|
|

The compact size of the Grundopit rig
means only small pits are required.
|
Almost every city or municipality
has one, a certain job or project that remains unfinished or
is not attempted, sometimes for years, because it is inherently
too difficult for current technology or too great a risk for
contractors. Occasionally, however, a contractor comes along
with the right attitude and the right tool to make the impossible
possible. Such was the case recently for contractor Hoffman
and Hoffman in the City of Waverly, lowa.
Hoffman and Hoffman is no stranger
to underground electrical work. The company is also no strangers
to Waverly and its limestone bedrock soil. Contractor and ground
conditions have done battle there before, but this job was different.
A 21 m (70 ft) long, 152 mm (6 in) diameter, and 914 mm (36
in) deep hole was required, under a state highway through solid
limestone. It seemed impossible, at least that is what everyone
thought until they were introduced to a powerful pit launched,
steerable, mini directional boring rig.
According to Dean Williams, Distribution
Planner for the City of Waverly, the project had been on the
shelf for quite some time. He said. "About a year and a half
ago, we had an automobile accident that took out one of the
overhead power poles downtown. Restoring the aerial lines was
not an option because the poles are already too close to the
highway. We needed to go underground." Going underground was
easier said than done.
The power line lost during the accident
was a tie between two feeders. It served as a backup line if
one of the feeders was lost. Whilst not essential, it needed
to be replaced to ensure back up power and maintain reliability
within the city's power distribution system.
Tough
Conditions
Waverly, lowa has a population of
some 10,000 and is located approximately 30 minutes north and
west of Waterloo. State Highway 3 runs directly through the
middle of the town. Hoffman and Hoffman has completed many jobs
for the town of Waverly including several trenchless electrical
conduit jobs with standard directional drilling equipment. Duey
Hoffman said, "We knew right away what we were up against when
Dean showed us the site. Going 21 m (70 ft) under a 4-lane highway
is tough enough, but through limestone bedrock, that's another
story."
Williams knew that open cutting the
heavily traveled Highway 3 was not feasible. In fact, it was
never even considered as an option. Williams said, "We did not
want to face tearing up the street, disrupting traffic, co-ordinating
traffic control and restoring the street. This section of highway
was resurfaced within the last 2 years."
In addition to extremely tough soil
conditions, a trenchless method would need to be able, if needed,
to circumvent a multitude of existing underground utilities.
These included a telephone line, gas, sewer and water mains,
as well as a 6-way fibre optic utility duct. Williams supplied
the Hoffmans with a map of sub-utilities in the area.
To successfully complete this job,
the equipment used would have to be powerful enough to bore
through limestone and have steering capabilities. In addition,
the work area was tight, a conventional directional drill rig
would not work. The tool would have to be compact.
|

Operating
the Grundopit rig beneath the busy highway. |
Situation
As in the past, the Hoffmans looked to TT Technologies Product
Specialist Jay Clark for assistance. Duey Hoffman said, "We
have known Jay for a long time. Once we were contacted by the
utility company for this job and knew what we were facing,
we called him. He came down and evaluated the job and thought
he had a piece of equipment that could do the job. This was
a Grundopit rig."
Recently made available from TT Technologies,
the Grundopit 40/60 is an hydraulically operated mini steerable
bore rig. Its compact nature, only 1,120 mm (4 ft) long, 480
mm (2 ft) wide and 480 mm (2 ft) tall, made it perfect for the
Waverly bore. But everyone wondered if the mini directional
had enough power to successfully tackle solid rock.
Dave Hoffman said, "We were quite
concerned about this job because we attempted to use a standard
directional drill to cross this highway in the early 1980s and
failed. When I talked with Jay Clark I said, ÔJay, we are not
talking about a small cable here, we're talking about 101 mm
(4 in) inner duct, through limestone.' He was still confident
the bore could be done."
The job was scheduled for a Tuesday.
A Waverly utility crew spent the better part of the preceding
Monday jackhammering a launch pit for the drill through the
sidewalk and limestone below. The launch pit measured 1,800
mm (6 ft) long, 900 mm (3 ft) wide and 1,200 mm (4 ft) deep.
Another pit of similar dimensions was dug on the opposite side
of the street in softer soil.
Dave said, "I knew the conditions
there were tough, but I could not believe it when I heard they
had to use a jackhammer to dig the launch pit.
Bore
After creating a small pilot bore
with the jackhammer, the Hoffmans were ready to tackle the solid
limestone.
By using the DigiTrak Mark III Receiver
with remote monitoring, the Hoffmans knew the location and depth
of the drill stem at all times. The remote system allowed the
operator to monitor depth and location from the launch pit.
Duey said, "We remained in constant
contact with the drill head as the bore was being made. The
operator can tell by the feel of the machine and by using the
locator where fractures and gaps occur in the limestone, as
well as the back-fill areas around the sewer and water mains.
At these points we would steer the drill right, left, down to,
avoid a utility or up to level off."
The areas of back-fill around the
sewer and water mains were crushed rock. The Hoffmans were able
to steer the drill at these points because the crushed rock
was much more forgiving than the solid limestone.
The bore's path traveled directly
above the two utility mains in the street as well the others
near the exit pit. Duey explains, "We had to bore above a water
main at 1.8 m (6 ft) deep, a sewer main at 2.4 m (8 ft), and
a 6-way fibre optic utility duct and gas main both at 965 mm
(38 in)."
The Hoffmans started the initial
bore around noon. It took the 50 mm (2 in) diameter drill stem
about 2 hours to make its way to the other side. The initial
bore was complete.
Subsequently, the crew put on a 76
mm (3 in) diameter reamer and proceeded with the backream. About
there was a 76 mm (3 in) diameter hole through 21 m (70 ft)
of stone. The Hoffmans then prepared for the second backream.
After sending the drill to the other
side, the Hoffman crew put on a 101 mm (4 in) diameter reamer
and backreamed again. Approximately 11/2 hours later there was
a 101 mm (4 in) diameter hole.
|

Schematic
of the ground and existing utilities faced on
the Waverly project.
|
Pullback
A spool of 101 mm (4 in) diameter
SDR 15.5 Plexco HDPE pipe sat waiting on the other side. When
installed, three 15,000 volt electrical cables would run through
the conduit and join two feeder lines on opposite sides of the
street. After the second backream, the crew prepared for the
third and final backream with product pullback.
The Hoffman crew attached a 152 mm
(6 in) diameter reamer to the drill stem and a PE pulling eye
to the HDPE pipe. The reamer and the PE pulling eye were then
linked and the pullback began. Again, approximately 11/2 hours
later, the reamer was through and the pipe was in place.
|

Ready
for pullback the 101 mm diameter HDPE pipe in position
at the reception pit. |
Mud
Mix
In addition to the right tool, the
proper mix of bentonite and water for lubrication was critical
to this job. Duey said, "In sandy conditions, the bentonite
mixture works as a bore hole stabiliser. In clay, the bentonite
works as a lubricant as well. Different mixtures and consistencies
are used for various soil conditions. In this situation, the
bentonite and water mixture acted as a coolant and helped reduce
the extensive friction of the limestone."
Jay Clark said, "We used a 1,140
1 (300 gallon) Grundomudd Bentonite Mixing System to mix and
deliver the straight bentonite, water and polymer. In this heavy
rock situation, we used high flow levels to maximise the cooling
capabilities of the fluid. The high fluid flow was also used
to carry out the rock cuttings during the backreams." The Hoffmans
had nearly used the entire 1,140 1 (300 gallons) bentonite mixture
by the end of the day.
After the last drill stem was removed,
the Hoffman crew lifted the Grundopit out of the launch pit
with a backhoe. Then an additional 1.2 m (4 ft) of HDPE pipe
slack was pulled through with using this machine and a tow chain.
Both ends of the HDPE pipe were capped and the clean up began.
Dave said, "The day Jay brought the
Grundopit machine to attempt the bore, I looked at it and said
to myself there is no way this thing is going to pull a 101
mm (4 in) diameter inner duct back, yet alone bore across. I
was amazed when it worked. It was truly unbelievable."
It took the Hoffmans a little over
6 hours to complete the bore, 3 successive backreams and product
pullback. Williams was also amazed. He said, "We figured we
would have some degree of success, but never this. I was very
impressed and very pleased when the machine made it all the
way through."
No-Dig, May 1999,
Pages 18-19.
|