|
|

The
Procision boring crew used a 24-inch diameter Grundoram Taurus
and an 18-inch diameter Goliath to install several casings
in this "telescopic" bore.
|
Procision Boring of Elk
Grove, Ill. recently completed a difficult 36-inch steel casing
installation in Channahon, Ill., just south of Joliet. The project
was part of a large-scale sanitary sewer upgrade for the city of
Channahon. The bore path traveled a lengthy 432 feet under two frontage
roads, two on/off ramps and I-55 at its intersection with US HWY
6.
According to Pipe Ramming
Specialist Mike Schwager of NUCA Member TT Technologies, the soil
conditions in that area are extremely challenging. Schwager said,
"The Joliet area is known as one of the most difficult areas
to complete any type of boring work. The soils range from clay to
gravel with boulders as larger as 24 inches, in some cases even
larger."
With several challenges
ahead of them, Procision Boring co-owners Donny Schmit and Wally
Koelle, along with Foreman Denny Hunziker, contemplated a telescopic
bore and the possibility of pipe ramming the 432-foot, 36-inch steel
casing.
Koelle said, "Because
of the extreme soil conditions, we decided to attempt a telescopic
bore. This involves ramming or augering a larger than specified
casing to a predetermined distance. The spoil is then removed and
the ramming of the actual casing takes place inside the larger one.
For long runs like this one, the telescopic bore gives the you a
head start in difficult conditions."
Hunziker was able to
auger bore a 42-inch casing 180 feet before running into trouble.
Jacking pressure had risen to the maximum, but could no longer move
the casing. The bore was slightly to the right of the intended line
and slightly above the intended grade.
The Procision crew picked
up a 24-inch diameter Grundoram Taurus from TT Technologies, and
Schwager arrived the next day. After prep work, the crew rammed
the casing another 60 feet to the halfway point. The spoil was cleaned
out with the auger and the Procision crew began preparations for
ramming the 36-inch casing.
At this point, steps
were taken to help ensure an acceptable grade on the 36-inch ram.
Schmit explained, "We decided to add an oversized cutting shoe
to the front of the 36-inch pipe in an attempt to gain back the
line and grade deviation. The oversized shoe would guide the pipe
downward."
The 24-inch Taurus was
returned and an 18-inch Grundoram Goliath was brought in to finish
the job. The Procision crew spent several days welding the 36-inch
casing sections together and placing the pipe in the 220-foot long,
42-inch casing with the jacking cylinder. Once in place, ramming
began.
It took the crew approximately
15 to 20 minutes to ram the first two 20-ft pipe sections. After
the first two were in place, the spoil was cleaned out and line
and grade were checked. Both line and grade were remaining well
within tolerance parameters. Ramming continued.
As the bore went farther
and farther, ramming times increased slightly. The 280- to 300-foot
section took approximately 40 minutes to complete. Typical ramming
times continued to range from 30 to 45 minutes for the remaining
sections of pipe.
Schmit was impressed
by the performance of the rammer. He said, "Cost control is
always an issue. With the ramming, our costs came way down. The
only alternative was to hand mine, but with hand mining you need
more personnel and get less than 10 feet a day. Once prep work was
completed, we could hammer in a piece in 30 to 40 minutes."
Hunziker said, "It
went well. We were in some pretty difficult ground. I was surprised
on how easy the rammer went through this type of soil. I look forward
to more ramming in the future."
UTILITY Contractor,
August 2000
|