and then the sections are joined and the
spline assembled to form the completed restrained joint.”
McIntyre said, “Pacific Liners
has used the Certa-Lok restrained joint C-900 PVC product
from CertainTeed in the past on sewer bypass projects. This
was the first time that we had the opportunity to use it
for pipe busting and we would have no issue with using
it again. Once
we
found our rhythm of fitting the pipe the installation
moved quite rapidly. The pipe proved to be a
very robust
product that withstood a substantial amount of pressure
and came out perfect on the post CCTV inspection.”
|