• Link to Facebook
  • Link to X
  • Link to Youtube
  • Link to Rss this site
  • About
  • Events
  • Videos
  • Literature
  • Engineers
  • Links
  • Contact
Call: 1-800-533-2078
TT Technologies, Inc.
  • Products
      • GRUNDOMAT® Horizontal Boring Tool
      • GRUNDORAM® Pneumatic Pipe Ramming
      • GRUNDOCRACK® Pneumatic Pipe Bursting
      • GRUNDOBURST® Static Pipe Bursting System
      • GRUNDOTUGGER® Lateral Pipe Bursting
      • GRUNDODRILL 5X® Compact Directional Drill
      • Cable & Pipe Pusher
      • GRUNDOPIT® Pit Launched HDD
      • GRUNDOSPLIT Pipe Splitting Tooling
      • GRUNDOWINCH® Constant Tension Winch
      • GRUNDOMUDD™ Bentonite Mixing & Delivery
      • GRUNDO-AIR® Air Compressor
      • ALL Products
  • Methods
    • Pipe Bursting
    • Pipe Ramming
    • Horizontal Boring
    • Compact HDD
    • HDD Assist
    • Slick Bore
    • Split & Pull
    • Winch Applications
    • Cable & Pipe Pushing
    • All Methods
  • Applications
    • Railroad
    • Water
    • Sewer
    • Gas & Electric
    • FTTH, TELCOM & CATV
    • Pipeline
    • Lead Service Line Replacement
    • All Applications
  • Job Stories
  • News
  • Menu Menu
  • Products
    • GRUNDOMAT® Horizontal Boring Tool
    • GRUNDORAM® Pneumatic Pipe Ramming
    • GRUNDOCRACK® Pneumatic Pipe Bursting
    • GRUNDOBURST® Static Pipe Bursting System
    • GRUNDOTUGGER® Lateral Pipe Bursting
    • GRUNDODRILL 5X® Compact Directional Drill
    • Cable & Pipe Pusher
    • GRUNDOPIT® Pit Launched HDD
    • GRUNDOSPLIT Pipe Splitting Tooling
    • GRUNDOWINCH® Constant Tension Winch
    • GRUNDOMUDD™ Bentonite Mixing & Delivery
    • GRUNDO-AIR® Air Compressor
    • ALL Products
  • Methods
    • Pipe Bursting
    • Pipe Ramming
    • Horizontal Boring
    • Compact HDD
    • HDD Assist
    • Slick Bore
    • Split & Pull
    • Winch Application
    • Cable & Pipe Pushing
    • ALL Methods
  • Applications
    • Railroad
    • Water
    • Sewer
    • Gas & Electrical
    • FTTH, TELCOM & CATV
    • Pipeline
    • ALL Applications
  • Job Stories
  • News
  • About TT
    • About
    • Events
    • Videos
    • Literature
    • Engineers
    • Links
    • Contact
Articles

Swage Lining with Static Bursting Equipment in Berlin

September 1, 2006/in General Job Stories/by TT Technologies
Swage Lining in Berlin, Germany

The swage line project took place in Berlin, Germany. Limited working space required a trenchless application.

Contractor Ludwig Pfeiffer Hoch-und Tiefbau GmbH & Co. KG was recently contracted by the Berlin Waterworks, Berlin, Germany, to rehabilitate a sanitary sewer pressure pipe, in the city of Berlin, using the swage line-method. The goal of the project was to renew the ND 1000 (39-in.) steel sanitary sewer pressure pipe a total length of approximately 600 m (2000 ft.) in order to accommodate higher pressure levels.

The host pipe ran under a street in a residential area. Numerous restaurants and shops are located in the neighborhood, so an open trench method would have been extremely disruptive. In order to avoid the disruption and wide range closures, the Berlin Waterworks intend to pull in a PE-liner in two sections into the old pipe without any annular space using the cold swage line application. This process is in accordance with the local water regulations.

The Pfeiffer Company often uses the cold swage line-method for projects like this. During this process a PE-Inliner is pulled into the old pipe within the diameter of the existing host pipe without the use of any heat and in a reduced size. This way the pipes from ND 100 up to ND 1200 (4 to 50 in.) with installation lengths of up to 1000 m (3300 ft.) can be restored utilizing this method.

The Pfeiffer Company has a good deal of experience with static pipe bursting, specifically with the Grundoburst static pipe bursting system from trenchless equipment manufacturer TT Technologies, Aurora, Ill, USA (a subsidiary of Tracto-Technik, Lennestadt, Germany). According to TT Technologies product specialist Collins Orton, while the Grundoburst unit is designed for static pipe bursting, it is also very effective for other trenchless applications. He said, “Static bursting systems can be used for these types of applications. In essence, the processes are very similar. In a swage line or even a slipline situation, however, there is no need to burst the host pipe. But each method does require the pulling in of a new product pipe and that’s where the similarities lie. And that’s why static bursting units can be used in all three scenarios.”

Swage Lining, Grundoburst Static Bursting Machine

The Pfeiffer Company utilized a Grundoburst 2500G static bursting
unit to complete the swage line. The Grundoburst unit provided the power needed for the project and took up less space than a comparable winch system.

At the jobsite in Berlin the Pfeiffer Company used the largest static pipe bursting unit available, the Grundoburst 2500G from TT Technologies.

Static Bursting & Swage Lining

During a typical static bursting process, a hydraulically powered bursting unit pulls specially designed bladed rollers are pulled through an existing line. As the bladed rollers are pulled through, they split the host pipe. An expander attached to the rollers forces the fragmented pipe into the surround soil while simultaneously pulling in the new pipe. For the swage line project in Berlin, the hydraulic bursting unit would be used to pull the swaged pipe into place. A very large bursting unit would be needed.

Orton said, “In this particular case the contractor chose to use the bursting unit instead of a winch because of the space limitations of the project. The Grundoburst 2500G provides up to 2550 kN (650,000 lbs) of pullback, enough to meet the requirements of the cold swage line method and still take up less space than a comparable winch system. Looking at it logistically, it is easier to move the bursting machine than a comparable winch.”

On The Job

The construction work in Berlin was divided into two sections. Crews dug a launch pit near the middle of the run, creating a run of 322 meters (1050 ft.) in on direction and a run of 216 meters (700 ft.) in the other. After a high-pressure cleaning process of the existing pipe, where all loose particles are removed, a camera inspection was performed. Build up within the pipe was removed mechanically with a scratching tool. For swage-lining a metallic smooth surface is not necessary, but any possible obstacles within the old pipe should be removed.

During the swage lining process, the oversized pipe is reduced in diameter to about 10% less than the inside diameter of the host pipe. The swaged down pipe is pulled in to the host pipe and allowed to return to its original diameter. Because the pipe cannot actually reach its original diameter, it becomes tight against the wall of the host pipe. In this case the new pipe was 3% bigger. As soon as the pulling force is relieved, the pipe tries to return to its original diameter again. But the inner diameter of the existing pipe limits it.

According to Orton, as crews fused together the necessary lengths of HDPE, the inner and the outer welding beads were removed from the pipe. He said, “The exterior and interior weld beads are removed to allow the PE pipe to pass through the reduction die without getting stuck. Removal of the exterior bead is done with a special skiving knife that removes the bead in a matter of seconds. The internal bead is removed with a tool similar to the bead trimmer commonly found in the US. This tool reaches back into the pipe just after the fusion weld is cooled and deploys a cutter and spacing gauge that then are rotated from the end of the pipe. The rotation carves the bead off. This procedure takes a few minutes per joint.”

Swage Lining in Process

The existing ND 1000 (39-in.) steel line with ND 1030 (40.5-inch) HDPE 100. During the swage line process, the HDPE product pipe is pulled through a reducing dye to enable it to fit inside of the host pipe. Once inside, the HDPE attempts to return to its original size forming a tight fit within the host pipe.

A pulling head was welded to the front the first section of pipe to be installed. Crews positioned the Grundoburst in the launch pit and rodded the first section of pipe with the Quicklock bursting rods. Once at the launch pit, the connection was made between the Quicklock rods and the product pipe. Once established, crews began the swage lining process. The static bursting unit pulled the HDPE through the reduction tool and the swage lining die, in order to reduce the pipe’s diameter. Crews monitored the pulling force constantly to make sure it stayed within the permissible limits for the PE-pipe. To keep the friction losses as low as possible, environmental friendly anti-seize fluids are applied. The pipe then continued on into the host pipe until fully installed.

Once the first section was in place, the bursting unit was rotated 180 degrees and crews set to work on the next section, utilizing the same launch pit.

Orton said, “A strong steady pulling force is exerted to pull the entire length of pipe to be replaced through a reducing die setup. The die is tapered and will accept the O.D. of the new PE pipe, it then continues through a funnel shaped die that continues to reduce the diameter of the PE pipe to a predetermined diameter, approximately 10 percent smaller than the I.D. of the host pipe. The process can be interrupted at any time, for example to butt-weld pre-fabricated pipe lengths together. The deformation and installation speed with this dimension is between 50 and 100 m (170 to 330 ft.) per hour, therefore pipe lengths from 300 to 600 m (1000 to 2000 ft.) lengths can be pulled in, without any problem, in one day’s work.”

For the project in Berlin, HDPE 100 with dimensions 1030 x 60,6 (40.5 in., SDR 17, PN 10) was chosen. Due to the large diameter, which in a typical swage line is generally about 3 percent greater than the host pipe, a 100 percent tight and durable fit of the PE-liner inside the old pipe is created.

After both pipe sections were successfully pulled in, pre-welded sockets with flanges were welded to each end of each pipe length to complete the installation. After assembly of the end flange a pressure check was carried out, as well as a final camera inspection.

The new PE-liner has the quality of a new pipe after the installation and can carry all loads from the ground and traffic, as well as the internal pressure without effects by the old pipe. Due to the very good hydraulic characteristics of the HDPE-pipe further flow reduction is not expected.

Trenchless Technology International Sept/Oct 2006

Related equipment

  • GRUNDOBURST® Static Pipe Bursting System
Tags: Quicklock Bursting Rods, Static Pipe Bursting, Swage Lining
https://www.tttechnologies.com/wp-content/uploads/2015/09/swage-lining-01.jpg 225 150 TT Technologies https://www.tttechnologies.com/wp-content/uploads/2020/02/tt-technologies-logo-2020.png TT Technologies2006-09-01 16:52:072016-09-19 14:16:09Swage Lining with Static Bursting Equipment in Berlin
You might also like
Grundocrack in Entry Pit The Expanding World of Pipe Bursting: An Inside Look
The static pipe bursting unit position in the exit pit. Lake Tahoe Steel Water Main Replacement via Pipe Bursting
TT Technologies Constant Tension Winches for Pipe Bursting & Trenchless Applications
Grundoburst in Action Product Pipe Material Options For Pipe Bursting
Grundoburst 1000G Gas & Water Markets Ready for Static Pipe Bursting In North America
PE pipe reduction die Pulling Power in Amarillo, TX AJM Pipelines Bringing Swagelining Back

Search Articles

Search Search

Connect With Us

  • Facebook
  • Twitter
  • Youtube
  • Rss

Trenchless Leader

Each year more trenchless sewer, water, gas and electric rehabilitation and replacement projects are successfully completed with trenchless equipment from TT Technologies than any other. Read more →

Reach Us

TT Technologies, Inc.
2020 E New York Street
Aurora, IL 60502, USA

US. 1-800-533-2078
International. 1-630-851-8200
Email. info@tttechnologies.com

  • Sales Centers & Worldwide Distribution
Search Search

Connect With Us

  • Facebook
  • Twitter
  • Youtube
  • Rss

Trenchless Products

  • GRUNDOMAT® Horizontal Boring Tool
  • GRUNDORAM® Pneumatic Pipe Ramming
  • GRUNDOCRACK® Pneumatic Pipe Bursting
  • GRUNDOBURST® Static Pipe Bursting System
  • GRUNDOTUGGER® Lateral Pipe Bursting
  • GRUNDODRILL 5X® Compact Directional Drill
  • Cable & Pipe Pusher
  • GRUNDOPIT® Pit Launched HDD
  • GRUNDOSPLIT Pipe Splitting Tooling
  • GRUNDOWINCH® Constant Tension Winch
  • GRUNDOMUDD™ Bentonite Mixing & Delivery
  • GRUNDO-AIR® Air Compressor

Latest News

  • SKE Construction Photo 1
    SKE Construction’s Pre-chlorinated Pipe Bursting Program A Model of Efficiency!October 8, 2026 - 4:18 pm
  • Water Main Drawing Jobsite
    Distribution System Pipe Bursting: Good Practice BasicsSeptember 21, 2026 - 9:08 am
  • WESTT Photo 7
    Restoring a Critical Water Transmission Main in Southern California Using Pipe BurstingSeptember 14, 2026 - 2:37 pm
  • Lateral Bursting Photo1
    A Tale of Two Laterals: Pipe Bursting Takes Center StageJune 2, 2026 - 2:29 pm
Copyright © 2001 - TT Technologies, Inc. All Rights Reserved.
  • Terms and Conditions
  • Terms of Usage
  • Privacy Statement
  • Limited Warranty
  • Patents
  • Site Map
Link to: Pacific Liners Static Pipe Bursting: Replacing Steel with C900 PVC in South Lake Tahoe Link to: Pacific Liners Static Pipe Bursting: Replacing Steel with C900 PVC in South Lake Tahoe Pacific Liners Static Pipe Bursting: Replacing Steel with C900 PVC in South...Pacific Liners Static Pipe Bursting Link to: With A Little Help From My Friends: Sunland Construction Completes Large Diameter Pullback with HDD Ram Assist Link to: With A Little Help From My Friends: Sunland Construction Completes Large Diameter Pullback with HDD Ram Assist Grundoram Taurus Pipe RammerWith A Little Help From My Friends: Sunland Construction Completes Large Diameter...
Scroll to top Scroll to top Scroll to top