|
|

The
Grundoburst is able to burst ductile iron and steel
pipe and repairs. Until recently this was a major
limitation of pipe bursting equipment. Bladed rollers
split the host pipe. The bursting head and expander
displace the fragmented host pipe in to the surrounding
soil while the new HDPE is pulled in simultaneously.
|
NUCA contractor
Michels Pipeline Construction, Milwaukee, WI, recently tackled
a water main replacement project for the Brown Deer Water
Utility, Brown Deer, WI. The project gave Michels the opportunity
to utilize static pipe bursting technology for the first
time.
According to Brown Deer Water Utility Superintendent Marty
Glodoski, the existing cast iron system suffered numerous
water main breaks over the last several years. Glodoski
said, "A large portion of the cast iron water system
was installed in the 1950s and 60s. Combining the
unprotected cast iron mains with copper services created
a situation where the mains actually conduct current, which
contributes to their deterioration. Most of the breaks
can be attributed in some fashion to the electrolysis of
the unprotected cast iron mains."
Utility officials identified a 1,300-ft section of 6-inch
diameter water main as a candidate for total replacement.
The main had undergone extensive repair over the years and
contained numerous stainless steel repair clamps. The Brown
Deer Water Utility contracted Michels Pipeline to replace
the existing main through static pipe bursting. Michels
used the Grundoburst 800G static pipe bursting system from
associate NUCA member TT Technologies, Aurora, IL.
|

For
their first static pipe bursting project, the Michels
Pipeline crew replaced over 1,300 feet of 6-inch cast
iron water main with 8-inch High Density Polyethylene
(HDPE). The crew divided the run into two 650-foot
sections. Bursting times with the Grundoburst 800G
averaged 2 1/2 to 3 hours each.
|
Contractor
Background
Michels
Pipeline has been involved in the construction industries
for over 50 years. During that time, the company has grown
into a national conglomerate and expanded into numerous
other industries. The Brown Deer project represented the
opportunity for the company to expand again into another
area of utility construction, static pipe bursting.
With the introduction of advanced static bursting systems,
contractors can now burst and replace ductile iron, steel
and lined pipes, as well as pipes with ductile iron and
steel repairs. During the process, specially designed bladed
rollers are pulled through an existing line by a hydraulically
powered bursting unit. As they are pulled through, they
split the host pipe. An expander attached to the rollers
forces the fragmented pipe into the surround soil while
simultaneously pulling in the new pipe.
The bladed roller configuration is an essential part of
the Grundobursts success. The specially designed
bladed rollers actually split the host pipe instead of
ripping or tearing it. This is a clean process and prevents
potential damage to the product pipe.
Patented Quicklock bursting rods are linked together, not
screwed together like traditional drill stems or other static
systems, speeding installation and breakdown.
The Project
The Michels
crew divided the 1,300-ft run into two runs of approximately
650 feet each. A launch pit was dug in the middle of
the two runs and exits pits were dug on each end. After
completing a temporary water bypass, the crew positioned
the Grundoburst in the first exit pit and connected
it to a hydraulic power pack. The crew then inserted
the bursting rods through the host pipe and into the
launch pit.
Once at the launch pit, the crew removed the guide rod and
attached the bladed rollers, bursting head, expander and
new 8-inch HDPE. The entire configuration was then pulled
back through the host pipe by the hydraulic bursting unit.
The power of the Grundoburst combined with the specially
designed bladed roller was able to burst the pipe and all
repairs. The first 650-ft run of 8-inch HDPE was installed
without incident.
Crews then set to work making lateral connections with electro-fusion
couplings while the Grundoburst was re-positioned for the
second run. The second run was also completed with out incident.
Bursting times averaged 2 1/2 to 3 hours for each run.
According to Michels' foreman Dave Schultz the crews were
excited about the use of the new technology and adapted
to it quickly. Schultz said, "Everyone was pleased
with the results. By the end of the first run, we were experts.
I think theres a future for static bursting with
us."
|