|

The near
completed view of the 82 total I-beams installed.
|
As part of a road improvement
project for Kent County Council, England, trenchless contractor
Genseed Underground Services Ltd. of Chelmsford, Essex was contracted
to install 82 I-beams varying in size from 775 mm to 975 mm by 460
mm by 15 m (2.5 to 3 feet by 1.5 feet by 50 feet) in length in order
to create the roof and side wall structures for a railway underpass
at Northfleet in Kent.
The temporary structure
involved sheet piling both sides of a 10-m (32-foot) high railway
embankment that supported a 13.5-m (44-foot) section of track. The
original plan called for the installation 27 tie bars through directional
drilling from sheet pile to sheet pile, a total distance of 14 m
(45 feet). Thirteen of these tie bars would be used to secure the
sheet piles and the embankment while the tunnel was dug. Fourteen
would be used, again at different levels, for the reaction frame
for hydraulic jacking.
|

The overall
jobsite view where the underpass road would evently be excavated.
|
Change of Plans
Genseed Underground Services Ltd. was
contracted by the main contractor, Christiani & Nielsen Ltd.,
to install the tie bars through directional drilling and install
the I-beams through hydraulic jacking.
After looking at drawings and making an initial site visit, Genseed
suggested ramming rather than jacking the interlocking I-beams.
It is believed that this was the first time in the UK that this
method has been used on such a project. Extensive research was carried
out to anticipate and overcome any technical problems that could
possibly arise.
Genseed contacted TT
Technologies UK in Bedford for technical support. After consultations,
it was decided that a 350 mm (14-inch) diameter Grundoram Koloss
pipe rammer was best suited for the project.
|

Each I-beam
installed was carefully aligned using interlocking steel profiles.
|
On the Job
The first five tie bars used to retain
the top of the sheet piles were installed at 1. 4 m (4.5 feet)
below the tracks running
level. This was completed in two days, after which another 1.6
m (5 feet) of earth was removed and a level platform was created
for ramming the I-beams. The first two beams were positioned,
on line and grade. This was critical because the line and grade
of all subsequent beams were dependent upon the first two. Entry
and exit holes were cut into both sheet pile walls and the ramming
commenced. The first two beams took approximately one hour to
ram with line and grade well within specification.
At the start of the third
beam, it became apparent that there was a problem. Ramming on the
flange of a steel beam rather than a standard casing was creating
some serious recoil problems. The ratchet straps were unable to
mitigate the recoil force of the hammer. The Genseed crew fabricated
a special ramming plate with a tapered hole for the nose of the
rammer and special fittings for the plate to the beam. The plate
helped overcome the problem of keeping the rammer in contact with
the beams and ensured maximum energy transfer. Subsequent beams
were installed in approximately 45 minutes each.
|

The Genseed
crew fabricated a special ramming plate for the 14-inch diameter
Grundoram Koloss to minimize recoil.
|
Progress
Forty-two
beams were installed in 12 days, meeting the target of 3.5 per day.
The beams were then welded to the sheet piles to stop the sheets
from moving outward. The Genseed crew then removed another 4 m (13
feet) of soil and installed another row of 4 tie bars.
The second phase of ramming
for the side walls was ready to begin. Two walls were built each
containing eight I-beams lying on their sides and supported on a
series of suspended pads. Ramming commenced from the top down using
the beam under the one being rammed as the guide for the ramming
equipment. The last beam in each stack was driven from a set of
rails mounted between the suspended pads. Two more rows of beams
were installed using the same method, bringing the total to 20 beams
per sidewall.
After a total of 25 days
(64 hours), the last beam was successfully driven. The Genseed crew
installed a total of 1,148 m (3,760 feet) of I-beams with the Grundoram Koloss. The work was completed 10 days ahead of schedule. The complete
roof and wall beams were well within specification. Both main contractor
Genseed were delighted with the successful outcome of the new joint
venture.
|

The
I- beams varied in width from 775 mm to 975 mm (2.5
to 3 feet).
|
|
|

At
the projects completion over 1,148 m (3,760 feet)
of I-beams were successfully installed under the railway
tracks using pneumatic pipe ramming.
|
|
|

The
Koloss averaged 45 minutes per 15-m (50-foot) I-beam.
|
|
| Trenchless
Technology International, August 2001 |
|