• Link to Facebook
  • Link to X
  • Link to Youtube
  • Link to Rss this site
  • About
  • Events
  • Videos
  • Literature
  • Engineers
  • Links
  • Contact
Call: 1-800-533-2078
TT Technologies, Inc.
  • Products
      • GRUNDOMAT® Horizontal Boring Tool
      • GRUNDORAM® Pneumatic Pipe Ramming
      • GRUNDOCRACK® Pneumatic Pipe Bursting
      • GRUNDOBURST® Static Pipe Bursting System
      • GRUNDOTUGGER® Lateral Pipe Bursting
      • GRUNDODRILL 5X® Compact Directional Drill
      • Cable & Pipe Pusher
      • GRUNDOPIT® Pit Launched HDD
      • GRUNDOSPLIT Pipe Splitting Tooling
      • GRUNDOWINCH® Constant Tension Winch
      • GRUNDOMUDD™ Bentonite Mixing & Delivery
      • GRUNDO-AIR® Air Compressor
      • ALL Products
  • Methods
    • Pipe Bursting
    • Pipe Ramming
    • Horizontal Boring
    • Compact HDD
    • HDD Assist
    • Slick Bore
    • Split & Pull
    • Winch Applications
    • Cable & Pipe Pushing
    • All Methods
  • Applications
    • Railroad
    • Water
    • Sewer
    • Gas & Electric
    • FTTH, TELCOM & CATV
    • Pipeline
    • Lead Service Line Replacement
    • All Applications
  • Job Stories
  • News
  • Menu Menu
  • Products
    • GRUNDOMAT® Horizontal Boring Tool
    • GRUNDORAM® Pneumatic Pipe Ramming
    • GRUNDOCRACK® Pneumatic Pipe Bursting
    • GRUNDOBURST® Static Pipe Bursting System
    • GRUNDOTUGGER® Lateral Pipe Bursting
    • GRUNDODRILL 5X® Compact Directional Drill
    • Cable & Pipe Pusher
    • GRUNDOPIT® Pit Launched HDD
    • GRUNDOSPLIT Pipe Splitting Tooling
    • GRUNDOWINCH® Constant Tension Winch
    • GRUNDOMUDD™ Bentonite Mixing & Delivery
    • GRUNDO-AIR® Air Compressor
    • ALL Products
  • Methods
    • Pipe Bursting
    • Pipe Ramming
    • Horizontal Boring
    • Compact HDD
    • HDD Assist
    • Slick Bore
    • Split & Pull
    • Winch Application
    • Cable & Pipe Pushing
    • ALL Methods
  • Applications
    • Railroad
    • Water
    • Sewer
    • Gas & Electrical
    • FTTH, TELCOM & CATV
    • Pipeline
    • ALL Applications
  • Job Stories
  • News
  • About TT
    • About
    • Events
    • Videos
    • Literature
    • Engineers
    • Links
    • Contact
Articles
Photo2 Grundoram In Action

The Pinnacle of Pilot Tube Pipe Ramming: Claude H. Nix Construction Achieves Pit Perfection and More!

October 23, 2025/in Railroad Applications, GRUNDORAM®, Job Stories, Pipe Ramming Job Stories, Pipe Ramming Methods/by TT Technologies
Photo1 Flooded Entry Pit

In order to keep the concrete from lifting, we had to keep the water in the pit to equalize the pressure and prevent the concrete from floating and lifting. We had to pump the concrete to the bottom of the pit with a tremie tube, pumping it from the bottom up. We created a 5-foot-thick seal slab of concrete for the pit floor. That was challenging.”

A tough project needs a great contractor to achieve an amazing result. That’s exactly what took place recently in Salt Lake City, UT.  Claude H. Nix Construction/Jasco, Inc (Nix Construction), Ogden, UT. is one of the premier trenchless contractors in the country. Family-owned and operated since 1974, Nix Construction is well known for quality of work, dependability and a commitment to safety. All these qualities and more would be brought to bear for a recent project in Salt Lake City.

The 1800 North Sewer Realignment – Phase 1 project consisted of a gravity sewer system installed under a rail yard and Interstate Highway I-15. The installation required precision, extensive dewatering, innovative pit design and construction, as well as effective communication and coordination between a variety of local and regional entities. Nix Construction was more than up to the challenge.

Owner Stephanie Nix-Thomas outlined the complexity of the project. She said, “The installation included four precisely installed 36-inch steel casings under twelve sets of rail tracks and two 36-inch steel casings under Interstate 15. We needed to construct three pits for the effort. Two were innovative secant pile construction and one was sheet piles. All were dug ‘in the wet’ and poured under water, ensuring they were watertight.”

For the installation of the casings, trenchless pilot tube and pipe ramming methods were chosen. Pipe Ramming Specialist Rick Melvin with trenchless equipment manufacturer TT Technologies, Aurora, Ill. explained how the two methods work together. He said, “When extremely accurate casing installation is required, using pipe ramming in conjunction with the pilot tube method can help achieve those results. The contractor can place pilot tubes through the ground very accurately with the assistance of the line and grade control system and a hydraulic jacking frame. Once the pilot tubes are in place, an adapter is used to make a transition to the casing that’s being installed. The casing basically follows the pilot tube’s path, resulting in a very accurate, line and grade installation.”

To facilitate the ramming, Nix Construction chose a Grundoram Taurus pneumatic pipe ramming system for TT Technologies.

Photo2 Grundoram in action

The relocation project planned to split up the flow from the trunk line and convey it across multiple 24-inch pipes placed within 36-inch steel casings under one of the highest priority transportation corridors in North Central Utah.

Project Overview

The existing 60-inch reinforced concrete pipe sewer trunk was constructed in 1960. The aging system conveys 23 million gallons per day of wastewater from downtown Salt Lake City. The city had been seeking to replace and relocate it since 2016.  

The relocation project planned to split up the flow from the trunk line and convey it across multiple 24-inch pipes placed within 36-inch steel casings under one of the highest priority transportation corridors in North Central Utah. Steel casings would be installed within several vertical feet of railroad ties and petroleum and gas facilities in what Nix-Thomas described as, “threading the needle.” These multiple carrier pipelines were to be installed at elevations and slopes required for gravity flow, while maintaining capacity, and, without disruption.

Teamwork Makes the Trenchless Work

According to Nix-Thomas, the design team did a good job of identifying anticipated challenges, such as high ground water, narrow band of suitable geology for the construction methodology, and the need to monitor groundwater. What no one anticipated was the amount of teamwork, communication, and coordination that would be required.

Nix-Thomas said, “Although the designers and the city had worked extensively with the stakeholders in the area, when construction started, the tracking system developed by the city and the communication process of the entire team became paramount to effectively manage the project. That communication system kept the entire process transparent. This project had complex geology, high ground water and expensive surface assets, but both the use of trenchless techniques and innovative communication tools provided an excellent project and a good example for future projects.

 “Teamwork was essential for regulatory compliance, construction coordination, and safety. This challenging project was successful thanks to multiple Salt Lake City departments, Waterworks Engineers, Salt Lake City, UT, Bennett Trenchless, Folsom, CA and multiple company representatives.”

Photo3 Grundoram under Railroad

One of the most significant challenges was excavating the pits. The pit construction included secant pile shafts and pit seals. Secant piles allowed the construction of large 45- by 60-foot and 35- by 45-foot open space pit areas.

Pit Construction Plus

One of the most significant challenges was excavating the pits. The pit construction included secant pile shafts and pit seals. Secant piles allowed the construction of large 45- by 60-foot and 35- by 45-foot open space pit areas. Compared with more traditional trench boxes or sheet pile pits that require spreader bars or whalers, the secant pit areas were safer and easier to work in.

Nix Construction Precision Manager Perry Seal explained, “There were three pits constructed total. Two outside pits and one in the middle. The area was extremely wet. We had to excavate the pits using GPS guided dig control because of the amount of ground water. But we needed that ground water too. In order to keep the concrete from lifting, we had to keep the water in the pit to equalize the pressure and prevent the concrete from floating and lifting. We had to pump the concrete to the bottom of the pit with a tremie tube, pumping it from the bottom up. We created a 5-foot-thick seal slab of concrete for the pit floor. That was challenging.”

Nix crews poured over 3,000 cubic yards of concrete between secants and seal slabs in all three pits. Melvin said, “The construction of the pits definitely highlighted the high level of quality that Nix Construction is known for in the underground utility industry. The depths of the excavations before pouring the 5-foot-thick slabs ranged from 12 to17 feet underwater. That’s impressive.”

Seal said, “We also needed to notch the secant walls before pouring the concrete.

We used our concrete grinder, that goes on the track hoe and put it down in the water to grind a notch, a channel, along the concrete secant so that when we poured the concrete slab floor, it would kind of lock in place. Again, to limit buoyancy.”

Photo4 Grundoram in action

The rail yard and the highway run parallel to one another. We pushed all the pilot tubes from the center pit out. We set up four auger bore machine tracks. Our GBM mounts on the tracks, so everything stays on the same center line.

Pilot Tube Pipe Ramming

The installation of four pipelines under the rail yard (12 sets of tracks, 10 commercial and two local commuter train tracks), and two pipelines under I-15, needed to be installed exactly parallel on a 0.4% grade under groundwater that, at one location, was artesian.

Seal said, “The rail yard and the highway run parallel to one another. We pushed all the pilot tubes from the center pit out. We set up four auger bore machine tracks. Our GBM mounts on the tracks, so everything stays on the same center line. Each pilot tube installation took about two days with setup and push. And then probably another day to get a 4-inch pipe in place and then move on to the next one.”

Because of the soil with heavy water concentration, Nix crews did not want to leave the pilot tubes in the ground for an extended amount of time. So, after each pilot tube install was completed, crews used a 4-inch pipe to push the pilot tubes out of the ground. The 4-inch pipe was then left in place to hold the alignment. All the pilot tube installations were completed before pipe ramming commenced.

While the pilot tubes were installed from the middle pit out, pipe ramming went from the outside pits in. Nix crews placed auger tracks in the outside pits for pipe ramming platforms. In order to follow the path of the installed 4-inch pipe, an adapter was used to connect to a 20-inch casing that would be installed next through ramming. Crews rammed in one 40-foot section of 20-inch pipe at time while the 4-inch pipe was removed at the center pit. Once installed, another adapter was used to connect the 36-inch casing to the 20-inch casing and ramming continued.

Each installation was completed the same way.  The 36-inch casings had to travel over 370 feet and hit a 48-inch opening +/- 3 inch within that opening. The pilot tubes set the precise line and grade for each alignment that allowed each casing to arrive on target.

Seal said, “Ramming went smoothly. There were a couple times when we had to stop and clean out. Because of either swelling clay soil and because of the weight was just slowing us down. But it wasn’t very often. We worked at least a month and a half of 24-hour shifts, two 12-hour shifts per day, to get everything in place.”

Melvin said, “When it comes to pipe ramming, the Nix crews are some of the best in the country. The 24-inch Grundoram Taurus provide plenty of power for this project and Perry and his crews got the most out it on this project.”

The rails and freeway were continuously monitored for settlement as was the quality of the excavated soil, and the quality and quantity of groundwater. The dewatering system was designed during the construction phase of this project. Although the original design did not include dewatering, the risk of a problem in the rail yard made it cost beneficial. The dewatering system moved over 1 MGD of ground water.

Once the casings were installed and cleaned out, the 24-inch HOBAS pipes and HDPE carriers were installed, marking the end of Phase 1 of the relocation project.

Melvin said, “This was one of those projects that only a contractor like Nix Construction could pull off. So many considerations. Highly complex. The skill level requirement on this project was off the charts. And the Nix crews really brought it home. Great job!”

Safety First, Always!

Claude H. Nix Construction is a safety-centric company, and this project exemplified that safety forward culture. Nix-Thomas said, “We always strive to be accident free. And any incidents are utilized to improve our safety program and though unfortunate, they increase safety awareness. In general, our safety program is comprised of a monthly companywide safety meeting, daily hazard analyses, and weekly toolbox meetings.” The project in Salt Lake City tallied 43,782 labor hours not including subcontractors and engineers and only netted two reportable incidents (Incident rate = 7.19) and no lost time accidents.

Related equipment

  • GRUNDORAM® Pneumatic Pipe Ramming
Tags: Grundoram, GrundoRam Pipe Rammer, Pilot Tube Pipe Ramming, Pneumatic Pipe Ramming
https://www.tttechnologies.com/wp-content/uploads/2025/10/Photo2-Grundoram-in-action.jpg 640 853 TT Technologies https://www.tttechnologies.com/wp-content/uploads/2020/02/tt-technologies-logo-2020.png TT Technologies2025-10-23 16:27:532025-10-23 17:08:04The Pinnacle of Pilot Tube Pipe Ramming: Claude H. Nix Construction Achieves Pit Perfection and More!
You might also like
Baltazar crew starting to get pit ready for the day Utility Connections in Connecticut: Baltazar Contractors, Inc Proves Pipe Ramming Proficiency!
Grundoram ramming pipe Pipe Ramming Texas Style: Pumpco, Inc. Defeats Tough Soils in the Lone Star State
LTL using a Grundoram pipe ramming machine. Ramming in the Great White North: LTL Directional Drilling Conquers Cold Weather & Collapsed Culverts
Replace, Remove & Repeat: Directional Service South Pulls Off Pipe Extractions in Texas
Roadway Pipe Ram: Staggs Environmental Construction Handles Heavy Traffic
West Yost 1 Bursting in the Bay: Static Pipe Bursting Overcomes Difficult California Conditions

Search Articles

Search Search

Connect With Us

  • Facebook
  • Twitter
  • Youtube
  • Rss

Trenchless Leader

Each year more trenchless sewer, water, gas and electric rehabilitation and replacement projects are successfully completed with trenchless equipment from TT Technologies than any other. Read more →

Reach Us

TT Technologies, Inc.
2020 E New York Street
Aurora, IL 60502, USA

US. 1-800-533-2078
International. 1-630-851-8200
Email. info@tttechnologies.com

  • Sales Centers & Worldwide Distribution
Search Search

Connect With Us

  • Facebook
  • Twitter
  • Youtube
  • Rss

Trenchless Products

  • GRUNDOMAT® Horizontal Boring Tool
  • GRUNDORAM® Pneumatic Pipe Ramming
  • GRUNDOCRACK® Pneumatic Pipe Bursting
  • GRUNDOBURST® Static Pipe Bursting System
  • GRUNDOTUGGER® Lateral Pipe Bursting
  • GRUNDODRILL 5X® Compact Directional Drill
  • Cable & Pipe Pusher
  • GRUNDOPIT® Pit Launched HDD
  • GRUNDOSPLIT Pipe Splitting Tooling
  • GRUNDOWINCH® Constant Tension Winch
  • GRUNDOMUDD™ Bentonite Mixing & Delivery
  • GRUNDO-AIR® Air Compressor

Latest News

  • SKE Construction Photo 1
    SKE Construction’s Pre-chlorinated Pipe Bursting Program A Model of Efficiency!October 8, 2026 - 4:18 pm
  • Water Main Drawing Jobsite
    Distribution System Pipe Bursting: Good Practice BasicsSeptember 21, 2026 - 9:08 am
  • WESTT Photo 7
    Restoring a Critical Water Transmission Main in Southern California Using Pipe BurstingSeptember 14, 2026 - 2:37 pm
  • Lateral Bursting Photo1
    A Tale of Two Laterals: Pipe Bursting Takes Center StageJune 2, 2026 - 2:29 pm
Copyright © 2001 - TT Technologies, Inc. All Rights Reserved.
  • Terms and Conditions
  • Terms of Usage
  • Privacy Statement
  • Limited Warranty
  • Patents
  • Site Map
Link to: Lead Service Line Replacement: Veit Gets it Done with Pit-Launched HDD Link to: Lead Service Line Replacement: Veit Gets it Done with Pit-Launched HDD Lead Service Line Replacement: Veit Gets it Done with Pit-Launched HDDPhoto 2 Grundopit In Action Link to: Horizontal Boring Tools The Gas Industry’s Trenchless Workhorse Link to: Horizontal Boring Tools The Gas Industry’s Trenchless Workhorse Trenchless For Gas LaunchHorizontal Boring Tools The Gas Industry’s Trenchless Workhorse
Scroll to top Scroll to top Scroll to top