|
by Jim
Schill

To
facilitate the ramming of such an enormous casing, Miller
the Driller had an inverted bell ramming adapter fabricated
by Arntzen Steel, Rockford, Ill. The 147-inch reduced
the overall diameter to 80 inches. An 80-inch ram cone
and a 24-inch ram cone made were added to make the connection
to the Grundoram Taurus.
|
Bike trails seem to be
some of the most popular community development projects. In times
when budgets are being slashed and public funds are at a premium,
communities around the United States continue to invest in improving
existing trail systems and creating news ones. But that doesn’t
mean that cost is not a major consideration. It is. And city
and county officials need to be careful and creative planners
when it comes to designing these projects and determining construction
methods.
A recent trail construction project in Altoona , IA. put community
services director Vern Willey to the test and required some creative
thinking and as well as some impressive trenchless construction
by a renowned trenchless contractor.
Project Background
According
to Willey, the idea for the project goes back almost a decade. He
said, “Back in 1995 the city got involved with
a community group and one of the members of the group came up with
the idea of a bike path loop through the city. Plans were developed
and the ultimate goal was to tie into another trail system that
would eventually become part of a 110-mile trail system. Eventually
a plan of where the trail would run was drawn up. After the plan
was adopted, we applied for and received a statewide enhancement
grant.” The $200,000 grant was designated for purchasing
an easement along the railroad right-of-way where the trail would
run.
Finding the proper balance
between existing areas and the new bike trail proved to be an
issue that Willey needed to address. He said, “We encountered some tight locations along the railroad
right-of-way. There is an industrial area there and some people
didn’t want the trail right up against those areas. At one
point the trail crossed the tracks with a pedestrian bridge. As
we got further in the layout, we realized that in order to connect
everything we would have to cross the tracks again. At grade crossings
were pretty much out of the question so we knew we would have to
go under the tracks.”
Willey and Snyder & Associates
Engineering, Ankeny , IA. looked at various options for installing
a tunnel under the tracks. Ultimately, pneumatic pipe ramming
was chosen.
Contractor Background
The
name Miller The Driller, Des Moines , IA , has become synonymous
with some of the most difficult utility construction projects in
the United States . In the world of pipe ramming, Miller the Driller
is considered a premier contractor. After the project in Altoona
, Miller the Driller reached a new plateau with a world pipe ramming
record.
For the project, Miller
The Driller was contracted to install the 60-foot casing needed
to facilitate the bike path tunnel under the rail line. The pipe
ram ranks as the largest diameter pipe ram ever completed. According
to vice president of operations Brandon Young, son of Miller
the Driller President Kris Young and grandson of founder Gene
Miller, the installation method was key to the project’s
success.
Young said, "During the early stages of this design. Snyder & Associates
Engineering, contacted us regarding jacking in a square concrete
tunnel underneath railroad tracks for a bike tunnel. We have completed
both square and round projects in the past. After looking at the
site we determined that a square tunnel would not be a good choice
for this project as the tracks were built on a levee. Our experience
has been that levees are typically built on or with fill material
that would hinder this type of trenchless application. We decided
to pipe ram a round casing instead."
In order to create a tunnel large enough to accommodate bicyclists,
the steel casing would need to be very large. The 147-inch outside
diameter casing ultimately used for the tunnel sets a new world
record for pipe ramming diameter, besting the previous record by
three inches. To complete the job, Young chose a 24-inch diameter
Grundoram Taurus pneumatic pipe rammer from TT Technologies, Aurora
, Ill.

In
preparation for ramming, the Miller the Driller crew
poured a 50- by 16-foot concrete pad. The pad served
as the support for ramming operations including a push
sled and auger track.
|
Ramming Basics & Benefits
Trenchless pipe installation through ramming is a basic process
that can have amazing results. A pneumatic hammer is attached to
the rear of the casing or pipe. The ramming tool, which is basically
an encased piston, drives the pipe through the ground with repeated
percussive blows.
A cutting shoe is often welded to the front of the lead casing
to help reduce friction and cut through the soil. Bentonite or
polymer lubrication can also be used to help reduce friction during
ramming operations.
According to TT Technologies
pipe ramming specialist Mike Schwager, several options are available
for ramming various lengths of pipe. He said, “An entire
length of pipe can be installed at once or, for longer runs,
one section at a time can be installed. In that case the ramming
tool is removed after each section is in place and a new section
is welded on to the end of the newly installed section. The ramming
tool is connected to the new section and ramming continues. Depending
on the size of the installation, spoil from inside the casing
can be removed with compressed air, water, an auguring system
or other types of earthmoving equipment.”
Some casing installation
methods are impaired or even rendered inoperable by rock or boulder
filled soils. Pipe ramming is different. During pipe ramming,
boulders and rocks as large as the casing itself can be "swallowed up" as
the casing moves through the soil and can be removed after the
installation is complete.
Ramming tools, in general,
are capable of installing 4- through 122-inch diameter pipe and
steel casings. At 24 inches in diameter, the Grundoram Taurus
is the world’s second largest pipe rammer.
The Grundoram Apollo at 32 inches in diameter is the world’s
largest ramming tool. Until the Miller the Driller project in Altoona
, diameters up to 144 inches had been successfully installed using
large scale ramming equipment. Ramming requires minimal working
depths and is proven effective for horizontal, vertical, and angled
applications. Ramming is also ideal for installations under roads
and rail lines because it displaces the soil without creating voids
or slumps.
Project Design
According
to Willey, project specifications varied in the beginning of the
project. He said, “With some of the requirements we
saw on bike trails and clear space, we were looking at a 14-foot
diameter tunnel. We approached these agencies and explained that
a 14-foot tunnel just wouldn’t work in this situation. So
eventually we got them to buy into the idea of a 12-foot diameter
tunnel.”
Costs also had a big
impact on the project design. Willey explained, “Well
once we got going on the ramming idea and contacted Miller the
Driller, we brainstormed and came up with what they thought they
could do and what it would cost. The only problem that we had occurred
after we got all of our estimates in and we thought that it’s
going to work, we put the project out for bid and the bids came
back substantially higher than we expected because the cost of
steel had skyrocketed.
So we looked at the design.
Installation costs were coming in at around $3,900 per foot.
At the time we had the tunnel a little lower in the slope of
the railroad right-of-way so the tunnel had to be longer. So
we went back and reworked the design and raised the tunnel up
a little and cut about ten feet off the total length. And that
helped cut the total cost of the project.”

The
crew used a Grundoram Taurus
pneumatic pipe rammer from trenchless equipment manufacturer
TT Technologies, Aurora, Ill. At 24 inches in diameter,
the Taurus is the world’s
second largest pipe rammer. The 32-inch Grundoram Apollo
is the world’s largest.
|
On the Job
The ram took place
under rail lines (which remained active throughout the project)
owned by the Iowa Interstate Railroad Ltd. A launch pit was dug
on the south side of the tracks to accommodate a 50- by 16-foot
concrete pad that would serve as a platform for operations. Young
said, “With an existing park on the north side of the
track, we didn’t want to cause any more environmental impact
to the area than was necessary. We built a concrete backstop and
concrete launch pit on the south side of the tracks where excavation
and clearing would take place anyway for the new bike trail.”
After the pit construction
was finished the Miller crew assembled a driving stage for the
Taurus from an auger track. The crew also utilizes a hydraulic
push sled to assist with ramming operations. Young said, “We
used the boring machine to push against the casing during ramming.
We also used it to move the rammer back after each segment of
pipe was rammed into place so the next piece of casing could
be brought in.”
The pipe chosen for
the project was made by Permalok, St Louis , MO. The casing was
fabricated in 20-foot sections. Each 20-foot section had a wall
thickness of 1.5 inches and weighed 2,330 pounds-per-foot or
approximately 47,000 lbs per section. The Permalok casing incorporates
a mechanical press fit design without an internal or external bell.
According to Young, this was a real time saver. Schwager commented, “On
a recent large diameter ram that incorporated a weld-in-place operation,
a single joint took a week to weld and x-ray. Brandon said the
time needed to make up one Permalok joint for the Altoona project
was less than one hour.” The crew carefully lowered a 20-foot
long 147-inch diameter pipe section into place and after the prep
work was complete, ramming was ready to begin.

The
147-inch OD casing represents the world’s largest
diameter casing successfully rammed, besting the old
mark by three inches.
|
Record Ramming
The
connection between the 24-inch diameter GrundoramTaurus and the 147-inch
OD diameter casing was made using a special adapter. The 147-inch
inverted bell pipe adapter, rolled by Arntzen Steel, Rockford ,
Ill. , reduced the overall diameter to 80 inches. An 80-inch ram
cone was then connected to the adapter and further reduced the
diameter to 30 inches. A 24-inch ram cone made the final connection
to the tool. The entire configuration was secured with tensioning
chains and the tool was connected to the air compressor.
The actual ramming went smoothly. Crews were able to install
the first 20-foot section of casing without incident. The ramming
tool was removed and some of the spoil was taken out of the casing.
Crews then positioned the next 20-foot section of pipe in place
and made the connection to the first section. The rammer was reconnected
and the second section was rammed in place. The entire ram was
completed on a 2.2% downhill grade. Once all of the casings were
installed the Miller the Driller crew removed the remaining spoil
with a skid steer loader. Almost 6,000 cubic feet of dirt was removed
from the casings.

The
giant casing was rammed 60 feet under Iowa Interstate
Railroad tracks. The tracks remained open during the
ramming operations. The casing was installed to create
a tunnel under the tracks for a new bike path for the
city of Altoona Iowa.
|
Ramming Success
Young attributes
the success of the project to several factors. He said, “The
willingness of the engineers to look beyond conventional construction
techniques and allow a trenchless solution to be developed was
the first part of the success. The other part was the crew. They
were the success. The crew was very professional and courteous
at all times. I am very proud of how our team represented Miller
the Driller. Our field supervisor Bill Mendenhall took hold of
a concept and made a highly difficult project highly successful.
Several railroads were watching this project very closely. They
couldn’t believe it when we rammed the pipe through to the
exit side and never disturbed the tracks.”
The community’s reaction to the project was positive as
well. Willey said, “The response has been just great. There
are so many people that use it. The kids, as well as adults, can
access the old swimming pool, the new aquatic center, the fitness
center, library, playfields, all without having to worry about
crossing the railroad tracks.”
Work continues to complete the next phase of the trail project
within Altoona . Several additional phases need to be completed
in order to complete the 110-mile loop. Willey estimates the project
is 50 to 60 percent complete.

Completed
tunnel.
|
Public Work ,
May 2005
|