|
Maintaining and upgrading
sanitary sewer systems where new meets old is a difficult proposition
and problems can arise. More and more contractors are utilizing
trenchless technology in these situations, but even trenchless presents
its own unique set of challenges. Contractors often need to employ
not only efficient, but creative solutions to these difficult situations.
EJM Pipe Services Inc. of Lino Lakes, MN did just that, using one
trenchless tool to help another when they employed a giant pipe
rammer to rescue their tunnel boring machine.
Growth
Maple Grove, MN,
a suburb of Minneapolis, is pushing its boundaries westward. The
addition of large commercial and retail centers in the area created
the need to increase sanitary sewer capacity. In response a $9.3
million, 17 mile, sanitary sewer interceptor project was approved
to help alleviate the sewer capacity issue.
EJM
Pipe Services was eventually sub-contracted to install several large,
grade critical concrete sewer sections. The first 865-ft section
of 60-inch OD, 42-inch ID concrete pipe would be placed under on
I-94 and Hennipen County Rd. 30. A second 175-ft section would travel
under a high voltage transmission line and tower.
|

The
Grundoram Taurus sits configured for large diameter ramming.
The 72-inch and 30-inch ram cones reduce the operating diameter,
allowing the tool to be "connected" with the casing.
|
Tunnel Boring
According to Mark
Montgomery, EJM Supervisor, they decided to use a tunnel boring
machine. Montgomery said, "The soil conditions were conducive
to a jack and bore type operation. We did not anticipate any problems
with the soil, but thats usually when things go wrong."
The
TBM has a powerful hydraulic system that turns the tools inner
drum. This particular TBM was equipped with a closed face cutter
head attachment for use the sandy conditions. As the TBM rotates,
spoil falls into the inner drum and is carried to a conveyor system
by a small auger.
A
jacking cylinder is used to push in the new 8-ft sections of high-pressure
concrete pipe, which in turn help push the TBM forward. Montgomery
said, "The TBM is equipped with a laser targeting device to
keep it on track. Its a very accurate system. And it needs
to be, especially with a grade critical bore for a gravity fed sewer
system like this one."
The
865-ft section under I-94 went extremely well. Progress was made
quickly and the entire bore was completed on schedule. Montgomery
said, "We were very encouraged by the bore. We averaged 40
feet per day. We figured the much smaller second section would be
a breeze."
The
second bore started well, as expected. The EJM crew launched the
TBM from a well shored pit some 60 feet below the surface. The first
14 sections of pipe went in without incident, but then the TBM began
to encounter some very large, unexpected, boulders. The machine
continued on until the 112-ft mark where it came to a stop. The
TBM was trapped.
|

After
the casing was in place, the EJM crew used the jacking cylinder
to push the TBM into the casing where it was ultimately retrieved.
|
How to Rescue A Trapped
TBM
Montgomery heard about
the pipe ram rescue technique from Mike Schwager, a Pipe Ramming
Specialist from pipe rammer manufacturer TT Technologies, Aurora,
IL. Schwager said, "The idea behind a ram rescue is simple.
Drive a casing from the opposite side of bore thats big enough
to swallow the trapped TBM. It provides a economical solution to
a potentially costly situation."
Hoping to find a solution
to his dilemma, Montgomery contacted Schwager. Schwager said, "After
Mark explained the situation I knew it was going take a very large
casing and a very large pipe rammer. We needed at least a 72-inch
casing to allow enough room for the TBM." Montgomery arranged
for the casing and Schwager delivered the worlds largest pipe
rammer, a Grundoram Taurus from TT Technologies.
With a piston that weighs
approximately 6,000 lbs., pounding out 180 strokes per minute, the
24-inch diameter Grundoram Taurus delivers more than 2,000 tons
of dynamic thrust. Schwager said, "Driving a 72-inch steel
casing is never easy, even with a tool like the Taurus. The hardware
that connects the tool to the casing (ram cone) weighs 10,000 pounds
alone. Its very impressive."
After a day or so of
prep, ramming was set to begin. The steel casing was fitted with
a 72-inch ram cone in order to reduce the operating diameter to
30-inches. The 24-inch diameter Taurus was fitted with a 30-inch
inch ram cone. The tool and casing were then matched and connected.
The EJM crew would attempt to ram in 5 sections of steel pipe for
a total length of 77 feet.
Montgomery said, "One
of my biggest concerns was being able to match the grade of the
bore coming from the top down and meeting the TBM. We called in
the engineering staff to reverse line and grade measurements. At
the point where you begin ramming you certainly hope that the transfer
of line and grade is accurate."
Schwager said, "The
actual ramming time was great, averaging between 15 and 20 minutes
per 20-ft section. Set up between sections, however, took a little
longer, but thats to be expected when dealing with large diameter
pipe." Over 5 days, three 20-foot casings, one 10-foot and
one 7-foot casing were rammed in, just a few feet short of the trapped
TBM.
Dewatering
Dewatering was a major
chore from the start of the job. Water was continually flowing from
the sand. Schwager said, "After the ram was finished, there
was so much water pouring into the casing that the crew decided
to try and stabilize the soil plug with straw and cribbing and wrap
things up for the weekend."
Montgomery said, "There
is really no way to estimate the amount of dewatering we did on
this job. Dewatering was a continuous effort, 24 hours a day throughout
the duration of the job."
After the weekend, the
remaining sand was removed from the 72-inch pipe all the way to
the leading edge of the cutting shoe using an auger bore system.
Well points were arranged around the perimeter of the opening between
the TBM and the casing. Everything was allowed to dewater overnight
before the actual rescue attempt would be made.
|

In order
to rescue the trapped TBM, the Taurus rammed 77 feet of 72-inch
casing in. Ramming times were very good, averaging 15 to 20
minutes per 20-foot section.
|
The Rescue
Early the next morning,
the EJM crew powered up the TBM. Using only the jacking cylinders,
the crew was able move the TBM forward. Slowly the TBM inched closer
to the casing and closer to safety. Sections of concrete pipe were
added to push the TBM into the casing. Eventually, to everyones
relief, the TBM pushed its way into the pipe. More concrete pipe
sections were jacked in place until the TBM moved far enough into
the casing to be safely removed.
After the TBM was retrieved
from the casing, the EJM crew placed the final two sections of concrete
pipe in the casing. Montgomery said, "I was certainly happy
when I saw the TBM make its way into the casing. Ultimately I would
have preferred not having to use the pipe ram rescue in the first
place, but this technique helped lessen the blow of a very spendy
situation."
Construction Bulletin, May
2000
|