by Jim
Schill
|

Through
the use of trenchless boring with the piercing tool
the crew was able to keep the only access road along
the mountainside open and work at multiple job sites
at the same time.
|
While
trenchless construction methods like pipe bursting anddirectional
drilling have taken center stage over the last few years,
one method continues to prove its value everyday, in
the field, without much fanfare-horizontal boring with
pneumatic piercing tools. Piercing tools could easily
be considered the genesis of modern pneumatic trenchless
technology. Contractors around the world continue to
achieve high rates of production and efficiency with
them.
Ray Toney and
Associates, Redding, CA, is a good example of a skilled
and multi- facetted contractor getting the most out of a
piercing tool. As part of the Cascade Flume Replacement
Project in Nevada City, CA, the contractor was required
to install over 5,700 total feet of 4-inch PVC drainage
pipe along a narrow road in the Sierra Nevada Mountains.
For the project,
Ray Toney and Associates Project Superintendent Allen Toney
turned to TT Technologies Product Specialist Joel Kurmann
for technical support. A 5-inch diameter Grundomat-P 130
was chosen to take on the tough mountain conditions.
Flume Project
The Cascade Canal
is a key water source for Nevada Irrigation District. The
canal feeds water to five water treatment plants that supply
more than 20,000 customers in western Nevada County California.
The Nevada Irrigation District, which manages the system,
knew that it was only a matter of time before the aging
concrete bench flume that carried the water would have to
be replaced.
A flume is basically
an above ground, open-channel that is used to carry or transport
material, liquid or otherwise, from place to place. Some
flumes accelerate flow through converging walls or an elevating
bottom, or a combination of both. The Cascade Canal flume
was gravity fed.
In March of 2000
the district put the project out for bid. Requirements included
the demolition of the existing flume and the installation
of more than 34,000 linear feet of 54-inch concrete pipe.
In addition, the construction of a major temporary bypass
was necessary.
Toney
said, "The
design of the project included installing a permanent
concrete pipeline in the same location as the existing
flume. But before work on the pipeline could begin, we
needed to install the 4-inch subsurface drainage pipes
along the right-of-way where the new pipe would be installed.
That's where the piercing tool came in."
|

The
Ray Toney & Associates crew used a 5-in. diameter
Grundomat-P 130 to complete the 50- to 60-ft. pilot
bores for the 4-in. diameter PVC drainage pipes.
The drains will accommodate run off from snowmelt
and rain and prevent erosion.
|
Tough Mountain
Conditions
The entire length
of the concrete bench flume paralleled a roadway. The roadway
traveled up the mountainside to the headworks of the flume.
The project required the new pipe to follow the same route
as the existing flume. PVC drainage pipes were also required
to be installed perpendicular to the new pipe, under the
roadway, in predetermined locations. The 50-to 60-foot drains
were designed to accommodate seasonal run off from snow
and rain and protect against the erosion of the new pipe
bedding.
Work
on drainage pipe installation began in January 2001.
Working during the winter months can be very challenging
in some parts of the country; working during the winter
months high in the Sierra Nevada mountains is beyond
challenging. Kurmann said, "The job site was very
remote. They had a limited right-of-way to work with
and extremely tough soil conditions. They also had
to deal with rain and snow. The conditions really put
the crew and piercing tool to the test."
With almost a
century of history behind it, the tool was ready for the
challenge.
Piercing
Tool Background
The first patent
for a piercing tool design was granted in the early 1900s,
in Europe around the time of World War I. The original design
called for a piston to propel the tool, and compressed air
to drive the piston.
It wasn't until
the 1950s however that interest in piercing tool technology
resurfaced in Poland and resulted in actual tools being
built and tested. During the 1960s the technology emerged
in Russia and Germany. In Poland the tool was referred to
as Kret, Polish for mole. The earliest moles were often
difficult to handle and hard to restart after stopping.
Accuracy was also a problem.
Because accuracy
was such a problem with most piercing tools, the technology
was often disregarded and not allowed developed fully. The
development of the reciprocating stepped-cone chisel-head
assembly changed all that in the 1970s.
Kurmann
explained, "The
Grundomat piercing tool basically works on the same principles
found in the first early piercing tools. A piston, inside
a casing, drives the tool, and air drives the piston.
The major improvement comes in the reciprocating head.
The chisel head assembly moves independently of the main
casing, creating a pilot bore for the rest of the tool
body to follow. This ultimately leads to greater bore
accuracy. The chisel like action helps the tool to power
through difficult soils and obstructions without being
pushed off course."
|

After
creating the pilot bore with the piercing tool the
4-in. PVC was inserted manually. The Ray Toney crew
averaged four to five complete drain installations
per day.
|
Piercing
Tool Benefits
Using
the Grundomat helped the Toney crew overcome the difficult
conditions in several ways. First was space. With limited
right-of-way space to operate in, the crew needed a tool
that would be effective in tight working conditions. The
piercing tool was able to operate from small launch pits
measuring on average 8 feet by 8 feet and 5 feet deep.
Second
was limited disruption. The trenchless application
allowed the road to remain open during operations.
Toney said, "Keeping
the road open improved our production. If we would have
dug across the road in 95 different locations to install
the PVC drains we would have been continually cutting
off the only access along to the subsequent job sites.
Keeping the road open meant we could work at multiple
locations simultaneously without cutting ourselves off."
Third was
time savings. Like any other construction project, the
Cascade Flume Replacement Project has an established timeline
for completion. With work on the main pipeline scheduled
for spring and summer, the installation of the PVC drains
needed to be completed in a timely manner. Using the piercing
tool helped the crew meet the aggressive time line.
Toney
explained, "We
averaged, over 95 locations, one hour per installation
with the Grundomat. That was complete. I couldn't justify
digging a hole, which would probably take an hour, then
installing the pipe, bedding it, back-filling it and
meeting compaction requirements. We would have probably
been able to do one every four to five hours under ideal
conditions. And that wouldn't have been possible here
with the soil conditions. I figure production and time
savings with the piercing tool was 4-to-1 over open cutting
the project."
Typical Installation
Throughout the
project, a three-man crew was used for all the drain installations.
The crew consisted of a backhoe operator and two piercing
tool operators. After digging the launch pit, the backhoe
operator continued to the next site and dug the next pit
while the other two crewmembers launched the tool.
When
the bore was complete, the backhoe operator returned
to help retrieve the Grundomat and remove the hose.
The PVC pipe was inserted manually into the pilot bore
at the point where the tool existed. Toney said, "We
were able to manually install 90% of the drains. Some
were tougher than others. On the difficult installations
we used a sling and the backhoe to help pull/push them
in."
The Future
of Piercing Tools
For Ray Toney
and Associates the future of the piercing tool looks like
it does for many other contractors. After living up to its
reputation as the workhorse of trenchless technology, the
piercing tool has become another trusted piece of equipment
in the Ray Toney and Associates toolbox.
|

The
project required the 4-in. PVC drainage pipes to be
installed perpendicular to the new 54-in. diameter
concrete watermain, under a roadway. Over the 95 installations,
bore times with the Grundomat averaged one per hour.
|
|