|
|

The
US Pipeline utilized the slick-bore process over 60 times
during the 28 mile Horizon Pipeline project. The process involves
installing a bore pipe with a pneumatic Grundoram pipe
rammer (shown here), then attaching the product pipe to the
bore pipe. As the bore pipe is removed with a winch, the
product pipe is pulled into place.
|
by Jim Schill
Over the last 30 years
trenchless technology has emerged as one
of the premier underground construction methodologies. New techniques
are continually being developed, while existing techniques are being
refined. This type of growth in technology can be seen in the gas
industry and its contractors.
Premiere pipeline installation contractor US Pipeline, Houston,
TX
is a good example of a company embracing new technologies and helping
develop new methods and ways of construction. Recently, US Pipeline
was contracted to install 28 miles of 36-inch gas pipeline for the
Horizon Pipeline project taking place in northern Illinois. While
a large portion of the project was open-cut, trenchless technology
played a major roll in certain areas.
Faced with numerous road crossings, rail crossings and other situations
where traditional open-cut construction would not work, US Pipeline
Vice President Jimmy Crotts opted for a trenchless installation
method. He decided to incorporate pneumatic pipe ramming into the
slick-bore process. This trenchless process allowed US Pipeline
crews to install pipe under roads, rail lines and other areas effectively
and efficiently. The results were impressive.
According to Crotts, the process is simple yet effective. He said, "Basically what were
doing is installing a bore pipe under a road or railway, etc. Once
the pipe is in place, we attach the product pipe to the bore pipe.
Then, we remove the bore pipe with a winch. As the bore pipe is
removed the product pipe is pulled in place."
The US Pipeline crews used pneumatic pipe ramming during the slick
bore process to install the bore pipe. For the Horizon project the
crews used two 18-inch diameter Grundoram Goliaths from trenchless
equipment manufacturer TT Technologies, Aurora, IL.
According to TT Technologies Pipe Ram Specialist Scott Kneip, there
are advantages to ramming in the bore pipe. Kneip said, "The
soil conditions in the area where the US pipeline crew are working
are not very conducive to auger boring. The glacial till soil contains
many rocks and boulders that can play havoc with a conventional
auger bore system. Ramming is a preferable option."
|

After
installing each section of bore pipe, the US pipeline crew
removed the spoil with a conventional augering system. The
crew successfully completed installations of over 380 feet
of the 36-inch steel gas pipeline.
|
Gas Goes Trenchless
The gas industry has been a leader in the development of new
construction technologies. Motivated by deregulation to find more
efficient ways of doing business, the distribution side of the industry
has embraced trenchless technology for maintaining/upgrading existing
systems as well as installing new ones.
The distribution segment has been instrumental in the wide scale
use and acceptance of directional drilling. Gas utilities are also
active users of pneumatic piercing tools and are responsible for
the development of the only guided piercing tool technology.
The transmission side of the industry has also adopted trenchless
construction methods. Some of the methods, i.e. directional drilling,
are the same, but others are quiet different. Piercing tools are
ideal for the distribution side of the industry because of the smaller
pipe diameters (1/2-inch to 6-inches) and different working conditions.
Piercing tools are not effective for installing 36-inch or 48-inch
natural gas pipelines.
Auger boring is one method has been a staple of the gas pipeline
industry for years. The method is extremely effective in certain
areas, but augering under roads and rail lines creates the possibility
for costly surface slump and voids. Over the last several years
a pipe ramming has gained greater attention in the gas industry
and its effectiveness in the slick bore process.
Slick-Bore
During the slick-bore process the product pipe is welded to
the back end of an installed bore pipe. A winch is connected to
the lead end of the bore pipe and is used to pull the casing out.
As the bore pipe is removed the product pipe is pulled into place.
In this scenario, the bore pipe is installed with a pneumatic pipe
rammer.
Trenchless pipe ramming is simple; a pneumatic hammer is attached
to the rear of the bore pipe. The ramming tool, which is basically
an encased piston, drives the pipe through the ground with repeated
percussive blows.
A cutting shoe is often welded to the front of the lead casing to
help reduce friction and cut through the soil. Bentonite or polymer
lubrication can also be used to help reduce friction during ramming
operations. For the Horizon project, the US Pipeline crew used both
a specially designed cutting-head on the lead end of the bore pipe
and Bentonite lubrication to help with ramming operations.
Several options are available for ramming various lengths of pipe.
An entire length of pipe can be installed at once or, for longer
runs, one section at a time can be installed. In that case the ramming
tool is removed after each section is in place and a new section
is welded on to the end of the newly installed section. The Grundoram is connected to the new section and ramming continues. Depending
on the size of the installation, spoil from inside the casing can
be removed with compressed air, water, a pig system, an augering
system or a combination of techniques.
Crotts described the process his crews went through for ramming
in a several hundred-foot bore pipe installation on the Horizon
project. He said, "Wed ram a section of bore pipe, say
80 feet, under a wetland or a road. Then clean that bore pipe out
using a conventional auger boring machine. Then we would weld on
another 80-foot section of pipe and ram that in. Then clean it
out. Cleaning out as during ramming takes the weight out of the
pipe and provides better control. Once we have the bore pipe in
place, then we can weld on the carrier pipe and pull it in."
Once the product pipe is installed, the bore pipe can be used again
for the next slick-bore.
|

The US
Pipeline crew used two 18-inch diameter Grundoram Goliath
tools from TT Technologies for the installation of the bore
pipe.
|
Ramming & Slick-Bore
Benefits
According to Kneip slick-boring and
ramming are particularly conducive to transmission pipeline installation.
He said, "Typically,
crews have a decent amount of room on either side of road or rail
crossing. This allows them to install longer sections of pipe.
But even in tighter working areas, they are still able to ram in
the bore pipe section by section and install the product pipe section
by section.
"Slick-boring also limits the amount of stress placed on the
product pipe, which is of concern to project owners. The bore pipe
ends up taking to brunt of impact from the ramming in tough soil conditions and
spoil clean out. Through ramming it can also be installed very accurately. The
product pipe is pulled into its ideal position without being subjected to much
of anything."
Ramming can also overcome rock or boulder filled soils. During
pipe ramming, boulders and rocks as large as the casing itself
can be "swallowed up" as the casing moves through the
soil and can be removed after the installation is complete. This
also allows for a significant level of accuracy and makes ramming
ideal for installations under roads and rail lines because it displaces
the soil without creating voids or slumps.
Crotts said, "If we werent using this ramming method
the conventional way would have been to auger bore. But what happens
much of the time is that you begin to experience an undermining
of the road. You get caverns and cavities and the road slumps.
We have not had to maintain any road that we bored under using
the ramming technique."
The technique proved especially valuable for a section of the project
that took place under Interstate 90. Crotts said, "The project
specifications called for the installation under the I-90 toll-way
to be hand tunneled. We invited the State engineers with the toll-road
department to come out watch what we were doing. They saw the operation
and gave us permission to ram under I-90."
|

Trenchless
pipe ramming allowed the crews to install pipe under roads,
rail lines and even protected wetlands.
|
Impressive
Statistics
The US Pipeline crews skill at ramming and slick-boring
paid off in many sections of the Horizon Pipeline project. Over
the 28-mile long installation, the crew performed over 60 slick-bores
in many different situations. Crotts said, "We did some roadways,
rail crossings, creeks and even wetlands. In one county working
through designated wetland areas was prohibited so we were required
to use some type of boring. We rammed and slick-bored through those
areas. It worked very well."
During the project Crotts and the US Pipeline crew completed some
very substantial installations in terms of length with the Grundoram.
According to Crotts, short installations averaged 60 feet, while
the long installations ran near 300 feet. The US Pipeline crew successfully
completed one slick-bore totaling an impressive 380 feet with 36-inch
pipe.
Reaction
Everyone associated with the project
was excited about the success the US Pipeline crew had with the
Grundoram and the slick-bore process. Kneip said, "Jimmy and his crew really did some incredible
installations on this project with the slick-bore/ramming method.
Theyre a top-notch pipeliner all the way."
Crotts said, "I dont think we would have been able to
complete the project the way we did, without the use of this process.
I know we would have had a lot of road maintenance. For the type
of soil conditions we were in, the glacial till, cobble, sandy etc,
I think ramming with the slick-bore will take the industry by storm.
The chance for us to be more competitive is there too. Its
a great opportunity."
ACP, May 2002
|