|
|

Having
one of the most experienced and aggressive in-house
pipe bursting programs in the United States has made
the Columbus Water Works, Columbus, GA a model for
other utilities to emulate.
|
Columbus Water
Works (CWW), Columbus, Georgia has a dubious distinction.
The water and sewer utility is undoubtedly one of the most
experienced pipe bursting utilities in the United States.
Roughly translated, more pipe bursting has been completed
in-house by the CWW than any other comparable water and
sewer utility in the United States. The results of their
efforts are substantial and the cost savings significant.
So, how does a utility go from having no practical experience
with pipe bursting to becoming a pipe bursting model for
public utilities around the country? Easy, according to
Columbus Water Works Manager of System Services Joey Murphy,
it is all in the planning.
Bursting
Background
In
the early 1990s the CWW began a sewer line evaluation program
designed to identify problem areas within the system. Workers
thoroughly evaluated sewer mains through smoke testing,
manhole inspections, dye testing and CCTV. Astonishingly,
the study identified over 100,000 lf of sewer line that
needed replacement because of deterioration, collapse and
root infestation.
Murphy said, "After the study was complete, we set
out to address the five most critical projects. Approximately
6,100 lf of pipe needed to be replaced or rehabilitated
immediately. We contracted several different rehabilitation
methods. Two of the projects were open-cut, two utilized
cured-in-place and one used pipe bursting. The total cost
for the five projects came to $62.38 per linear foot. We
knew with over 90,000 more feet of work in front of us that
wed have to find a more economical solution."
In 1997, with the help of pipe bursting equipment manufacturer
TT Technologies, Aurora, IL, the Columbus Water Works found
its economical sewer replacement solution in the form of
an in-house pipe bursting program, one of the first such
programs in the United States. Today, they are a model of
pipe bursting efficiency for other municipalities to emulate.
|

Since
1997, the CWW has burst over 28,000 lf of pipe at
an estimated savings of well over $1 million.
|
The Plan
Facing
an incredible amount of work with an almost more incredible
price tag, CWW looked for an economic solution to its sewer
replacement predicament. After calculating the costs of
the first 6,100 lf, a comparison was made between contracted
work and what similar sized projects would cost by utilizing
in-house labor for traditional open cut methods. The price
per linear foot dropped from approximately $62 to $38. Impressive
savings, but when calculations were taken one step further,
combining in-house labor with pneumatic pipe bursting (including
purchasing and operating), the results were dramatic. Cost
per linear foot dropped to $22.
In August of 1997 the decision was made to purchase a pneumatic
pipe bursting system. They chose an 8-inch diameter Grundocrack
Hercules from TT Technologies, along with rear expanders
for bursting 8-, 10- and 12-inch pipe, a 10-ton constant-tension
Grundowinch and a Grundomudd bentonite mixing and delivery
system.
According to TT Technologies Pipe Bursting Specialist
Eddie Ward The system that CWW purchased is standard
gear for high production pipe bursting. He said, "The
rear expander tool is a second generation tool. When
we began bursting in the late 1970s and early 1980s,
straight barrel tools with front expanders were used.
They can be removed through manholes or reversed
out through the newly installed pipe. Their effectiveness,
however, is somewhat limited by soil conditions,
length of run and host pipe material.
Today
the rear expander configuration is the one most commonly
used in the industry. It provides several key advantages.
First, it allows the use of bentonite in conditions that
warrant it. Second, the rear expander tool configuration
means that a majority of the tool itself is actually
in the pipe. This allowing increases bursting power and
assists in maintaining line and grade."
Work began immediately to assemble a team and begin training.
|

The
Columbus Water Works (CWW) started their in-house
pipe bursting program with a 8.5-inch diameter Grundocrack
Hercules from TT Technologies, Aurora, IL. They have
since added a 14-inch diameter tool for larger diameter
bursting work (12-inch and beyond).
|
First Projects
TT
Technologies provided on-site training to CWW crewmembers
and progress was made quickly. The pipe bursting crew was
comprised of four full-time members including a coordinator,
an operator and two team members. They received part-time
assistance from the sewer cleaning crew and the sewer investigation
team. Crewmembers caught on to the basics of pipe bursting
and soon it was time for their first solo project.
The first project called for the replacement of 1,600 linear
feet of 8-inch concrete sewer pipe with 10-inch HDPE. The
project took place in a heavily populated and traveled area
of downtown Columbus, an ideal setting to highlight the
social benefits of pipe bursting as well as the economical
benefits.
Murphy said, "The initial projects proved all of our
theories about pipe bursting true. The projects went smoothly
and when we calculated the cost, the figures were impressive.
The first project was completed in less than one month
for a cost of $29,000." Traditional open cut method
costs were calculated at $170,000.
Upgrades
From
1997 through 1999, the Columbus Water Works in-house pipe
bursting crews replaced over 13,400 linear feet of 8-, 10-,
and 12-inch VCP and RCP sewer pipe with their pneumatic
system. In 2000 it became apparent that the utility was
starting to enter a new phase in its pipe bursting program.
Murphy said, "Even as we were using our original equipment
and getting used to it, we knew there were other projects
out there with larger diameter pipes. So we decided to
make the investment and upgrade our equipment to accommodate
larger diameter bursting and begin the Milbranch project."
|

The
CWW pipe bursting crew is comprised of four full-time
members including a coordinator, an operator and two
team members. They receive part-time assistance from
the sewer cleaning crew and the sewer investigation
team.
|
Milbranch
The
Milbranch project marked a new level of pipe bursting proficiency
for Columbus Water Works. The utility was moving from small
diameter bursting (6-, 8- and 10-inch pipes) to larger (12-inch
and beyond) more difficult mains. This step required a larger
more power tool. The CWW turned again to TT Technologies.
Ward said, "The addition of a 14-inch diameter Grundocrack
Koloss and several new expanders greatly increased their
pipe bursting capabilities. Their bursting program could
now address 14-inch, 16-inch and even diameters into the
20-inch range."
The Milbranch project called for the bursting of over 8,000
lf of 12-inch concrete pipe and replacing it with 15-inch
HDPE. According to Murphy the benefits of pipe bursting
this project could not be denied. He said, "The selection
of pipe bursting as the rehabilitation method was made after
estimates of open cutting the project came in around a million
dollars. The cost of pipe bursting, using in-house personnel
with some sub-contracted help, came in about $500,000 less.
Those figures combined with less disruption to our customers
and the lower environmental impact made pipe bursting the
choice hands down." The Milbranch project began in
June of 2000 and continued, between other projects, until
April 2001.
To date, including the Milbranch project, the Columbus
Water Works in-house pipe bursting program has been
responsible for replacing over 28,000 lf of sewer main
at a cost savings of well over $1 million.
Pipe Bursting
Beyond
The
future of pipe bursting at the CWW appears to be very active
according to Murphy. He said, "Pipe bursting has migrated
to our preferred method of sewer replacement. We have a
highly trained staff that can perform pipe bursting efficiently
and effectively. We have also begun cross training our
other collection employees on how to use the bursting equipment.
And we continue to update that equipment. In fact, we are
purchasing a 24-inch expander for bursting even larger
mains. And we are look at the potential for using pipe
bursting to replace our cast iron water mains."
The next big step for the CWW is replacing the sewer main
under Cherokee Avenue. The over 50-year-old concrete main
is 21 inches in diameter and represents the largest bursting
project CWW has undertaken to this point. According to
Murphy, the utilitys bursting program is a continuous
operation with big goals.
He said, "Our plan is based on need. Even as we start
bursting larger diameter pipe, the smaller diameter bursting
is still going on. The smaller diameters make up most
of our system. That being said, our largest diameter is
72 inches. And heck, one day I might be bursting it! Thats
what Im looking at. This equipment and technology
has been such a blessing to the industry and especially
to us; the sky is the limit. We dont have any reservations
what so ever in saying, lets burst it."
Side Bar:
Emergency Work
Every municipality hopes to avoid emergency sewer line repair.
However, with most cities and towns around the country dealing
with aging infrastructure, emergency repair is a fact of
life and municipalities prepare for it accordingly.
Whether an accurate description of pipe bursting or not,
it is still considered by many a new technology despite
having been used successfully for over 20 years. With that
label in place, the tools do not typically get hauled out
in the middle of the night to fix a failed sewer line. According
to Columbus Water Works Manager of System Services Joey
Murphy, municipalities might want to change their way of
thinking when it comes to pipe bursting.
He said, "For emergency repairs, this equipment has
been a welcomed addition. In an emergency setting we have
found the method is comparable to an open cut excavation,
as far as time to set up, burst it and be gone. So we are
not only using our [pipe bursting] equipment for preventative
maintenance, where were replacing aged lines, we
use it for emergency repairs as well."
Murphy added that it is always a good feeling to successfully
finish an emergency job through pipe bursting. In addition
to correcting the problem, crews do not have to face lengthy
restoration after the work is done because they were able
to use the trenchless method.
|