|
By Jim Schill
When ramming large-diameter pipe
along railroad lines, underground construction crews face several
challenges, including maintaining the grade of the bore and
minimizing settlement of the tracks. Sometimes, just getting
to the jobsite can be a challenge. Angelica Boring Company,
a NUCA-member contractor based in Pittsford, N.Y., recently
overcame these challenges on a pipe ramming job in the state's
Catskill Mountains.

Angelica Boring Company's crews do final prep work on
the first section of casing, using an auger track as
a drive platform and a jacking cylinder system to keep
constant pressure on the casing and eliminate reboud. |
The stretch of Conrail line, 2 miles
east of Chester, N.Y., intersects a creek system that produces
heavy runoff during the spring melt and heavy rainfalls. Existing
culverts under the tracks could not handle the water flow. Backup
from the creek was damaging surrounding areas and threatening
the tracks.
To give the creek system a better
flow path, the Angelica crew installed 145 ft. of 72-in.-dia.
steel casing under the rail line. Angelica vice president Dewight
Cartwright called pipe ramming product specialist Mike Schwager
from TT Technologies, Aurora, Ill., for technical support on
the job.
The first major hurdle Angelica faced
was getting the necessary equipment to the jobsite, as no roads
lead directly to that section of track. "The ram took place
at the bottom of the ravine, alongside the creek," Schwager
said. "They [Angelica] basically built a road to the site."
The Angelica crew used a 24-in.-dia.,
10,580-lb. Taurus Grundoram pneumatic pipe rammer for the job.
The crew laid approximately 100 ft. of auger track as a drive
platform for the Grundoram. A jacking cylinder frame supported
the pipe rammer and eliminated rebound, which was crucial to
reducing track settlement.

For this tough job, the company chose
the Grundocrack Taurus to ram 145 ft. of 72-in. steel
casing under the Conrail line. |
"The jacking cylinders help
keep the tool from rebounding backwards as the ram is taking
place," Cartwright said. "We put a preset amount of
pressure on the tool and casing, allowing the pipe to move forward
but not backward. We put the rammer on the track in a special
saddle. Then we put 8- by 8-in. hardwood blocks between the
front of the sled and the tapered ram cone. We were able to
exert about 300,000 lbs. of pressure on the casing before ramming."
After a few days of prep work, the
Angelica crew began ramming. Workers welded together two 40-ft.
sections of 72-in.-dia. Grade B steel casing and used two tapered,
locking ram cones (a 72-in. and a 30-in.) to connect the casing
to the Grundoram.
As the casing and tool moved forward,
the Angelica crew stopped periodically and reset the jacking
cylinders to maintain pressure. The casing was placed in just
2 1/2 hours. The crew used an auger to clean spoil from the
casing and began prep work for the next section.
Everybody's
Happy!
After cleaning the spoil, the crew
moved the final 65-ft. section of casing in place. Workers took
only a few hours to complete the weld that connected the sections.
The crew once again fit the Taurus with tapered ram cones and
commenced ramming. Just 3 hours later, the entire 145-ft. casing
was in place under the rail line.
Angelica held track settlement to
an almost undetectable .04 in. The crew completed the entire
job in approximately 2 weeks. Actual ramming took slightly more
than 5 1/2 hours.
"Angelica's teaming of the Grundoram with an auger jacking system proved extremely effective,"
Schwager said. "Everyone was very happy with the results
of the project."
Utility Contractor,
June 1999, Page 34
|