Restoring a Critical Water Transmission Main in Southern California Using Pipe Bursting
When a critical water transmission main began failing repeatedly, Trabuco Canyon Water District, located in Southern California, found itself in an increasingly costly position. Each repair appeared successful—until the pipeline was pressurized again. Then another section failed.
The transmission main, a 14-inch and 16-inch cement mortar-lined and coated welded steel pipeline installed in 1964, carried treated drinking water nearly four miles from the district’s water treatment plant to its distribution system. As failures multiplied, the district had little choice but to shut down its most economical water supply source and begin purchasing treated water from a neighboring agency to maintain service to customers.
Every day the pipeline remained out of service increased operating costs while placing pressure on the district to restore the line as quickly as possible. Replacing the pipeline would ultimately require more than simply selecting a construction method—it would demand a collaborative effort between the owner, consulting engineer, equipment manufacturer, and trenchless contractor to balance technical risk, construction speed, budget limitations and environmental constraints.
The result was a hybrid rehabilitation strategy that restored nearly 2.4 miles of critical pipeline while demonstrating how thoughtful engineering and experienced field execution can successfully solve even the most challenging infrastructure emergencies.

Pipeline alignment
A Pipeline with No Margin for Delay
The transmission main follows Trabuco Creek through southern Orange County, California, connecting the district’s water treatment plant to the distribution system that serves the community.
Constructed decades before suburban development transformed the surrounding area, the original alignment traversed what were once orchards and open land. Over time, the corridor evolved into a heavily used recreational area featuring mature trees, environmentally sensitive creek banks and a popular public bike trail.
When the aging steel pipeline began experiencing structural failures, repairing isolated sections quickly proved ineffective. Each time their crews repaired a break and restored pressure, another weak section of pipe failed somewhere else along the alignment. With emergency water purchases rapidly increasing operating expenses, restoring the transmission main became both an operational necessity and a financial priority.
Evaluating the Rehabilitation Options
The district engaged a consulting engineer to evaluate alternatives that could restore service quickly while minimizing both construction impacts and overall project costs.
One early concept involved rehabilitating the entire pipeline using a loose-fit Flexible Fabric Reinforced Pipe (FFRP) liner. The approach offered several attractive advantages, including limited permitting requirements, minimal public disruption and an accelerated procurement process without the need for extensive design documents.
However, hydraulic modeling revealed a critical limitation—although the smoother liner would improve hydraulic efficiency, the reduced internal diameter would create enough head loss that the existing pumps at the water treatment plant could no longer deliver the required flow. That finding prompted engineers to expand the alternatives analysis to include close-fit FFRP systems, pressure-rated cured-in-place pipe (CIPP), open-cut replacement and pipe bursting.
The operating pressures—reaching approximately 300 psi near the treatment plant—effectively eliminated pressure CIPP as a practical option. Open-cut replacement remained technically feasible but presented its own challenges, including excavation adjacent to Aliso Creek, impacts to mature vegetation, disruption of the bike trail and uncertainty surrounding the exact location of the original 1964 pipeline. Instead of searching for a single solution that fit every condition, the project team began evaluating where each rehabilitation method could provide the greatest value.
The approach also reflected another practical consideration—district maintenance personnel had identified portions of the transmission main that were in significantly worse condition than others. Rather than attempting to replace the entire system immediately, the project focused available funding on the most critical segments, allowing the transmission main to return to service much sooner.

Test section of cement-lined, cement-coated steel pipe – showing successful splitting and expansion.
Reducing Risk Before Construction Began
One of the most significant questions involved pipe bursting. Bursting aging steel water mains presents unique challenges because steel wall thickness, corrosion and previous repairs can vary significantly along the alignment. Rather than discovering those unknowns during construction, the district sought to reduce uncertainty before bidding the project.
Working with trenchless equipment manufacturer TT Technologies, Aurora, Ill., the engineering team removed a section of failed pipeline from the system and shipped it to the manufacturer’s testing facility in Illinois. There, the recovered pipe was successfully burst using tooling specifically configured for the material.
The testing confirmed that bursting the existing cement mortar-lined steel pipe was achievable while also identifying the cutter configuration and equipment necessary for successful field installation. That relatively simple step significantly reduced construction risk while providing both the owner and prospective contractors greater confidence in the selected approach.
A Hybrid Solution Maximizes Value

Simple drawing showing pipe size details, alignment, and profile.
With bursting confirmed as a viable option, the district adopted a hybrid rehabilitation strategy that matched construction methods to existing site conditions. Approximately 4,400 linear feet of pipeline located beneath roadways would be rehabilitated using loose-fit FFRP, eliminating extensive pavement restoration and traffic control requirements while accommodating the system’s high operating pressures.
The remaining 8,800 feet following the creek corridor and bike trail would be replaced using pipe bursting and fusible C900 PVC pipe. To further protect the owner’s interests, bid documents also included open-cut replacement as an alternate, allowing contractors to determine whether trenchless installation truly represented the best value.
Equally important, the engineering team intentionally resisted overdesigning the project. Rather than producing an extensive set of construction documents, engineers relied on original as-built drawings, publicly available aerial photography and contours to define the approximate pipeline alignment. Given the emergency timeline and the contractor’s expertise, that level of design proved sufficient for competitive bidding while avoiding months of additional survey work and engineering effort.
The strategy reflected a simple philosophy–provide enough information to build the project safely while allowing experienced contractors the flexibility to determine the most efficient means and methods.

Walking and bike path open during pipe bursting – minimal disruption
Construction Begins Along a Busy Recreational Corridor
The construction contract was ultimately awarded for approximately $6.1 million—well below early planning estimates—and Morrow Trenchless, San Clemente, Calif. was selected to perform the pipe bursting work.
From the outset, logistics presented one of the project’s greatest challenges. Unlike many pipeline replacement projects, the district wanted to maintain public access along the heavily used bike trail throughout construction. Rather than closing the corridor, crews were required to share the space with cyclists and pedestrians while moving specialized equipment, hauling excavated material and positioning pipe strings.
Site access points were located roughly one and one-half miles apart, meaning equipment and materials often had to travel long distances through the narrow corridor. Those logistical constraints influenced virtually every aspect of construction planning.
Bursting the Existing Steel Main
Construction began at the downstream end of the alignment by replacing an existing 16-inch steel main with 16-inch DR14 fusible C900 PVC. Although nominal pipe diameters remained the same, the new pipe measured approximately 17.4 inches outside diameter, requiring bursting heads approaching 20 inches in diameter to fracture the existing steel pipe while simultaneously expanding the surrounding soil.
Initial bursting operations proceeded largely as expected. Typical pulling forces ranged between 120 and 150 tons as approximately 500-foot installation sections were completed. However, like many rehabilitation projects involving aging infrastructure, existing conditions soon introduced unexpected challenges.
Several previous repairs had not been fully documented. Although closed-circuit television inspections identified portions of the pipeline before construction, accumulated debris prevented complete inspection of every segment. Eventually crews encountered heavily reinforced welded repair sections that could not be burst.
Rather than forcing equipment beyond its intended limits, crews excavated those isolated locations, removed the problematic sections and resumed bursting operations. The approach minimized delays while maintaining production.

FPVC inside HDPE shown on walking and bike path being moved into place
Protecting the New Pipeline
Transporting hundreds of feet of fusible PVC through the project corridor presented another unique challenge. Pipe supplied by Underground Solutions, San Diego, Calif., was fused in a centralized staging area before installation. To protect the PVC while dragging it to insertion pits, crews inserted each fused section into a slightly larger HDPE sleeve approximately 500 feet long.
The HDPE acted as a sacrificial protective jacket while the pipe was pulled, sometimes more than a mile, along the bike trail before installation. The system reduced handling damage while allowing long pipe strings to be positioned efficiently despite limited site access.
Expecting the Unexpected Underground
Approximately 2,000 feet into the project, crews encountered the planned transition from the original 16-inch pipeline to an existing 14-inch main. The transition fitting required excavation so cutters could be resized appropriately before bursting continued.
Despite the smaller pipe diameter, bursting operations continued with pulling forces generally comparable to those experienced earlier in the project. As installation progressed, however, natural variations in soil conditions and pipeline alignment occasionally increased bursting forces.
Several sections followed gradual horizontal curves where the original steel pipe had been installed using joint deflections. While most of these curves were negotiated successfully, localized changes in alignment occasionally produced significantly higher pulling loads.
The project team also investigated several locations identified during CCTV inspection as containing internal hand holes—access openings historically used to apply internal cement mortar during repairs or at heavily deflected joints.
Some excavations proved worthwhile, exposing potential obstructions before bursting operations reached them. Others confirmed that suspected obstacles could safely remain in place. Experience and field judgment ultimately dictated which conditions warranted intervention and which could simply be managed during installation.

Typical pipe bursting launch pit with tooling, expander, and new FPVC entering steel pipe
Adapting to New Challenges
Because construction was progressing successfully, the district elected to expand the project by adding approximately 2,000 additional feet of replacement pipeline. That decision introduced one final surprise. As-built drawings identified the remaining pipeline as 14-inch steel. After excavation, crews discovered portions of the line were 10-inch pipe.
Rather than redesigning the project, Morrow Trenchless fabricated a custom extension for its multi-stage bursting head incorporating a cutter sized for the 10-inch steel while progressively expanding to accommodate installation of the 17.4-inch fusible PVC.
Upsizing pipe to that extent is generally avoided, but the contractor’s familiarity with the equipment, soil conditions and existing pipeline provided confidence that the installation could be completed safely.
Not every section cooperated. In isolated areas, bursting forces exceeded either the capacity of the pulling system or the structural capacity of the machine pit’s reaction wall. When those situations occurred, crews excavated directly above the stalled bursting head to relieve localized soil pressure before resuming operations.
Once confinement was removed, the bursting equipment again advanced normally. The solution illustrated a hallmark of successful trenchless construction—adapting to changing underground conditions without losing sight of the overall objective.

Adapting by using two cutters enter the 10” steel splitting and pulling in new 16-inch FPVC
Collaboration Drives Success
Over approximately two months, nearly 10,000 linear feet of pipeline was successfully replaced through pipe bursting while other project segments were completed using open-cut construction or rehabilitation methods where conditions made those approaches more practical.
Perhaps equally significant, construction was completed while maintaining public access along the popular bike trail, limiting excavation to selected locations and minimizing impacts to surrounding natural resources. For the district, the project restored its preferred water supply source and eliminated the ongoing expense of purchasing replacement water from neighboring agencies. For the project team, it demonstrated that emergency infrastructure replacement does not necessarily require lengthy design schedules or one-size-fits-all solutions.
Instead, success resulted from matching the appropriate rehabilitation technology to each pipeline segment, validating technical risks before construction began and relying on close collaboration between owner, engineer, equipment manufacturer and contractor throughout the project.
Authors:
Adam Brown – BKF Engineers
Rob Morrow – Morrow Trenchless
George Mallakis – TT Technologies, Inc.