|
by Jim Schill
|

The
Kinsel crew utilized a 18-inch diameter Grundocrack
Goliath pneumatic pipe bursting tool for the Hillsborough
project. The pneumatic tool effectively bursts the
existing pipe and forces the fragments into the surrounding
soil while pulling in the new pipe simultaneously.
|
With a quickly
deteriorating national infrastructure and continuing
mandates from governmental agencies, the urgency to replace
water and sewer mains has never been greater. Crowded
city streets, historic locations and the expense of major
restoration, has shifted the focus from traditional open
cut construction and put trenchless construction techniques
center stage. Over the last few years, pipe bursting
has emerged as one of the most popular and preferred
methods of trenchless pipeline rehab and replacement.
Dave Arthurs, Area Manager for Kinsel Industries, Houston,
TX, has been in the utility construction business for
over 15 years and involved with pipe bursting for almost
10 of those years. Recently, Kinsel Industries took
on a difficult pipe bursting project in the hills of
northern California that put Arthur’s
knowledge and experience to the test.
Arthurs said, “The project for the city of Hillsborough, California was
very challenging. Sections of the failing sewer system ran parallel to some very
large diameter water transmission mains. In addition, the area along the San
Mateo Creek, where much of the work was done, is considered environmentally sensitive,
home to several endangered species of plants and animals. Trenchless pipe bursting
provided a pipe replacement option that addressed all the concerns we had going
into the project. It’s a trenchless option that limits disruption and has
a low impact on structures above and below ground.”
The project called for the replacement of the existing 15-inch Vitrified Clay
Pipe (VCP) sanitary sewer main with 28-inch High Density Polyethylene (HDPE).
Arthurs turned to pipe bursting specialist Collins Orton from trenchless equipment
manufacturer TT Technologies, Aurora, Ill, for technical support.
The
System
Hillsborough’s collection system consists of approximately
82 miles of sanitary sewer pipes ranging in size from 6
to 18 inches. Two Inflow and Infiltration studies completed
in the 1990s showed the 50-year-old plus system to be capacity
deficient and not able to meet needs of Hillsborough’s
11,000 residents. Peak flow was estimated at 8.9 million
gallons per day. The existing system was sized to handle
approximately 5.5 million gallons.
The study identified a large section of the system as a major problem area with
significant deterioration. That section runs through a right-of-way that houses
the Hetch Hetchy water mains and is maintained by the San Francisco Water Department.
Those mains run from the Hetch Hetchy watershed located in Yosemite National
Park and supply over 85% of the water for the city of San Francisco and surrounding
areas. The water is transported through large diameter water transmission mains,
ranging in size from 49 inches to 79 inches. They are an invaluable resource
and are treated as such.
In addition to concerns about the Hetch Hetchy mains
and the environmentally sensitive area, the diameter
of the existing pipe needed to be increased three nominal
sizes in order to raise the system’s capacity
to desired levels. Pipe bursting offered an economically
feasible and environmentally sound solution to the
replacement dilemma.
|

A
20-ton Grundowinch was used to guide the pneumatic
bursting tool through the existing pipe. The winch
is key to the bursting process providing constant
and consistent tension.
|
Pipe Bursting
Pipe bursting was developed in Europe from the concepts
found in pneumatic piercing tools. The tool is basically
a piston within a casing. Compressed air drives the
piston and the piston drives the tool, creating percussive
action.
Piercing tools have been widely used since the 1960s.
Orton explained, “In the late 1970s German and
British contractors tried using piercing tools to break
cast iron pipe and pull in new pipe. In Europe at that
time, there was a great need for trenchless pipe replacement,
specifically for cast iron pipe in the gas industry.
The results of those early experiments eventually evolved
into pipe bursting as we know it today.”
While static pipe bursting equipment is growing increasingly common for ductile
iron and steel pipe, a majority of pipe bursting done in the United States is
done with pneumatic tools. During pneumatic pipe bursting, the pipe bursting
tool is guided through a fracturable host pipe (pipes such as clay, concrete,
cast iron, etc.) by a constant tension winch. As the tool travels through the
pipe, its percussive action effectively breaks apart the old pipe.
Depending on the specific situation, the tool is equipped with an expander, located
at the rear of the tool, that displaces the host pipe fragments and makes room
for the new pipe. As the tool makes its way through the host pipe, it simultaneously
pulls in the new pipe, usually HDPE.
With the use of expanders, one tool can be used to burst several different size
host pipes and replace them with new HDPE of the same size or larger. Pipe bursting
is the only trenchless method of rehabilitation and replacement that allows for
the upsizing of the existing pipe.
Hillsborough
Pilot Project
A 500-ft pilot bursting project in late 1999 opened the
way for pipe bursting to be specified as the method
of choice for remaining replacement. During that initial
project,
vibration studies were conducted and much scrutiny
given to the affects of bursting on the Hetch Hetchy water
mains.
It was determined that any effects from vibration through
the pipe bursting method were negligible.
Arthurs said, “Monitoring stations were also
set up during the main project. The stations were located
in sections of bursting that were in close proximity
to the large diameter water mains, typically anytime the bursting came within
20 feet of the mains. Again, vibration proved to be a non-factor in this project.
Everything was well within tolerances. In addition, an environmentalist was employed
full time to supervise the project and make certain nothing occurred that would
put the endangered species in harms way.”
To perform the over 1,800 feet of bursting operations, Kinsel Industries chose
to use an 18-inch diameter Grundocrack Goliath pneumatic pipe bursting tool,
a Grundomudd bentonite/lubrication mixing and delivery system and 20-ton constant
tension Grundowinch from TT Technologies.
Orton said, “We needed a tool that would have
enough power to complete the upsize. Also, winch selection
was key. The Grundowinch provides constant tension
at variable speed. That means the winch is able to
make adjustments for conditions that affect line speed
during operation, providing constant, consistent and
smooth pulling force which is essential for successful
pipe bursting.”
On the Job
|

The
Kinsel crews replaced the existing 15-inch VCP
sewer main with 28-inch High Density Polyethylene
(HDPE). The existing main ran through a right-of-way
that houses large diameter water transmission mains
that supply much of San Francisco and the surrounding
area with water.
|
Before any bursting
could begin, the Kinsel crews were required to pothole
sections of the run that cam in
close proximity to the Hetch Hetchy water mains. In
addition,
the Kinsel crews needed to replace existing 48-inch
manholes with 60-inch manholes throughout the project.
In order to accomplish the significant upsize the Goliath
pipe bursting tool was fitted with a 34.5-inch OD rear
expander. Orton said, “The large expander
was needed to create the annular space necessary to accommodate the new 28-inch
pipe. This adds another dimension to pipe bursting. Instead of the upsize being
15 inches to 28 inches, it’s really 15 inches to 34.5 inches. It’s
something that needs to be taken into consideration when choosing the appropriate
bursting equipment for a particular project.”
The Kinsel crew divided the project into 400-ft sections for bursting. Crews
would then replace one 400-ft section at a time. First, crews prepared launch
and exit pits on either end of the 400-ft run. After completing the launch and
exit pits, crews then fused the necessary length of 28-inch SDR 17 HDPE for that
section. The 20-ton Grundowinch was positioned at the exit pit while the bursting
tool was attached to the new HDPE at the launch pit. The winch cable was then
rodded through the existing pipe section and connected to the bursting tool.
At that point, bursting operations were ready to begin. The pneumatic tool was
launched into the host pipe and the process was under way. According to Arthurs,
from start to finish, a 400-ft section of bursting took between four and five
hours to complete.
|

Pipe
bursting was well suited for this project because
it is a trenchless construction method and creates
minimal disruption. The location of the project
was not only home to large diameter water transmission
mains, it was also considered an environmentally
sensitive area, home to several species of endangered
species of plants and animals.
|
Results
Over 1,800
feet of 15-inch VCP was replaced with 28-inch HDPE through
pneumatic pipe bursting for the Hillsborough project. Arthurs
said, “In the sections where pipe bursting was utilized
it was extremely effective. It was a very environmentally
friendly method and very capable one at the same time.”
Orton said, “Pneumatic pipe bursting has had a tremendous impact on the
pipe line rehabilitation and replacement industry. It’s developed into,
in many cases, a preferred method of pipeline replacement because of its inherent
benefits. It has a wide range of capabilities and can be used is many different
situations. Plus, because the method is trenchless, it offers minimal social
disruption. Being able to replace aging sewer and water mains without tearing
up roads, sidewalks, landscape and other sensitive areas is something everyone
can be excited about.”
Heavy Equipment News,
November 2003
|