|
| 
J.
Fletcher Creamer crews lower the Grundoburst 800G
static pipe bursting system in the exit pit. Crews
burst and replaced approximately 700-ft of 8-inch
ductile iron pipe with 10-inch High Density Polyethylene
(HDPE).
|
The Las Virgenes
Municipal Water District (LVMWD), Calabasas, CA. provides
potable water and wastewater treatment services to residents
of Agoura Hills, Calabasas, Hidden Hills, Westlake Village,
and surrounding areas of Los Angeles county. The facility
is considered to be a model for wastewater treatment
and environmental stewardship.
Recently an eight-inch ductile iron force sludge main
deteriorated beyond the point of operation. LVMWD Facilities
Manager David Lippman needed to find an
effective, efficient and environmentally friendly pipeline replacement method.
Lippman said, "The loss of this sludge line really put a strain on our operations.
We needed to replace the line in a short amount of time, but, because of its
location, we wanted a method that minimized social and environmental disruption."
After reviewing method recommendations, Lippman chose static pipe bursting. J.
Fletcher Creamer, California Operations, Sylmar, CA. was contracted and trenchless
equipment manufacturer TT Technologies, Aurora, Ill. was contacted for technical
support.
District
Information
The
LVMWD was formed in 1958. Today, in addition to potable
water, the district also offers wastewater and water recycling
services. Recycled water from the district’s Tapia
wastewater facility is used to irrigate golf courses, school
grounds, highway medians and other areas. A percentage
of biosolids (waste removed from the wastewater) is transferred
to the Rancho Las Virgenes Composting Facility four miles
away. At Rancho, the biosolids go through a process that
produces 20,000 cubic yards of soil amendment a year.
Two state-of-the-art fuel cells at Rancho take the methane gas by-product and
use it to create energy to run the facility. This fuel cell arrangement is one
of only five similar plants in the world. The district and its facilities have
been recognized nationally for quality operations.
Infrastructure
For all
its advancements, the LVMWD still faces the same infrastructure
problems treatment facilities around the country are facing.
The recent replacement of a section of force main between
the Tapia plant and the Rancho facility highlights the
issue.
Lippman said, "We have two force sludge mains running
from Tapia to the Rancho facility, a six-inch main used
prior to the development of the composting facility and
the eight-inch, PE wrapped main. In October of last year
we experienced a failure in the eight-inch main. It was
determined that a microbiological induced corrosion caused
the failure."
In October of 2002, a 40-foot section of the ductile iron main was replaced.
In December, the pipe failed again. The 8-inch pipe was taken offline and the
6-inch main was used instead. Lippman began putting together a plan to correct
the problem. After reviewing several methods, static pipe bursting was chosen
and J. Fletcher Creamer and Son was contracted.
| 
During
the static bursting process specially designed bladed
rollers are pulled through the existing line by a
hydraulic bursting unit. The rollers split the line
while a bursting head and expander displace the line
into the surrounding soil. The new pipe is pulled
in simultaneously. Note: Expander and new HDPE.
|
Contractor
Background
J.
Fletcher Creamer and Son has a distinguished history as
a multifaceted contractor. Over the last 75 years the company
developed into one of the most respected contractors in
the United States. With offices throughout the country,
J. Fletcher Creamer has developed a reputation for dependability,
progressiveness and innovation.
Both California based J. Fletcher Creamer and Son Area
Manager George Mallakis and Lippman agreed that trenchless
pipe bursting was a good option for this project. Mallakis
said, "The location of the pipe made a trenchless
option very attractive. The pipe ran along Las Virgenes
road, the main artery between Highway 101 and the Pacific
Coast highway. This is a highly traveled two-lane road.
The less disruption the better. Trenchless bursting was
a good choice."
Static Pipe
Bursting
During
the static bursting process, specially designed bladed
rollers are pulled through an existing line by a hydraulically
powered bursting unit. As the bladed rollers are pulled
through, they split the host pipe. An expander attached
to the rollers forces the fragmented pipe into the surround
soil while simultaneously pulling in the new pipe.
The specially designed bladed rollers actually split the host pipe instead of
ripping or tearing it. This is a clean process and prevents potential damage
to the product pipe.
Patented Quicklock bursting rods are linked together, not screwed together like
traditional drill stems or other systems. This speeds the installation process
as well as the breakdown procedure. The rods can be quickly removed one at a
time at the exit pit as bursting is in operation.
The Job
Approximately 700 feet of the main was designated to be
replaced and upsized with 10-inch HDPE SDR 9 pipe. The
run was divided into two 350-foot sections with an exit
pit dug in the middle. Launch pits were dug on each side
of the run.
The crew began by placing the Grundoburst 800G bursting unit from TT Technologies
in the exit pit and inserting the locking bursting rods through the first run
to the launch pit. A flexible guide rod attached to the front of the first rod
was used to help ensure the smooth installation of Quicklock rods.
Once at the launch pit, the J. Fletcher Creamer crew removed the guide rod and
attached the bladed cutting wheels, bursting head, expander and new 10-inch HDPE.
The entire configuration was then pulled back through the host pipe by the hydraulic
bursting unit. The 8-inch ductile was effectively split and the new HDPE was
installed without incident.
After a day of heavy rains, the bursting unit was repositioned 180 degrees in
the exit pit and prep began for the second run. The procedure was repeated and
the second section of main was successfully replaced. Crews then set to work
connecting the new pipe with the existing pipe and restoring the exit and launch
pits. Once connected, the entire system was pressure checked before being put
back into service.
Results
Mallakis was pleased with the static bursting results.
He said, "This was a project that needed to be done
quickly. It had to be done in a way that didn’t impact
traffic and open cutting wasn’t competitive. The
static method allowed use to meet the requirements of the
job."
Lippman said, "By using the static system they only
needed to open up three sections, a pit on each end and
one in the middle. That had a very minimal impact on traffic.
If we had used traditional open cut methods, we would have
had to close a lane. The static method worked very well
in this situation."
Orton said, "Working with the J. Fletcher Creamer
crew is always a pleasure. And I think the forward thinking
that is so much a part of the Las Virgenes facility showed
through in their willingness to look at different construction
methods and choose the best one for the project."
|