Railroad crossings pose a challenge for any contractor that needs
to install a utility line from one side of the tracks to the other.
Surface slump and track settling caused by a utility line installation
can make a routine project extremely costly. Trenchless technology,
specifically pneumatic pipe ramming, has helped make crossing rail
lines a bit easier. Pilchuck Contractors, Kirkland, WA, has been
utilizing trenchless technology for over 20 years. Recently they
utilized pneumatic pipe ramming on a number of gas main installation
projects for Puget Sound Energy, Bellevue, WA.
Pilchuck vice president
Bob Gray said trenchless technology has allowed Pilchuck crews
to improve their efficiency and broaden their capabilities. He
said, “We
have completed ramming projects in the past and in order to complete
the installation of the high pressure gas main for Puget Sound
Energy, we needed to install a protective casing. We looked at
several options, but ultimately pipe ramming was selected as
the best option for installing the casing without disturbing
the tracks or nearby utilities.”
For the ramming project in Snoqualmie, WA, Pilchuck used an 8.5-inch
diameter Hercules pneumatic pipe ramming tool from trenchless equipment
manufacturer TT Technologies, Aurora, Ill.
Contractor Background
Pilchuck Contractors
has been servicing the needs of the telecommunications, gas, and
oil industries throughout the western United States for over 20
years. Their experience in these industries has earned them an
enviable reputation for quality and expertise. Pilchuck works closely
with clients on a regular basis from design and material recommendations
through the construction phase, all in an effort to minimize the
costs of construction.
As a recognized leader in the construction of utility systems,
Pilchuck firm employs a wide range of construction techniques to
successfully complete projects. These techniques range from trenching
in highly congested metropolitan areas, to trenchless methods such
as directional drilling, pipe bursting, and pipe ramming to the
plowing of cable in rural locations.
Snoqualmie Project Background
According to
Gray the first ramming project was designed to help meet the growth
expectations for the city of North Bend. He said, “Puget
Sound Energy wanted to extend its high pressure gas line they have
in Snoqualmie out to feed the community of North Bend. At the time,
North Bend had an intermediate pressure line serving the area.
With fast growth, the line was undersized for the community. They
have cold weather issues out there as well. With that area being
the end of the system, when it got cold, the pressure would drop.
They were out there all the time with their CNG [compressed natural
gas] trailers to reinforce the town. So the objective of the project
was to get them they’re own high-pressure feed and district
regulator right in town. Once in place, the town would have a 250
psi system rather than the undersized 55 psi system that currently
serves the area.”

|
In order to reach
the community, the new utility line needed to run under a set
of rail lines located at the intersection of Snoqualmie Parkway
and Highway 202. According to Gray the rail line is part of an
area tourist attraction. He said, “The Northwest Railway
Museum operates a small rail line called the Snoqualmie Valley
Railroad. The museum offers small excursions on the line to places
like Snoqualmie Falls, another top tourist attraction. It’s
not like it’s a highly traveled rail track but, it’s
railroad none the less and we needed to install the new high pressure
gas line under the tracks without disturbing them.” To facilitate
the installation of the new 8-inch high-pressure steel gas main
under the rail tracks, the crew needed to first install a 120-foot,
12-inch steel casing to house the new line.
In addition to
the tracks, Pilchuck crews needed to be as precise as possible
with the installation because of adjacent utilities. Gray said, “We
were having to thread a needle. We had several drainage culverts
above us, and an un-located water main in the vicinity. In addition,
we were required by PSE to install the casing with a 2% downward
grade to allow drainage.”
Ramming
Basics & Benefits
Trenchless
pipe installation through ramming is a basic process that can be
very effective and productive. A pneumatic hammer is attached to
the rear of the casing or pipe. The ramming tool, which is basically
an encased piston, drives the pipe through the ground with repeated
percussive blows.
According to TT
Technologies pipe ramming specialist Scott Langfeldt, several
options are available for ramming various lengths of pipe. He
said, "An entire length
of pipe can be installed at once or, for longer runs, one section
at a time can be installed. In that case the ramming tool is
removed after each section is in place and a new section is welded
on to the end of the newly installed section. The ramming tool
is connected to the new section and ramming continues. Depending
on the size of the installation, spoil from inside the casing
can be removed with compressed air, water, an auguring system
or other types of earthmoving equipment."
Ramming tools, in general, are capable of installing 4- through
144-inch diameter pipe and steel casings. Ramming requires minimal
working depths and is proven effective for horizontal, vertical,
and angled applications. Ramming is also ideal for installations
under roads and rail lines because it displaces the soil without
creating voids or slumps.
On the Job
At the location chosen for the
installation the Pilchuck crew faced a series of obstacles. The
Pilchuck crew began by excavating a driving pit on one side of
the tracks. But being in the flood plain of the Snoqualmie River
meant the ground was very saturated and needed to be dewatered.
The crew dug in two dewatering wells to stabilize the flowing
sand ground conditions. Once stabilized the crew dug the pit to
a depth of approximately 15 feet and placed shoring boxes. After
the shoring was completed the crew used 4- and 6-inch riprap to
create a base to work from. Rammer set up was ready to begin.
Gray said, “For
the ramming portion, we set an I-beam down on the rip-rap base.
The beam acted like a sled for the pipe. Because of the limited
amount of space we were only able to ram 20-foot sections of
pipe at a time.”
After setting the
first section of casing in the pit, the pipe rammer was brought
in and connected to the casing through the soil port. Langfeldt
explained, “To
make the connection between the 8.5-inch diameter Grundoram Hercules
and the 12-inch diameter pipe we attached a soil port which made
the transition between the tool and the pipe. The soil port also
helps reduce the head pressure created by the spoil inside the
pipe by giving it a place to escape. For larger casing diameters,
a series of segmented ram cones and sometimes ramming adapters
are used to make the connection between the ramming tool and
the casing.”
With the tool connected and in position, ramming proceeded without
incident. Once a 20-ft section of casing was installed, the Pilchuck
crew would remove the rammer, position the next 20-foot section
of pipe. The new pipe section was then welded on to the end of
the installed section. According to Gray the crew was required
to perform complete penetration welds and welding times ranged
from 20 to 30 minutes. Once welding was complete, the rammer was
reconnected with the pipe and ramming continued. All totaled, the
Pilchuck crew rammed in six (6) 20-foot sections of casing at a
2 percent grade.
Clean Out
Cleaning out the spoil in the pipe
proved to be difficult. Gray said, “We have are own vac
truck, so we tried to remove the spoil with that first. But
we found that after the sand was dewatered, it was just too
hard packed. So we ended up bringing in a high-pressure water
jet to clean out the pipe. The unit has jets that shoot water
back at a 45-degree angle. Through the force of the water the
unit burrows it’s way through the sand. While it’s
doing that, water jets force the sand out of the pipe. It was
very effective.”
Once the spoil was cleaned out the crew was able to install the
new 8-inch gas main.
Gray was pleased
with the speed and success of the project. He said, “We
started ramming on a Monday in the afternoon. We were able to
punch in a couple of joints. Then we came the next day and knocked
the rest of them through. It was so fast, I had people that were
interested in coming down and seeing the process and I had to
call them and say, ‘Sorry, it’s done already.’”
Pipe Ramming Powers Through
Pipe ramming was
also the method of choice for another Pilchuck casing installation
project, this time in Seattle. While some casing installation
methods are impaired or even rendered inoperable by rock or boulder
filled soils. Pipe ramming is different. During pipe ramming, boulders
and rocks as large as the casing itself can be "swallowed
up" as
the casing moves through the soil and can be removed after the
installation is complete.
A cutting shoe is often welded to the front of the lead casing
to help reduce friction and cut through the soil. Bentonite or
polymer lubrication can also be used to help reduce friction during
ramming operations.
While installing
a 10-inch steel casing to house a 6-inch MDPE gas main in Seattle
, the Pilchuck Crew encountered some very difficult conditions.
Gray said, “We were punching underneath two of
Amtrak’s live rails and four future tracks. It’s an
older industrial area and when we dug down our pit was full of
bricks and other debris.
We ended up ramming
that casing through a concrete wall and a bunch of bricks and
other construction material. When we were all done, we used a
directional drill rig to clean the debris out of the pipe.”
Pipeline & Gas Journal, May 2006
|