by Jim Schill
|

The
500 ft (150 m) of new HDPE is fused to the pipe bursting
tool with a McElroy pipe fusion machine.
|
Water is a valuable commodity. Just
ask Mike Grahek, contract administrator at the Los Angeles Department
of Water and Power, Pipeline Rehabilitation Group. Since 1994,
the LADWP has spent an average of $40 million a year on rehabilitation
of potable water linesÑapproximately $110,000 a day. With replacement
of lines, the total soars to $80 million.
The department is doing everything
it can to live up to its mission statement: "...to deliver a
dependable supply of safe, quality water to our customers in
an efficient and publicly responsible manner." That means meeting
capacity issues, replacing deteriorated lines when they have
to and rehabilitating lines when they can.
The LADWP, headed by William Mulholland,
became a city agency in 1902. Back then, as a provision for
receiving water service from the LA Municipal Water System,
the recipientÑbe they individual or governmentalÑneeded to be
part of the city. Over the next 40 years, the areas surrounding
Los Angeles annexed themselves to the city. Today, the LADWP
serves a 468-sq mile (1,216-sq km) territory, maintains 7,200
miles (11,520 km) of pipeline and is the largest municipal water
provider in the United States.
The LADWP utilizes many different
technologies to meet the needs of 3.6 million customers. Grahek
said, "We're not married to any one specific technology. Some
work better than others in certain situations. We don't try
and restrict ourselves. We use what works." For a job this past
January, on the highway named after the LADWP's first administrator,
Mulholland Drive, pipe bursting was the method of choice.
|

Diagram
A
|
The LADWP oversees a vast network
that is referred to by many as an engineering masterpiece. The
water system is fueled by three major sources: local groundwater,
the Los Angeles Aqueduct and purchased water that is imported
by the Metropolitan Water District of Southern California. The
aqueduct system attributes for almost two-thirds of the city's
water supply. According to Grahek, daily water use for the City
of Los Angeles is about 700 cu ft (21 cu m) per second. That
roughly translates into 450 million gal (1.7 billion L) a day.
A majority of the water delivery
system-98 percent-is ferrous metal, i.e. cast iron, ductile
iron and steel. Water mains range in size from 4 in. (101 mm)
to 10 ft (3 m) in diameter with some installed 15 years before
the turn of the century. Over 40 percent of the lines were installed
prior to 1939. About 80 percent of the rehabilitation and replacement
work done by the LADWP is due to deterioration, the other 20
percent due to inadequate capacity.
Grahek said, "In order to maintain
these lines, the LADWP has initiated a huge cement mortar lining
program. However, if the line has deteriorated beyond rehabilitation
or has capacity issues, replacement has to be done." Such was
the case on Mulholland Drive.
The 12-in. (304-mm) line on Mulholland
Drive served as a supply main to several pump stations and tanks.
In case of a large fire, like the ones associated with the Santa
Anna winds, that line would supply the needed water. According
to Grahek, the line was no longer meeting capacity needs. That
meant two things. First, a line of this importance would have
to be replaced. Second, the line could not be out of commission
for a long period of time, in case of a fire.
Located on an easement in the hills
between Bel Air and Encino, the water main ran downhill at a
45-degree angle. Grahek said, "As far as site access goes, this
is one of the most difficult in our territory. That's why we
went to pipe bursting. We didn't want to attempt trenching a
hillside."
Pipe bursting this line was not going
to be easy either. Grahek turned to Dave Arthurs, pipeline rehabilitation
manager for ARB Inc. of Lake Forest, Calif., and Collins Orton,
pipe bursting product specialist from TT Technologies, Aurora,
Ill., to provide the technical expertise needed to accomplish
this job.
|

Finding
room to stage the 500 ft (150 m) of pipe product was difficult.
Only one lane of traffic was closed.
|
During the bursting process, the pneumatic
tool, guided by a constant tension winch, travels through the
original line. As it moves through, it effectively bursts apart
this "host" pipe, displacing the fragments into the surrounding
soil while simultaneously pulling the new pipe. Orton said,
"Advances in tool/expander configuration and guide head (schnozz)
technology over the last 10 years has made jobs like this possible."
Grahek said, "I don't know if there
is a perfect rehabilitation or replacement method for this particular
job, but pipe bursting was the best choice. Put it this way,
if it wasn't for pipe bursting, a job like this would not be
attempted." (See Diagram A)
The burst ran from the top of the
hill to a tee located 500 ft (150 m) below at the base of the
hillside. Positioning equipment and crew on the winding two-lane
highway worried Arthurs and Orton.
Before the job could truly begin,
ARB crew members isolated the existing main, separating it from
the system. They excavated the pipe on both ends, then cut it.
Crew members then installed isolation valves on each end which
allowed them to stop the flow of water through the line. After
the isolation valves were in place, the crew dug a launch pit
on top of the hill and an exit pit at the base.
The next task was figuring out how
to position the constant tension Grundowinch at the exit pit
at the base of the hill. After exploring several options, including
bringing in a helicopter and air-lifting the winch in place,
Arthurs decided to tow the winch into place with a dozer.
Arthurs said, "After realizing that
lifting the winch in place was a logistical nightmare, we towed
down the hillside. Our foreman did a great job negotiating the
hill and getting the winch in place."
A 10-ton winch was positioned at
the top of the hill. Because of the extreme slope of the hill,
the 10-ton winch was used to pull the winch line from the 20-ton
winch up the hill, through the existing pipe, where it was connected
to the pipe bursting tool.

Finding enough space to stage the
500 ft (150 m) of new 20-in. (508-mm) OD, 16-in. (406-mm) ID,
200 psi (13.7 bar) HDPE water pipe before installation was also
a challenge. One lane of the two-lane highway was closed for
a short stretch to facilitate the length of new pipe and give
workers room to work.
ARB Crew members used a McElroy pipe
fusion machine to fuse together the 40-ft (12- m) sections of
Plexco HDPE until they reached the required 500 ft (150 m).
The air compressor hose was threaded through the inside of the
new pipe in order to power the 14-in. (355-mm) diameter Grundocrack
Koloss pipe bursting tool from TT Technologies. Finally, the
new HDPE was fused to the pneumatic bursting tool.
Authors said, "To achieve the 90-degree
turn into the launch pit and position the tool on line for the
45-degree grade of the hillside, we elevated sections of the
pipe with boom trucks. This also aided in minimizing traffic
disruption." Pipe slings held the pipe above the ground, while
pipe rollers were used on the ground to help reduce pipe drag.
Orton said, "Keeping the tool from
jumping out of the host pipe on such a steep grade was tricky.
The use of a guide head, or schnozz, helps the pneumatic bursting
tool stay within the host pipe." A special schnozz was fabricated
on site and attached to the front end of the bursting tool.
(See Diagram B) After several days of prep work, the burst was
about to begin.
|

ARB
crews considered using a helicopter to position the Grundowinch
at the base of the steep hillside.
|
The Koloss, equipped with a 22.5-in.
(571-mm) rear expander, was maneuvered into place and began
moving through the host pipe. The ARB crew encountered no difficulty
with the sandy loam soil. Soil conditions can mean the difference
between bursting success and failure. To compensate for difficult
conditions, bentonite lubrication is often used. No lubrication
was needed for this job despite the very large diameter of the
new pipe.
The burst went very quickly, averaging
approximately 5.5 ft (1,672 mm) per minute. The entire 500-ft
(150-m) run was completed in less than 2 1/2 hours. The ARB
crew then tied the line into a tee at the base of the hill.
Arthurs said, "From a job site and
access stand point, this was definitely a tough bursting project.
Once everything was in place, however, the actual burst went
as smooth as any of us could have hoped for. I was concerned
about existing anchor blocks, but the tool just powered through
them. We were all very happy"
|

The
14-in. (355-mm) diameter Koloss pipe bursting tool goes
through final preparation.
|
Grahek was pleased with the results
of the burst. "With additional capacity that a 16-in. (406-mm)
ID line gives, we will be better able to meet the flow requirements
of our pump stations and reservoirs on all levels, especially
in case of a fire or other emergency. We plan to do a hydraulic
study, and depending on those results, we could be back here
bursting the 12-in. (304-mm) tee line of this new pipe."
Grahek estimates the LADWP's use
of pipe bursting will increase yearly by about 10 percent. Their
usage of other rehabilitation and replacement techniques is
also anticipated to increase. That's no surprise from the largest
water municipality in the United States.
Trenchless Technology,
Water Supplement-1999, Pages W10-W13
|