|
by Jim
Schill
NUCA contractor Di Paolo Company, Glenview, IL was recently
contracted by Lake County Public Works, Libertyville, IL
to replace 600 feet of undersized 15-inch VCP with 20-inch
High Density Polyethylene pipe (HDPE) through pneumatic
pipe bursting. For the challenging project Di Paolo Company
used a 14-inch diameter Grundocrack Koloss from associate
NUCA member TT Technologies, Aurora, IL.
|

The
Di Paolo crew used a 14-inch diameter Grundocrack
Koloss with a 22.5-inch expander to complete the large
upsize from 15-inch VCP to 20-inch HDPE.
|
Project Background
Wildwood Subdivision near Gages Lake, IL was constructed
prior to the 1970s, before the establishment of clear and
enforced restrictions against the use of sanitary sewers
for home footing drain and sump pump discharges. For many
years residents in low lying areas near Gages Lake and adjacent
Valley Lake encountered basement flooding and overflowing
neighborhood manholes during heavy rains. Wet-weather sanitary
sewer flows were sometimes greater than 20 times normal
dry-weather flow.
According
to Public Works Project Manager Art Malm, engineering
studies during the late 1990s identified possible solutions
to the areas problems. Malm said, "Video, dye and smoke testing
detected some cracked pipes, some leaking manholes, a few
gutter and patio drains and several broken lateral connections.
Added up however, these defects accounted for less than
30% of measured wet-weather I&I. We concluded that
70% or more of our stormwater flows most likely came from
footing drains and sump pumps."
There were two
possible solutions to correct this situation. First, the
owners of several hundred properties could each voluntarily
pay several thousand dollars to correct their home sanitary
services. Or, the carrying capacity of the sanitary sewer
system could be increased. According to Malm, the appropriate
economic and political decision was clear.
Bursting
Background
Lake County Public Works had successfully used pipe bursting
to upsize an 8-inch VCP pipe in a heavily forested neighborhood
in 1998 where storm-flow problems similar to Gages Lake
were encountered.
At Gages Lake, the interceptor passed under maturing trees
and through a new residential neighborhood adjacent to a
wetland area. Open cutting would have required loss of wetland
woodlands and a considerable effort to obtain construction
permits and easements. Pipe bursting eliminated these potential
problems. It was an ideal choice for the project.
On the Job
The Di Paolo crew divided the 600-foot run in half and decided
to burst from the middle, using the same launch pit for
each run. The launch and exit pits measured 10 feet wide
by 20 feet long. A 10-ton constant tension Grundowinch was
placed at the exit pit, at the end of the first run. After
the crew direct bolted the 300 feet of fused HDPE to the
22.5-inch diameter front expander on the Koloss, the tool
was lowered in to the launch pit. Bursting was ready to
begin.
According to Di Paolo Company Vice President Sal Di Paolo,
the biggest challenge during the first run came from an
undocumented section of steel casing. He said, shortly
after the start of the first run, the progress of the bursting
began to slow down. At the end of the run we discovered
the section of steel casing. The winch and bursting tool
moved 20-foot length of steel casing nearly 200 feet."
In light of the
unexpected section of steel casing, the Di Paolo crew opted
for a rear expander configuration on the Grundocrack Koloss
for the second 300-foot run to provide stability in the
host pipe and cracking power if another unexpected point
repair was encountered. The second run was completed without
any complications.
Future Bursting
According to Malm the next phase of interceptor capacity
improvement in Gages Lake through bursting will include
an 890-foot segment of 15-inch VCP upsizing to 19.4-inch
ID HDPE. The upsize work to resolve the remaining capacity
problems in this community is scheduled for completion before
2004.
Di
Paolo sees more bursting in his companys future as well. He said,
"Pipe bursting is a very valuable pipe replacement
method. Owners and engineers should take a look at current
and future projects and find the areas where pipe bursting
would be beneficial. I believe the potential for pipe bursting
in our company as well as the market in general is tremendous.
It will continue to grow as more and more people become
familiar with the method."
NUCA,
December 2001
|