|
by Jim Schill
|


Middle
Creek Mining of Peabody, KS used a 24-inch diameter Grundoram Taurus to ram this 138-inch diameter casing 148 feet underneath
the railroad right-of-way.
|
Risky or experimental
projects do not attract many contractors. However, like any other
endeavor, there are those who are confident enough in their abilities
and their equipment to take on difficult, challenging or even impossible
projects. These are the contractors and projects that push the envelope
of equipment and technology performance, and provide valuable information
to equipment manufacturers, engineers and the general construction
population. Middle Creek Mining Corporation, Peabody, KS is one
such contractor that recently wowed the underground construction
industry with a pair of world record setting pipe rams.
Middle Creek
Mining President Frank Oursler is no stranger to difficult jobs.
He has seen his fair share of challenging soil conditions, complicated
projects and difficult working situations. But the two giant casing
installations near El Dorado, KS, not only pushed the limits of
his pipe ramming equipment, they set new standards by which all
other large diameter pipe rams are measured.
Oursler said,
"We were approached by the city of El Dorado to provide suggestions
on the installation of two large-diameter casings under the Burlington
Northern/Santa Fe railroad right-of-way. The casings were 118 inches
in diameter and 138 inches in diameter. We have been pipe ramming
for several years, and I suggested that method as an option to the
city engineers. They eventually accepted it."
To complete
the amazing task, Oursler teamed the worlds largest pipe rammer,
the 24-inch diameter Grundoram Taurus from TT Technologies, Aurora,
IL., with a Bor-It MFG split auger boring machine.
Pipe Ramming Background
Pipe ramming
has been around as long as piercing tools. Adapting a piercing tool
to install a small-diameter casing in the ground is not a difficult
task. The difficulty or challenge in pipe ramming comes with large-diameter
casing installation. According to TT Technologies Pipe Ramming Specialist
Mike Schwager, before the Middle Creek project, pipe ramming was
just beginning to tackle some very large diameters.
He
said, "Ive worked on a couple of 72-inch diameter ram
jobs in the last few years. And I believe, before the Middle Creek
job, that the largest diameter casing installed was right around
the 72-inches. We fully expected the next leap in diameter to be
around 80 to 84 inches. I dont think anyone saw 118-inch and
138-inch installations occurring so soon. The tools to complete
that type of project are out there, but a lot of it has to do with
a contractor like Middle Creek having the fortitude to attempt it."
Product
Pipe
For the El
Dorado jobs, Oursler chose Permalok steel casings. Often times during
a ramming or a jack and bore project, welding casing segments can
take many hours of production time. According Permalok President
Mike Argent, Permalok casings employ a simple mechanical press fit
design that provides a strong, quick connection between casings
as an alternative to welding.
The Project
Between 100
and 120 trains travel the Burlington Northern/Santa Fe mainline
through El Dorado each day. Expansion of the local golf course and
hiking and biking trails in the area necessitated an easy and safe
way to cross from one side of the tracks to the other. With the
extreme amount of train traffic, safety alone precluded an above-ground
crossing. Large-diameter casings under the tracks were the best
solution.
The first ram
created what became known as the south tunnel. Five 21-ft segments
of Permalok casing were delivered to the job site. When rammed in
place, these segments would create a safe and stable 89-foot long
tunnel below the tracks.
The second
pipe ram took place approximately 1/4 mile north of the first one.
This ram was even larger; 138-inches in diameter covering 148 feet.
In addition to providing golf course patrons and area recreationalists
safe passage under the rail line, this tunnel would provide a crossing
for two utility mains. New 8-inch water and sewer lines were to
be installed along the bottom of the casing. Concrete flooring would
protect the mains and provide a flat surface for travelers. The
stage was set for two world record rams.
On The Job
After receiving all the necessary equipment
and materials, Middlecreeks crew, led by Project Superintendent
LaRue Nolen, set up and began ramming. At the start of the first
ram a 20-inch pneumatic ramming tool was used, but slow progress
and other difficulties prompted a change of tools. Mike Schwager
was contacted, and the 24-inch diameter Grundoram Taurus was brought
in to continue ramming.
Schwager said, "The initial tool
configuration of segmented ram cones could not stand up to the amount
of stress placed on it. Mike Argent at Permalok was able to fabricate
a 118-inch pipe adapter that resembled an inverted bell. This configuration
proved much more successful. With large diameters like this, its
a learning experience. Everyone gained valuable knowledge."
Ramming continued at a much greater pace.
The Grundoram Taurus rammed an average of six feet per hour at the
start of the job despite being operated at less than full power.
Jacking cylinders and a frame were used to support the pipe and
put an addition 200,000 lbs. of push force against the back of the
fabricated pipe adapter. After each segment was rammed in, mini
excavators were used to clean out the spoil. Finally, the Middle
Creek crew rammed the last segment in place. A new pipe ramming
diameter record was established, but that was just the beginning.
|

The combined
weight of the installed sections of pipe topped 323,000 pounds.
|
Monster Ram
Armed with valuable information from
the 118-inch diameter ram, Nolen and the Middle Creek crew set to
work on the giant 138-inch job. In preparation for this larger bore,
steel rails provided by the railroad were laid on the line and grade
at the foot of the right-of-way. The rails were then embedded in
concrete. At the rear of the rails, a large push block was constructed.
The push block had steel walls on three sides and was reinforced
with steel cross bracing. The box was then filled with concrete
and allowed to harden for two weeks.
Nolen then placed twenty feet of auger
track just in front of the push block and arranged the jacking cylinders
to allow them to push against the back of the 118-inch fabricated
adapter cone from the previous ram.
Again Mike Argent at Permalok was called
upon to fabricate a reducing cone to bridge the 138-inch casing
diameter and the 118-inch adapter cone diameter. The Bor-It auger
machines hydraulic pressure was increased to provide an additional
500,000 lbs. of push force. Another air compressor was also brought
in to ensure the Taurus operated at its 1,766 cfm full capacity.
Big Pipe
The pipe provided by Permalok had an
O.D. of 138 inches and a 1.5-inch wall thickness. Each section was
21 feet long and weighed 2,187 lbs. per foot. When complete, the
installed sections combined weight topped 323,000 pounds.
Oursler said, "Weve been using
this pipe for several years and were very pleased with it.
It would have taken two to three days per connection longer had
we had to weld it. They [the casings] slide together and lock from
the pressure. They have lock rings manufactured on them and the
pressure of the pipe rammer and boring machine push them [the segments]
together."
Two CAT EL 300B excavators were needed
to lift and position each casing segment on the rail before ramming.
The Middle Creek crew also used a Straightline bentonite pump to
deliver a polymer lubricant to the lead edge of the ram through
two 1-inch supply lines.
|

A special
adapter cone was fabricated to connect the 138-inch casing
with the 24-inch diameter Grundoram Taurus.
|
The Ram Is On
Ramming began at a furious pace with
the first 21-foot section taking only 40 minutes to install. The
next 15 feet were in place in approximately 75 minutes. As the weight
of the pipe segments and the soil inside them increased, ramming
times increased significantly. At this point, Nolen removed the
soil in order to help ramming production return to previous levels.
Over a period of 12 days, the Middle
Creek crew rammed in segments of casing and cleaned out the spoil.
Spoil was removed from the casing with a Case 1845 C skid steer
and a Yanmar D 27 mini excavator. At noon on the 13th
day of ramming, the final casing was installed and the spoil removed.
Over 140 feet of 138-inch diameter steel casing was in place. Ramming
times averaged three to four feet per hour. A new benchmark in pipe
ramming was set.
Ramming Review
The El Dorado pipe rams have created
a lot of excitement in the industry. According to Schwager this
amazing feat could be repeated or bested in the future. He said,
"Combining the worlds largest pipe rammer with auger
bore technology definitely helped this project succeed. The equipment
is out there. For skilled and adventurous contractors like Middle
Creek, there are no records that cannot be broken."
Underground Construction,
September 2000
|