|
Roll and lock. For any contractor
that performs horizontal drilling, it's the last thing they
want to happen.
When loose rock or gravel rolls into
the cavity during directional drilling, its spells disaster.
The gravel can lock into place around the drill, preventing
the tool from moving forward or backward. That means a loss
of time and the need to abandon equipment, which can cost thousands
of dollars.
To avoid roll and rock, brothers
Don and Ken Shipalesky of D&K Horizontal Drilling, Spruce
Grove, Alberta, Canada, decided to incorporate a pipe ramming
tool when performing directional drilling bores in rock soils.
Their idea was to drive a casing,
at a predetermined angle, through gravel-ridden earth until
it reach a stable soil. This provides a "guaranteed hole,"
a bore that will not fill-in or erode.
With years of experience in directional
drilling as an equipment distributor, Ski Craigmile worked with
the Shipalesky brothers to develop this unique combination of
trenchless tools. Craigmile is now a representative for TT Technologies
Inc., Aurora, IL.
Recognizing this as a new application
for pipe ramming, the three men came up with the term "conductor
barrel."
"Today's drilling rigs can have a
hard time with gravel," stated Craigmile. He indicated that
conductor barrels are not only important for the initial bore,
but also during pull-back.
The
Job
After performing a half dozen bores
of this nature, D&K was now asked to perform a single, 4,500
foot, 22-inch diameter bore beneath a rive in a northeast corner
of British Columbia for a large petroleum company. "We worked
for them before We had to bid, but other bidders weren't capable
of performing the bore," stated Don Shipalesky. Not only would
this be one of the largest bores for multiple lines attempted
in North America, but the elements were also against them.
The bore was performed in the dead
of winter, with an average daily temperature of minus 31 degree
Fahrenheit. Plus, the amount of available daylight was limited
from 9 a.m. to around 4 p.m. each day. These two factors severely
limited the amount of ramming that could be accomplished each
day.
To obtain the desired depth of 76
feet, the crew would need to ram a total of 330 feet (at 15
degrees) of pipe into the frozen ground. Craigmile was onsite
for the ramming portion of the job, bringing a Grundoram Koloss
rammer, which had a diameter of 14-inches and air consumption
of 700 cfm.
The Koloss was positioned to perform
the installation of casings at a 15 degree angle to accommodate
the directional drilling rig. The 60-foot pipe sections had
an outside diameter of 24-inches. Attached to the front of the
first casing was a "cutting shoe," which facilitated slicing
through the difficult soil.
After each section of pipe was rammed
into the soil, the Koloss tool was lifted out of the way for
the positioning of the next length of casing. This new pipe
was then welded to the back of the installed pipe. "The first
three joints went in with no trouble at all. Ramming times were
approximately 12 to 16 inches per minute," offered Craigmile.
About halfway into the installation,
the rammer was again removed. But this time, it was to allow
crews to clean spoils from inside the conductor barrel with
an auger. This was done to check the grade of the bore. Using
a computerized level to check the grade, Craigmile found that
they were right on track. Based on this information, he decided
to continue the bore without the need to stop again to check
grade.
The pipe ramming proceeded until
the front pipe had penetrated the soft shale beneath the gravel.
Once in the shale, the directional drill would be able to make
a "clean start," allowing it to travel beneath the river and
exit on the other side.
At 331 feet, the ramming was complete
and the Koloss was removed. The auger was used again to
remove the earth from inside the conductor barrel. The entire
ramming process was completed in six days. In normal conditions,
this amount of pipe installation would take hours instead
of days. But the incredible cold kept all movement at a
snail's pace.
In fact, the constant, brutal cold
affected all aspects of the job. "We had some freezing problems,"
said Shipalesky. Fuel tanks had to be carefully monitored
to prevent gelling of the diesel fuel. A special additive
was regularly added to keep the fuel fluid. Crews were also
careful not to expose skin to the air, because frostbite
could occur in just seconds.
Successful
Completion
The ramming was now accomplished.
D&K now had their "guaranteed hole," and were ready to complete
the installation.
Because the conductor barrel was
extremely secure in the soil, no directional drilling anchors
were needed. Two ears were welded onto the exposed conductor
barrel, which allowed the attached directional drilling machine
to push the full 160,000 pounds without moving. An American
Augers DD-160 was used to make the bore.
Using a 9 7/8-inch bit, Don Shipalesky
guided his directional drilling tool down the conductor pipe
to the shale. There, Shipalesky proceeded horizontally beneath
the frozen river, drilling the pilot bore. The bit was then
angled up to exit at the top of the river valley hill. Soil
conditions there offered no problems for the bore's exit. Crews
then backreamed the pilot bore to 14 inches in diameter. Two
more back reams were performed to attain the desired 22-inch
tunnel, which would accommodate the lines.
Plans had been to install three steel
lines in the hole, an eight-inch for oil, a six-inch for gas,
and a four-inch spare. This was modified for the oil company
to simply the eight and six-inch lines. The eight-inch line
was designated for natural gas, with the six inch as a spare.
In all, D&K spend just under three months to perform the
4,500 foot installation.
This contractor's innovation provided
the solution to the difficult bore entry. D&K Horizontal
Drilling was able to lower installation costs as well as limit
the disruption to the region's ecosystem.
Reprinted from Pipeline &
Utilities Construction, October 1996
|