• Link to Facebook
  • Link to X
  • Link to Youtube
  • Link to Rss this site
  • About
  • Events
  • Videos
  • Literature
  • Engineers
  • Links
  • Contact
Call: 1-800-533-2078
TT Technologies, Inc.
  • Products
      • GRUNDOMAT® Horizontal Boring Tool
      • GRUNDORAM® Pneumatic Pipe Ramming
      • GRUNDOCRACK® Pneumatic Pipe Bursting
      • GRUNDOBURST® Static Pipe Bursting System
      • GRUNDOTUGGER® Lateral Pipe Bursting
      • GRUNDODRILL 5X® Compact Directional Drill
      • Cable & Pipe Pusher
      • GRUNDOPIT® Pit Launched HDD
      • GRUNDOSPLIT Pipe Splitting Tooling
      • GRUNDOWINCH® Constant Tension Winch
      • GRUNDOMUDD™ Bentonite Mixing & Delivery
      • GRUNDO-AIR® Air Compressor
      • ALL Products
  • Methods
    • Pipe Bursting
    • Pipe Ramming
    • Horizontal Boring
    • Compact HDD
    • HDD Assist
    • Slick Bore
    • Split & Pull
    • Winch Applications
    • Cable & Pipe Pushing
    • All Methods
  • Applications
    • Railroad
    • Water
    • Sewer
    • Gas & Electric
    • FTTH, TELCOM & CATV
    • Pipeline
    • Lead Service Line Replacement
    • All Applications
  • Job Stories
  • News
  • Menu Menu
  • Products
    • GRUNDOMAT® Horizontal Boring Tool
    • GRUNDORAM® Pneumatic Pipe Ramming
    • GRUNDOCRACK® Pneumatic Pipe Bursting
    • GRUNDOBURST® Static Pipe Bursting System
    • GRUNDOTUGGER® Lateral Pipe Bursting
    • GRUNDODRILL 5X® Compact Directional Drill
    • Cable & Pipe Pusher
    • GRUNDOPIT® Pit Launched HDD
    • GRUNDOSPLIT Pipe Splitting Tooling
    • GRUNDOWINCH® Constant Tension Winch
    • GRUNDOMUDD™ Bentonite Mixing & Delivery
    • GRUNDO-AIR® Air Compressor
    • ALL Products
  • Methods
    • Pipe Bursting
    • Pipe Ramming
    • Horizontal Boring
    • Compact HDD
    • HDD Assist
    • Slick Bore
    • Split & Pull
    • Winch Application
    • Cable & Pipe Pushing
    • ALL Methods
  • Applications
    • Railroad
    • Water
    • Sewer
    • Gas & Electrical
    • FTTH, TELCOM & CATV
    • Pipeline
    • ALL Applications
  • Job Stories
  • News
  • About TT
    • About
    • Events
    • Videos
    • Literature
    • Engineers
    • Links
    • Contact
Articles
Photo1 Taurus Grundoram From Tt Technologies

Remote Railway Ramming: Total Trenchless, LTD. Up to the Challenge

September 20, 2024/in Railroad Applications, GRUNDORAM®, Job Stories, Pipe Ramming Job Stories, Pipe Ramming Methods/by TT Technologies
Grundoram Installation

For the remote access project near Kamloops, BC, Total Trenchless used two Grundoram Taurus pipe rammers from TT Technologies to install 12 casings, of various diameters, under an isolated rail line.

Defined by the tight urban and suburban locations where the cost of restoration is as high as the cost of closing streets and shutting down roadways, the reach of trenchless technology has grown beyond those confines and has expanded into some extremely remote areas. Working in remote access locations is difficult by any standard, but the inherent benefits of trenchless technology apply no matter the location or conditions.

And for certain contractors, working in difficult conditions is just another challenge to be overcome to get the job done. For Total Trenchless, LTD., Calgary, AB, Canada a recent railway pipe ramming project in British Columbia provided significant logistical and physical challenges.

According to Total Trenchless Safety/Field Operations Supervisor Jeff Corsie the remote nature of the project necessitated creative transportation options. He said, “We all stayed in Kamloops, BC and we’d drive about 25 minutes out of Kamloops to a marina. That’s where we’d leave our vehicles. Then we’d walk down to the docks, get on a boat every morning and take about a ten-minute boat trip across the lake to the work site. Then we walked from the shoreline up the hill to the work location. That’s how remote the jobsite was.”

The project consisted of the installation of 12 drainage casings, through pneumatic pipe ramming, under an isolated rail line outside of the Kamloops, BC area. The busy mainline railway is critical to moving imported and domestic cargo to the landlocked provinces to the east, the containers originate overseas and are handled at the port of Vancouver and loaded onto the railcars. The casings that Total Trenchless was installing ranged in diameter from 36 to 60 inches and with an installation length averaging 100 feet. Total Trenchless utilized two 24-inch diameter Grundoram Taurus pipe rammers from TT Technologies for the project.

The railway companies make rolling trains through a priority, even during a tough remote construction project.

Rick Melvin TT Technologies Pipe Ramming specialist said the tool was a good choice.  He explained, “The Taurus is ideal for that range of diameter and length of the rams. It can handle all that and more. So, the Taurus was a good equipment selection for this job.  And pipe ramming under railways is often the preferred trenchless method.  Pipe ramming allows for the casing installation without surface slump and when you’re talking railroads, that’s critical. The method was right, and the tool was right, but getting everything to the jobsite, that was the fun part!”

Established in 2018 by several experienced trenchless individuals, Total Trenchless is an indigenous-owned company that offers a range of trenchless options including horizontal auger boring, pipe ramming, guided horizontal auger boring, guided pipe ramming, pipe jacking and pipe bursting. The utility contractor operates throughout western Canada and is no stranger to remote access sites. That was just one of many challenges that Total Trenchless crews would face on this project.

Photo2 Grundoram With Ramming Gear

Crews utilized a special railcar, powered by excavator hydraulics, to shuttle in materials to the jobsite over six miles away.

Logistics

In order to transport the necessary equipment, casings and ramming gear to the jobsite locations, Total Trenchless used a Hytracker rail car.  Corsie explained, “So it’s an ordinary excavator. The operator crawls up onto the deck of the rail car. The hydraulics from the excavator are plumbed into that unit. So, the excavator physically drives that car that he’s sitting on, and then he’s able to put a cart on either side of him to carry cargo. This is something that is widely used up here in Canada anyway, for remote work.”

Corsie said, “When telling somebody about a remote rail job, people got to understand how in the world you would get your equipment to a place where there’s no roads.  Well, materials and equipment combined, I would say that those little tracker units probably made 20 trips to get everything we needed to do the job there.

It was approximately six miles by rail from location where crews could load the tracker unit to the initial jobsite location. After arriving at the first ram site, crews had to travel even further as ramming locations moved down the rail line.

Corsie said, “Some jobsite locations were closer than others. Some were quite a distance. Somewhere between a quarter of a mile and a third of a mile apart. The total span of the work area was probably about two miles. But we didn’t have any transportation options other than our own two feet. So that last install location was two miles from where we would start our day, where we get off the boat.”

As materials were brought out to the jobsite crews did their best to position the materials where they would be used. However, because of narrow right of ways along the rail line, a stockpile of material was created in one of the wider areas. This added to the logistical difficulty as the project continued moving further down the tracks.

Photo2

The project included ramming in new casings and decommissioning the existing drainage culverts under the rail line. Some culverts were over 90 years old.

Project Scope & Operations

For the project in Kamloops, Total Trenchless was contracted to install twelve casings to replace existing, aging culverts along the railway. Of the twelve installations one was 36 inches in diameter, another was 60 inches and the other ten were 48 inches in diameter. All installations ranged between 70 and 100 feet in length under the rail line.

According to Corsie, the ramming did not require building out an extensive ramming platform. He said, “Basically we just prepared that pad to the installation slope and the height to the invert of pipe. We let the pipe lay right on the ground as we installed it. We would ram in a short portion and then we’d check our elevation again. Small adjustments on elevation or the installation pitch were made if necessary. A 20-foot stick of pipe would only take about ten minutes to install.”

Melvin said, “There was no need to fabricate any ramming gear on site. Standard ramming gear is available for all the pipe diameters that were being installed on the Kamloops project. However, because of the remote nature of the site Jeff and his crew did bring some extra ram gear just in case.”

Trains, Spiders & Snakes

While ramming operations went smoothly, crews were still working around live railroad tracks and from time to time, they would need to stop operations. Corsie said, “On this project we had what they call a protecting foreman. That individual is very well-versed in rail procedures. He does the majority of the coordinating between the railway and the prime contractor. Every time a train came through our work area, westbound or eastbound, everyone was notified by radio that we have train traffic. And we basically had to stop working until that train passed and we received radio verification that we can go back to work.”

While crews used the mainline to transport the jobsite materials the carts needed to be moved off the mainline when trains came through. Sidetrack areas (or siding) were used to divert the equipment carts off the mainline to allow train traffic through.

Corsie said, “It made things difficult and slowed the work down. With twelve installations of this length in any other environment, this work would take us maybe three or four weeks. In this environment, it took about ten weeks to accomplish. Just because of the tight quarters and the logistical requirements. But we were able to overcome a lot of challenges because of Field Superintendent Rouel Aragon and his efforts to coordinate the installations, sort through logistics and ensure the quality of the installations.”

But train traffic and logistics were only a couple of aspects that added to the difficulty level of the project. The area itself provided its own challenges.

Corsie said, “One other thing that was ‘really fun’ about this project, that I didn’t know until I landed on that site, was that we are in the desert. So, if you added large cactuses to this environment, it would look just like Arizona. But being the desert here, we had a fair number of rattlesnakes and other scary things like black widow spiders.

“So, we had an environmental management guy on site that had us install a silt fence on each side of the work area. He insisted that this black silt fence be always standing as tall as possible, because that’s how we mitigated the snakes entering our work area!  And anytime that we did spot a snake inside or outside the fence line, we had to call this individual, and he would come and relocate these snakes. We would show up in the morning after leaving the site the day before and we would find snakes, both rattlesnakes and other types, in our work areas, even in the pipe.”

Photo2

In order to decommission the existing culverts, Total Trenchless brought a cement batch plant on site to mix cement to fill the old culverts and seal them off.

Finish It & Fill It Up

Once ramming was complete, Total Trenchless crews used an auger bore machine to clean the spoil out of the pipes. Crews brought along 36-inch augers for the 36-inch casing and cleaned the 60-inch and 48-inch casings with 48-inch augers to reduce the amount of gear they had to bring.

The scope of work on this project, however, went beyond the twelve installations and included ten decommissions as well. Corsie said, “We needed to decommission a lot of the existing culverts. Some were very old and in bad shape. So, we brought out a cement batch plant. And we were using bulk bags of material, and we were mixing material right on site and pumping it down these old culverts. After we filled them with grout, they were officially decommissioned.”

Melvin said, “This project had so many challenges, not to mention that the British Columbia wildfire season was rather severe this year. So, crews had to contend with that, along with temperatures consistently near the 100-degree mark. Pretty amazing project.”

 

 

Related equipment

  • GRUNDORAM® Pneumatic Pipe Ramming
Tags: Grundoram, GrundoRam Pipe Rammer, Railroad applications
https://www.tttechnologies.com/wp-content/uploads/2024/09/Photo1-Taurus-GrundoRam-from-TT-Technologies.jpg 480 640 TT Technologies https://www.tttechnologies.com/wp-content/uploads/2020/02/tt-technologies-logo-2020.png TT Technologies2024-09-20 12:31:422024-09-20 12:32:41Remote Railway Ramming: Total Trenchless, LTD. Up to the Challenge
You might also like
Grundoram ramming pipe Pipe Ramming Texas Style: Pumpco, Inc. Defeats Tough Soils in the Lone Star State
Photo2 Grundoram In Action The Pinnacle of Pilot Tube Pipe Ramming: Claude H. Nix Construction Achieves Pit Perfection and More!
Grundoram-Mocon Precision Ramming: Mocon Trenchless Provides Pipe Ramming Solution in San Diego
Grundoram-In-Ling-Contracting Large Diameter Pipe Ram Leaves Highway Undisturbed in Edmonton, Alberta
Roadway Pipe Ram: Staggs Environmental Construction Handles Heavy Traffic
Grundoram pipe ramming methods Tech Forum Pneumatic Pipe Ramming: Basics and Beyond

Search Articles

Search Search

Connect With Us

  • Facebook
  • Twitter
  • Youtube
  • Rss

Trenchless Leader

Each year more trenchless sewer, water, gas and electric rehabilitation and replacement projects are successfully completed with trenchless equipment from TT Technologies than any other. Read more →

Reach Us

TT Technologies, Inc.
2020 E New York Street
Aurora, IL 60502, USA

US. 1-800-533-2078
International. 1-630-851-8200
Email. info@tttechnologies.com

  • Sales Centers & Worldwide Distribution
Search Search

Connect With Us

  • Facebook
  • Twitter
  • Youtube
  • Rss

Trenchless Products

  • GRUNDOMAT® Horizontal Boring Tool
  • GRUNDORAM® Pneumatic Pipe Ramming
  • GRUNDOCRACK® Pneumatic Pipe Bursting
  • GRUNDOBURST® Static Pipe Bursting System
  • GRUNDOTUGGER® Lateral Pipe Bursting
  • GRUNDODRILL 5X® Compact Directional Drill
  • Cable & Pipe Pusher
  • GRUNDOPIT® Pit Launched HDD
  • GRUNDOSPLIT Pipe Splitting Tooling
  • GRUNDOWINCH® Constant Tension Winch
  • GRUNDOMUDD™ Bentonite Mixing & Delivery
  • GRUNDO-AIR® Air Compressor

Latest News

  • SKE Construction Photo 1
    SKE Construction’s Pre-chlorinated Pipe Bursting Program A Model of Efficiency!October 8, 2026 - 4:18 pm
  • Water Main Drawing Jobsite
    Distribution System Pipe Bursting: Good Practice BasicsSeptember 21, 2026 - 9:08 am
  • WESTT Photo 7
    Restoring a Critical Water Transmission Main in Southern California Using Pipe BurstingSeptember 14, 2026 - 2:37 pm
  • Lateral Bursting Photo1
    A Tale of Two Laterals: Pipe Bursting Takes Center StageJune 2, 2026 - 2:29 pm
Copyright © 2001 - TT Technologies, Inc. All Rights Reserved.
  • Terms and Conditions
  • Terms of Usage
  • Privacy Statement
  • Limited Warranty
  • Patents
  • Site Map
Link to: Roadway Pipe Ram: Staggs Environmental Construction Handles Heavy Traffic Link to: Roadway Pipe Ram: Staggs Environmental Construction Handles Heavy Traffic Roadway Pipe Ram: Staggs Environmental Construction Handles Heavy TrafficPhoto3 Install 54 Inch Casing2 Link to: Under the River and to the Camp: Allstate Boring All-Stars Complete Horizontal & Vertical Pipe Rams Link to: Under the River and to the Camp: Allstate Boring All-Stars Complete Horizontal & Vertical Pipe Rams Photo 3 Horizontal Pipe RammingUnder the River and to the Camp: Allstate Boring All-Stars Complete Horizontal...
Scroll to top Scroll to top Scroll to top