|
by Jim
Schill
Over the
last 25 years, Kamloops Augering LTD, Trail, BC, Canada
has faced some tough jobs. The trenchless pipe rehab contractor
utilizes several trenchless techniques including directional
drilling, pipe ramming, auger boring, and pipe bursting.
Not one to back down from a challenge, Malcolm Bachand,
son of Kamloops founder Monte Bachand, recently completed
one of the most unique and difficult pipe bursting projects
ever attempted.
General
contractor Marwest Industries, LTD, Trail, BC contracted
Kamloops to replace 700 feet (213 m) of 30-inch (762-mm)
wood stave pipe with 30-inch (762-mm) High Density Polyethylene
(HDPE). For the project, Bachand would use the worlds
largest pipe bursting tool, the 24-inch (610-mm) Grundocrack
Taurus from TT Technologies, Aurora, IL, USA.
Project
Background
The
pipe bursting project was being done for Cominco, LTD, Trail
BC. Cominco is one of the largest integrated zinc and copper
producers in the world. The Canadian company, incorporated
in 1906, has operations in Canada, the United States, Chile
and Peru. As part of a general upgrade and plant rehabilitation
project, a water cooling line was earmarked for replacement.
According
to Bachand, the burst was especially challenging. He said,
"Cominco had a critical cooling line at its facility
in British Colombia that had begun to collapse. To add to
the problem, the pipe was 700 feet (213 m) long, extremely
deep and was below a highly congested area of the plant
with buildings, roads and extensive underground infrastructure.
"The
only solution was to pipe burst the entire run. An open
cut option was not feasible. The old cooling line was wood
stave pipe and in very rough condition. In many places collapsed
to half its diameter."
|

An
example of wood stave pipe. Wood stave was used extensively
throughout North and South America in the early 1800s.
Kamloops Augering is the only recorded contractor
to successfully pipe burst 30-inch diameter wood stave
pipe.
|
The
Host Pipe
Two
other factors made this particular pipe bursting job unique,
the host pipe and the bursting tool chosen for the project.
Wood stave pipe in itself is not unique. The pipe was used
extensively throughout North and South America throughout
1800s. Replacing deteriorated wood stave through pipe bursting,
however, is unique.
TT
Technologies Pipe Bursting Specialist Mike Schwager explained,
"Until the Kamloops project, only a small number of
wood stave bursting projects were ever attempted and certainly
none of this magnitude and diameter. The thing that makes
wood stave so difficult to burst is actually steel. Wood
stave pipe is usually bound together with steel bands like
a wooden barrel or a continuous steel spiral band."
Bachand
selected the largest bursting tool available for the project,
the Grundocrack Taurus pneumatic pipe bursting tool. In
order to effectively burst the steel banding the Kamloops
crew used a 32-inch (813-mm) diameter front expander for
the tool and equipped with special cutting blades. This
expander was crucial to the success of the project.
Equally
rare to the type of pipe being burst, was the use of such
a large bursting tool. Schwager said, "We dont
run into situations where we need that large of a tool for
bursting that often; except in cases like this. The majority
of the pipe bursting work currently being done can be more
efficiently handled by bursting tools from 3 to 18 inches
(76 to 457 mm) in diameter. In the future I believe we will
see the need for the larger and more powerful tools, like
the Taurus, as we start bursting more and more pipe diameter
over 30 inches (762 mm)."
Prep
Work
Marwest
Industries prepared the entrance pit. The pit was quite
extensive because the wood stave line was located 20 feet
(6 m) below the surface. In addition the entrance pit needed
long enough and wide enough to accommodate the 30-inch (762-mm)
HDPE product pipe as it was pulled into place during the
bursting operation. The 700 feet (213 m) of HDPE was fused
on site.
A
winch system was set up at the end of the run, in a 54-inch
(1372-mm) diameter manhole. Once the bursting was completed,
the Kamloops crew planned to remove the front expander from
the tool and pull the bursting tool out through the new
product pipe.
|

The
700 feet of wood stave pipe was burst and replaced
with 30-inch HDPE in just 3 1/2 hours.
|
The
Burst
The
bursting proceeded without incident. Bursting times averaged
3 to 4 feet (914 to 1219 mm) per minute. Bachand said, "We
were very impressed with the performance of the equipment.
We excavated one section of the pipe in order to tie in
some lateral connections. Other than that, we expected retrieving
the 10,000 lb (4535 kg) Taurus pipe bursting tool through
the newly installed HDPE to be the most difficult part of
the project."
Once
the tool arrived at the exit manhole, the Kamloops crew
removed the expander without incident or damage to the manhole.
The winch was then moved to the entrance pit and a winch-line
was rodded through the new HDPE and attached to the tool.
The Taurus was pulled back, through the new HDPE, to the
entrance pit without a problem.
The
new HDPE line was tied into the existing manholes and put
back into service. The entire project took a mere eight
days to complete, start to finish.
Bachand
said, "Everyone was extremely pleased with the results.
Pipe bursting was the only way that job could be completed.
Cooperation between Marwest, Cominco and our crews was excellent.
It was a good job all the way around."
Trenchless Technology International,
February 2001, Page I-26
|