|
by
Jim Schill
|

During
the slick-bore method, a pneumatic pipe rammer is used to
install a bore pipe under a rail line, road way or other
structure.
|
Trenchless technology
continues to find a home in the gas industry. Arby Construction,
New Berlin, Wis. was recently contracted to install 12,000 feet
of 12-inch gas pipeline for Nicor Gas, Aurora, Ill. Faced with several
rail line crossings where traditional open-cut construction would
not be feasible, Arby Illinois Division Manager Mario Lipira choose
a trenchless installation method. Lipira decided to utilize pneumatic
pipe ramming and the slick-bore process. This method allowed the
Arby crews to install pipe under the rail lines effectively and
efficiently.
According to Lipira, the process was simple. He said, "Basically
what were doing is installing a bore pipe under the railway.
Once the pipe is in place, we attach the product pipe to the bore
pipe. Then, we remove the bore pipe with an excavator. As the bore
pipe is removed the product pipe is pulled in place."
For the Nicor project the crews used a 10-inch diameter Grundoram Gigant from trenchless equipment manufacturer TT Technologies, Aurora,
IL.
According to TT Technologies Pipe Ram Specialist Bill Brennan,
there are advantages to ramming in the bore pipe. He said, "The
soil conditions play a big part in choosing the right installation
method for the project. Ramming can be a preferable option in areas
with difficult soils. This was especially true of the rocky, boulder-filled
area where Mario [Lipira] and his crew were working."
|

After
the bore pipe is installed, the spoil is removed and the
new product pipe is attached. A winch, track-hoe or excavator
is then used to remove the bore pipe. As the bore pipe is
removed, the new product pipe is pulled into place behind
it.
|
Contractor & Utility
Background
Started in 1956, Arby Construction has grown from a small telephone
contractor to one of the largest underground construction contractors
in the United States. For the gas industry, Arby Construction offers
complete installation services for all sizes of pipe for gas distribution
systems.
Safety is always priority with Arby. Lipira said, "We have
received numerous awards for the attention we give to safety on
the job. For this particular job, job-site supervisors were required
to attend a three-day pipe installation and safety course sponsored
by Nicor. Its something that we take very seriously here."
Nicors roots, like Arby Constructions, date back to
the 1950s. Founded in 1954, Nicor Gas is an investor-owned natural
gas utility that serves nearly two million customers in northern
Illinois, excluding Chicago. Nicor Gas is the largest natural gas
distribution company in Illinois and one of the largest in the
United States. The company maintains a 29,000-mile distribution
system that is connected to seven interstate pipelines. In addition,
Nicor Gas transports and stores natural gas for customers that
purchase their own gas supplies. These commercial, industrial and
residential customers total 129,000.
Nicor contracted Arby Construction to complete the 12,000-foot
gas system improvement near Aurora, Ill. While a majority of the
project was completed through conventional construction methods,
several key railway crossings were completed using the slick-bore
process. Lipira said, "The railroad permits for this project
specified that no directional drilling could be used under the
tracks. The railroad was concerned about the potential for voids
under the track. We needed an alternative construction method that
would not create the potential for slumps under the tracks, so
we opted for the slick-bore method."
|

The
Arby crew used the slick-bore method to install 12-inch steel
gas main under several rail crossings. A pneumatic Grundoram Gigant was used to ram the bore pipe into place.
|
Slick-Bore
During the slick-bore process the product pipe is welded to
the back end of an installed bore pipe. A winch, track-hoe or excavator
is used to pull the casing out. As the bore pipe is removed the
product pipe is pulled into place. The bore pipe is installed with
a pneumatic pipe rammer.
A cutting shoe is often welded to the front of the lead casing to
help reduce friction and cut through the soil. Bentonite or polymer
lubrication can also be used to help reduce friction during ramming
operations. For the Nicor project, the Arby crew used both a specially
designed cutting-head on the lead end of the bore pipe and Bentonite
lubrication to help with ramming operations.
Several options are available for ramming various lengths of pipe.
An entire length of pipe can be installed at once or, for longer
runs, one section at a time can be installed. In that case the ramming
tool is removed after each section is in place and a new section
is welded on to the end of the newly installed section. The Grundoram is connected to the new section and ramming continues. Depending
on the size of the installation, spoil from inside the casing can
be removed with compressed air, water, a pig system, an augering
system or a combination of techniques.
Lipira described the process his crews went through for ramming
in the bore pipe and installing the new 12-inch diameter steel
gas pipe. He said, "We rammed a single section of bore pipe to
make it to the other side of the rail line. Then wed clean
out the spoil from bore pipe. Once we have the bore pipe in place,
then wed weld on the product pipe and pull it in with a track-hoe.
Once the product pipe is installed, the bore pipe can be used again
for the next slick-bore."
The Arby crew successfully completed all three of the slick-bores
they attempted for the project. The first bore was approximately
120 feet long. The subsequent bores were shorter, averaging 65 feet
each. The total time per slick-bore ranged from 30 minutes to one
hour to complete.
According to Brennan slick-boring
and ramming are particularly conducive to transmission pipeline
installation. He said, "On
these types of installations, crews usually have enough room on
either side of the road or rail crossing to install good sized
sections of pipe. But even in tighter working areas, they are still
able to ram in the bore pipe section by section and install the
product pipe section by section.
"Slick-boring also limits the amount of stress placed on the
product pipe, which is of concern to project owners. The bore pipe
ends up taking the brunt of impact from the ramming in tough soil conditions
and spoil clean out. Through ramming it can also be installed very accurately.
The product pipe is pulled into its ideal position without being subjected to
much of anything."
Ramming can also overcome rock or boulder filled soils. During
pipe ramming, boulders and rocks as large as the casing itself
can be "swallowed up" as the casing moves through the
soil and can be removed after the installation is complete. This
also allows for a significant level of accuracy and makes ramming
ideal for installations under roads and rail lines because it displaces
the soil without creating voids or slumps.
Reaction
Everyone
associated with the project was pleased with the success the Arby
crew had with the Grundoram and the slick-bore process. Lipira
said, "If we werent using this ramming method, it would
have been extremely difficult to complete the rail crossings. Obviously
everyone was concerned about voids and slumping. We were able to
avoid that issue all together by the use of ramming. We plan to
use ramming and slick-boring in the future."
Pipeline & Gas
Journal,
January 2003
|