Pipe Ramming & HDD, A Texas Two Step! Iowa Trenchless Rams Conductor Barrel Casings in Fort Worth

The project in Fort Worth consisted of the installation if two 54-inch conductor barrel pipe rams. The first one was 90 feet, and the second one was 180 feet.
Horizontal directional drilling and pneumatic pipe ramming are two trenchless methods that complement each other on small and large projects alike. HDD is the ultra-capable installation method that has allowed projects that were once unthinkable to become realty. And pipe ramming is the ultimate muscle method, there to help, assist and even salvage HDD projects that run into problems.
The two methods recently teamed up on a project in Fort Worth, TX for the installation of a large diameter force sewer main. The wide-reaching project includes the installation of approximately three miles of 36-inch diameter HDPE force main to service the Fort Worth area. Along with conventional construction methods, several sections of the project were specified as horizontal directional drilling.
While another company was subcontracted for the HDD work, General Contractor SJ. Lewis of Texas subcontracted Iowa Trenchless, Panora, IA. to install two Conductor Barrel casings to help facilitate the HDD work.
Jason Clark President of Iowa Trenchless said, “There were two 54-inch conductor barrel pipe rams. The first one was 90 feet, and the second one was 180 feet. We did both prior to any of the drilling occurring, but they were consecutive. They were installed on the entry side of separate HDD crossings. One for a crossing parallel to the Trinity River. The other one was for crossing an interstate and multiple frontage roads, and five or six railroad tracks.”
Pipe Ramming and HDD Assist Specialist Rick Melvin from trenchless equipment manufacturer TT Technologies, Aurora, Il. explained the concept behind the casings Iowa Trenchless was contracted to install. He said, “With the Trinity River, the conductor barrel was installed as a way to contain the drilling fluid, protect the start of that bore and ultimately get into a point where drilling can begin. And that’s the basic definition of a Conductor Barrel. It’s a casing that is rammed into the ground, at a predetermined angle, until desirable soil conditions are met. Drilling happens within the casing that helps the drill head reach desirable soil conditions. It also helps contain the drilling fluids and help in other ways, but that’s the concept of the installation.”
To install the two conductor barrel casings, Iowa Trenchless used a 24-inch diameter Grundoram Taurus pneumatic pipe ramming system from TT Technologies.

Iowa Trenchless used a Grundroram Pipe Ramming system from TT Technologies to install the Conductor Barrel Casings. Shown: Pipe rammer with ramming gear attached.
Iowa Trenchless Quality Contractor
Iowa Trenchless has performed conductor casings on numerous projects, ranging in diameter from 24 inches to 54 inches. And other than conductor barrel ramming, the contractor has rammed 60-, 72- and 84-inch casings. In addition to pipe ramming, Iowa Trenchless is a well-rounded utility contractor, experienced in other trenchless methods including auger boring, GBM guided boring, tunneling, pipe jacking and rock boring.
This high level of capability also comes with a high level of attention on safety. Iowa Trenchless has received the NUCA (National Utility Contractors Association) William H. Feathers Safety Award numerous times, including the years 2010-2013, 2015-2016, 2019 and 2022. Clark said, “We care for every employee’s safety and well-being and are constantly motivated to make sure every employee has the knowledge and resources to be as safe as possible while on a jobsite. Safety is a topic at every meeting we have, whether it’s a company meeting or specifically a safety meeting. Every Iowa Trenchless employee participates in at least OSHA 10-Hour, Excavation Safety and Competent Person, Confined Spaces Entry and CPR/First-Aid training, as well as specialized job training. A number of employees have also been certified in OSHA 30-hour, and have been trained in Hazardous Materials Handling, Waste Remediation and Underground Construction Rescue. I always say that I’m going to end my career without having anybody ever get seriously injured or killed on one of my jobs, because safety is the number one thing.”
According to Clark, with a crew of seasoned professionals including supervisor Brandon Derry, and superintendent Rick Seamers, this was a great opportunity to involve some of the younger crew members on a project that they might not have been on before. He said, “My son Wyatt is 20 years old. Another one on that list, Avere Doles, is 21 years old and from Louisiana Tech Trenchless Technology Center. We had a few more people than we probably needed, but we wanted a bunch of young guys to see what this looks like. Not necessarily a training exercise, but as a way to introduce some of the guys to the installation and equipment that might not get on that type of job as often. If you’ve ever been on a pipe ramming job, I mean, you can feel it in your body when the hammer is hitting, you can feel it.”

During the Conductor Barrel process, a casing is rammed in place at a predetermined angle. That casing serves several purposes including helping contain drilling fluid and allowing drilling to begin in optimum soil conditions.
On the Job
Crews began work establishing the ramming pad at the angle required of the project. Clark said, “We set up on a dirt berm into the subsurface to get us to where we needed to be rather than build a big, elaborate platform. We needed to ram the conductor barrel in at 16 degrees, 28.1% grade. It was about two thirds underground and one third ramped above ground.”
Once the angle was established, the ramming platform was shored, and an auger bore track was set in place to drive the casing from. After the first 30-foot section of 54-inch casing was in place, crews used an excavator to lift the 24-inch diameter Grundoram Taurus into position. Prior to positioning the ramming tool, the ram cone was attached to the lead end of the rammer. This piece makes the connection between the 24-inch diameter rammer and the 54-inch diameter casing.
Melvin said, “Standard ramming gear is now available for casings as large as 120 inches in diameter. Having standard ramming gear for all those sizes of pipe makes everything a little easier for the people in the field pushing in casing. It reduces the amount of field fabrication significantly and ensures the most efficient transfer of power from the pipe rammer to the casing. That’s essential to successful ramming projects.”
Two 1600 CFM compressors were used to power the ramming tool. Crews proceeded to ram (3) 30-foot sections of pipe in for the first conductor barrel. Ramming moved as quickly as 1-foot per minute early in the ramming process. Once the first section of 30-foot casing was installed, the next segment was brought in and placed. That section was welded to the back end of the installed casing. Pipe set and welding took approximately 8 hours to complete per casing segment.
It was determined through discussions with landowners in the area that the soil conditions on the first site left something to be desired. Clark explained, “The first one, which was near the river, was mostly fill and garbage. There was one individual we talked to that knew or was related to the owner of that property and indicated that it had been filled in with garbage years ago. So, we literally went through garbage.”
As ramming traveled deeper toward bedrock, speed decreased significantly. Total working time to install all three segments for the first Conductor Barrel was six working days. Then crews moved the ramming gear and set up to the next site, which was a little bit deeper.

Iowa Trenchless crews installed both Conductor Barrel casings successfully, without incident, using the pneumatic pipe rammer.
According to Clark the site conditions improved on the second installation. He said, “The soil on the second one was better ground. This one was not on the river, but it was crossing railroad tracks and a few other obstacles. It started out as clay, then changed to sand and gravel. On the second one, the advancement rates were faster at the beginning, then we got into sand, gravel, and then eventually cobbles and boulders. It went from moving fast to moving moderately to moving slow to barely moving, which is what you’re looking for when you’re trying to get into the rock interface. In total that one was 180 feet.”
For both sites, Iowa Trenchless crews used bentonite lubrication in combination with the pipe ramming. Melvin said, “Ramming can be successfully completed with or without lubrication. It depends on the type of soil. Mud manufacturers can be a big help for lubrication/mud design for specific soil conditions. You need to decide whether to use mud at beginning of a ramming project because once you’ve started, it’s too late to add lubrication.”
Iowa Trenchless crews cleaned out portions of each Conductor Barrel casing with an auger boring machine before turning over the jobsites to the HDD contractor. Melvin said, “Great to work with these guys. Jason has a lot of experience, and his crews are right there too. Good project all around.”