|
by Jim Schill
|

The 250-ft
casing installation took place under one of only two roads
leading to the Los Alamos National Laboratory. Traffic disruption
was avoided through the use of trenchless pipe ramming.
|
The Cerro Grande fire ravaged the Los Alamos,
New Mexico landscape in May of 2000. In addition to threatening
the world famous Los Alamos National Laboratory, the firestorm consumed
over 47,650 acres of forest and left over 400 families homeless.
Almost as soon as the fire was contained a new threat aroseflooding.
The massive fire left the mountainous region
vulnerable to excessive water run-off. The threat of massive summer
flooding prompted the Los Alamos National Laboratory and local communities
to take steps to help mitigate the potential disaster. New drainage
pipes had to be installed to help route the expected run-off.
The first project called for the installation
of a 250-foot, 36-inch steel drainage casing under a roadway near
the lab. The areas sediment rich soil was not going to make
the job easy. Boring contractor DH Underground, Albuquerque, NM,
was contracted for the project. To perform the work DH Underground
partners John Theiler and Mark DeVaney ultimately chose the Grundoram Pipe Ramming System from trenchless equipment manufacturer TT Technologies,
Aurora, IL.
Theiler said, "We anticipated a simple
trenchless auger boring project, but plans changed dramatically
once we encountered the soil conditions. We decided on pneumatic
pipe ramming instead, another trenchless casing installation method
that would allow us to place the drainage pipe without open cutting
the road." The road was one of only two roads that traveled
to and from the National Laboratory.
Fire and Water
Ironically, the Cerro Grande fire was a result
of a controlled burn designed to help prevent just such an incident.
While the Laboratory basically escaped unscathed, the areas
watershed and natural erosion controls were not as lucky. The firestorm
destroyed thousands of acres of forest. The underbrush in that forest
slows water run-off.
In addition, the intense heat of the fire transformed
the soil. The charred soil became unable to readily absorb water.
For an area that averages over 8 1/2 inches of rain from July through
September, these conditions signaled potential disaster.
Efforts to reduce the impact of potential flooding
began almost immediately. US Forest service workers cut down charred
trees to help divert run-off. Prison inmates were used to till the
scorched soil and volunteers planted rye, barley and other vegetation
to help soak up rainwater and begin the restoration process.
The National Laboratory took steps as well,
identifying drainage routes and contracting to have drainage casings
installed and replaced. Theiler said, "After the fire, local
representatives sought out roadways that experienced excessive water
run-off and designated them for drainage casings. Our particular
job took place under a roadway just a few blocks from National Laboratory
and about a mile and a half from the fire itself. When installed,
the new casing would channel the water under the road and on its
way down the mountain."
Change of Plans
According to Theiler the 250-foot installation
was intended to be an easy auger bore through drillable volcanic
ash type soil. After digging a test hole it became apparent that
auger boring was not going to work. Theiler said, "We could
barely dig through the ground with a 90,000-lb. track-hoe. The soil
was a densely compacted cobble conglomerate with large boulders,
some as large as 24 inches in diameter. We found that out later."
The original project specification called for
250 feet of 36-inch .375-inch wall casing. When it became apparent
that augering wasnt going to work, Theiler and DeVaney decided
to try pipe ramming instead. He turned to TT Technologies Pipe Ramming
Specialist Rick Melvin for technical support and put in a change
order for a thicker walled casing to accommodate pipe ramming.
Ramming Basics & Benefits
Trenchless pipe installation through ramming
is simple; a pneumatic hammer is attached to the rear of the casing
or pipe. The ramming tool, which is basically an encased piston,
drives the pipe through the ground with repeated percussive blows.
A cutting shoe is often welded to the front
of the lead casing to help reduce friction and cut through the soil.
Bentonite or polymer lubrication can also be used to help reduce
friction during ramming operations.
|

Typical
pipe ram set up. For the Los Alamos job, the DH Underground
crew was able to install 250 feet of 36-inch casing through
extremely challenging soil conditions using an 18-inch diameter
pneumatic Grundoram Goliath pipe ramming tool.
|
According to Melvin, several options are available
for ramming various lengths of pipe. He said, "An entire length
of pipe can be installed at once or, for longer runs, one section
at a time can be installed. In that case the ramming tool is removed
after each section is in place and a new section is welded on to
the end of the newly installed section. The ramming tool is connected
to the new section and ramming continues. Depending on the size
of the installation, spoil from inside the casing can be removed
with compressed air, water, an augering system or with a mini backhoe."
Some casing installation methods are impaired
or even rendered inoperable by rock or boulder filled soils. Pipe
ramming is different. During pipe ramming, boulders and rocks as
large as the casing itself can be "swallowed up" as the
casing moves through the soil and can be removed after the installation
is complete.
Ramming tools are capable of installing 4-
through 80-inch diameter pipe and steel casings. Diameters up to
148 inches have been successfully installed using large scale ramming
equipment. Ramming requires minimal working depths and is proven
effective for horizontal, vertical, and angled applications. Ramming
is also ideal for installations under roads and rail lines because
it displaces the soil without creating voids or slumps.
The conditions at Los Alamos would put the
pipe ramming method to the test.
Prep Work
Over the 250-foot run, the DH Underground crew
needed to maintain a 0.01/10 lf grade and line. The crew dug a 60-ft
long launch pit to accommodate the ramming equipment and the 40-ft
long sections of casing. Theiler said, "After the pit was dug,
we moved the first casing section into position. We checked line
and grade using surveyors equipment and water levels."
Once the casing was in position, the DH crew began assembling the
ramming gear to connect the 18-inch diameter Grundoram Goliath pipe
ramming tool with the 36-inch diameter casing.
The Grundoram Goliath weighs approximately
5,400 lbs. and operates at 1,236 cfm. At full force, the Goliaths
piston moves at 180 strokes per minute. A pneumatically powered
adjustable bearing stand was used to raise the tool to the required
height for ramming.
In order to connect the ramming tool with the
casing, a series of tapered and segmented cones are used. The configuration
for the Los Alamos lab included a segmented ram cone as well as
a soil removal cone.
Melvin explained, "When assembled, the
segmented ram cone reduces the overall diameter from 36 inches to
approximately 24 inches. The soil removal cone is then added and
further reduces the diameter to approximately 18 inches. At this
point, the tool is connected, friction fit, to the soil removal
cone completing the assembly."
|

Casings
from 4 through 80 inches are regularly installed through pipe
ramming. Casings as large as 138 inches have been installed
through pneumatic pipe ramming.
|
Pipe Ramming Prowess
Once the connection between tool and casing
was complete, the crew was ready to begin ramming. Theiler said,
"We encountered some giant boulders about 60 feet into the
run, which had to be removed before ramming really got under way.
After they were out of the way, the first sections of casing went
in at an incredible rate. We welded the next section on and continued
without a problem. We were able to swallow up all the remaining
boulders in our path."
The DH crew pumped approximately 100 gallons
of bentonite and water per 40-foot casing section. Once a section
was installed, welds between casings took anywhere from 3 1/2 to
4 hours to complete. Ramming times averaged 1 foot every seven minutes
in the beginning of the run and slowed to 1 foot every 20 minutes
at the end of the run.
Once the 250-foot casing was in place, the
DH crew began removing the spoil with its auger system. Theiler
said, "We went in there with a lead auger of 24 inches and
removed as much as we could. After that, we went in with a 30-inch
and removed more. Then we finished up with our 36-inch auger."
Overall, Theiler was impressed by the equipment
performance. He said, "It was unreal. We could barely dig through
the ground with our track-hoe. These were some incredibly difficult
soil conditions. We were extremely pleased when the last section
of pipe was in the ground." Theiler anticipates more pipe ramming
work in the Los Alamos area. He is also making plans for a 72-inch
ram later this spring.
Water Engineering
& Management, March 2001, Pages 13-17
|